RESOLVED to: 1) Note progress with delivery of the Sustainability Strategy and Action Plan; 2) Agree that future work on sustainability is encompassed in the Gedling Plan and relevant Service Plans, with any continuing high-level targets incorporated in the Gedling Plan; and 3) Manage future sustainability performance through established performance management mechanisms, with any target changes to be put forward for member consideration through quarterly performance review processes.
Word for word from the decision Gedling published for this meeting.Source: democracy.gedling.gov.uk
• To report back to members on progress with delivery of the Sustainability Strategy and Action Plan • To set out outline plans for the review and update of the Action Plan.
Key Decision
This is not a key decision.
Background
1. Cabinet adopted a Sustainability Strategy and Action Plan in January 2013.
2. The Strategy set out the Council’s high level goals and aims for sustainability against five themes, specifically: -
• Energy • Transport • Waste • Biodiversity • Resilience and Behaviour Change
3. Of these, energy was acknowledged to be the central theme around which other themes would be anchored, given the impact energy has on climate change and adaptation, the need to contribute to future energy security and the wider economic imperatives resulting from increasing energy costs.
4. The strategy also included a series of eight high-level outcome targets, progress towards which is the subject of this report.
5. Attached to the strategy was an Action Plan, setting out a range of actions against the five priority themes.
6. Progress towards these actions is being managed through the Council’s established performance management framework and is therefore not covered in detail here. Examples of actions delivered include: - • Solar Photo Voltaic panels installed at Richard Herrod Leisure Centre also attracting a 25 year Feed in Tariff • LED lighting installed in Arnot Hill House • Planning permission granted for a 5.5mW solar farm at Gedling Country Park • 63 boilers replaced and installed 15 new heating systems installed in fuel poor households in the borough • Voltage optimisation unit installed at the Civic Centre • Energy efficient lighting installed as part of upgrade at Bonington Theatre and Arnold Leisure Centre • Energy efficient lighting and new pool covers and new boiler installed at Calverton leisure centre • The Council’s first all-electric vehicle acquired and in use • 2 electric vehicle charging points installed at Jubilee House and the new car park in Arnold (former Druids pub site) • New staff Travel Plan adopted • 51 employees trained in smarter driving techniques • Electric lifts installed on 4 bin lorries • Maintained recycling levels without further major waste streams • Piloted a wood waste collection service • Signed up to Climate Local
Summary of Progress and Proposal
7. Progress towards the eight high-level outcome targets is attached at Appendix A. All of the targets cover a five-year period.
8. Members will note that good progress is being made in the majority of areas. Targets are being met or exceeded with regard to reduced energy use; reduced carbon emissions from the Council’s estate; generation of renewable energy; use of more environmentally friendly vehicles and reduced business mileage.
9. Gas and electricity consumption has reduced, contributing to a 3% reduction in carbon emissions from the Council’s estate. 9% of the total electricity used by the Council was generated by the solar panel installations at Richard Herrod Leisure Centre; Civic Centre and Jubilee House. This has contributed to an overall cost saving of 3% on electricity, against a backdrop of a 10% electricity price increase.
10. It has not proved possible to accurately record overall carbon emissions from the Borough and it is proposed that this measure is dropped in favour of a measure to reflect the Borough Council’s overall carbon emissions (not just that from its own estate). Changes to the way that domestic renewable energy installations are treated by the planning system mean it has not been possible to gather date against that measure – this measure will therefore be dropped for the future.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.