RESOLVED that: 1) Under the provisions of Regulation 19 of the Community Infrastructure Levy Regulations 2010 the Statement of Modifications be published for a period of four weeks to allow for public representations; 2) In accordance with Regulations the Revised Draft Charging Schedule, Regulation 123 List, supporting documentation and representations received together with the changes the Council would propose to make in light of those representations be submitted for examination; 3) The Corporate Director be authorised to appoint the examiner and if necessary, appoint other persons to assist the examiner; and 4) The Corporate Director in consultation with the Portfolio Holder for Leisure and Development be authorised to agree minor amendments to the revised draft documents in response to the consultation process.
Word for word from the decision Gedling published for this meeting.Source: democracy.gedling.gov.uk
(a) the proposed responses to the main issues raised in the comments received on the Revised Draft Charging Schedule (June 2014) and associated documentation; and
(b) the submission documents for examination which comprise the Revised Draft Charging Schedule (June 2014), the Proposed Statement of Modifications (dated for submission January 2015), and supporting documents.
Key Decision
This is a Key Decision.
Background
1. The Community Infrastructure Levy is a charge levied on new buildings and extensions to buildings according to their floor area and the money raised from the development helps to pay for the infrastructure to ensure the Borough grows sustainably.
2. The intention is for Community Infrastructure Levy and planning obligations to play complementary roles. Community Infrastructure Levy will provide infrastructure to support the development of an area. The levy cannot be expected to pay for all of the infrastructure required but it is expected to make a significant contribution. S.106 obligations will provide site specific impact mitigation to make individual developments acceptable in planning terms and to provide affordable housing.
3. Appendix A “Community Infrastructure Levy and Section 106 Statement” provides a
Further information on the subject of this report is available from Alison Gibson Planning Policy Manager on (0115) 901 3733 more detailed explanation of how the two systems will operate.
4. The Borough Council has adopted a protocol for addressing cross boundary impacts of new development. This document sets out the principles guiding how Gedling Borough will work with its neighbouring authorities and the County Council when dealing with section 106 planning obligations relating to development which would have an impact on the services and facilities in a neighbouring authority.
5. The Levy takes effect through a Charging Schedule which sets out the rate or rates of charge. The first public stage in preparing this document was the Preliminary Draft Charging Schedule and consultation took place in the autumn of 2012.
6. The Charging Schedule relies on two important pieces of evidence – infrastructure planning and a viability assessment of the impact of the proposed rate of Community Infrastructure Levy on development in the Borough Council’s area. The Infrastructure Development Plan sets out the range of infrastructure required to support the Aligned Core Strategies. The viability assessment must show that the proposed rate of Community Infrastructure Levy can be borne by most development without making the project commercially unviable.
Consultation Responses to the Draft Charging Schedule and Revised Draft Charging Schedule
7. The Draft Charging Schedule was originally issued for consultation in October 2013 and the key issues raised were reported to Cabinet. However, following the conclusion of this consultation there were significant changes in circumstances with further amendments to the Community Infrastructure Levy Regulations 2010 which came in force in February 2014. In combination with the review of the distribution of housing supply in the Aligned Core Strategy it was concluded that it would be appropriate to review the Draft Charging Schedule and a Revised Draft Charging Schedule was issued for a further round of consultation. The comments received on the original Draft Charging Schedule were therefore superseded by the review. The six week consultation on the Revised Draft Charging Schedule concluded in September 2014, with 22 respondents making over 120 comments.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.