1) To agree that the Gedling Community Infrastructure Levy Charging Schedule, as attached as AppendixB to the report, is submitted to Full Council for approval and that it should come into effect on 16 October 2015; 2) To recommend to that Council delegates authority to the Corporate Director and the Chairman of Planning Committee to make any minor changes (e.g. typing errors, formatting and images) necessary prior to publication (such changes will not alter the content of Appendix B): and 3) That subject to Council approval of the Community Infrastructure Levy Charging Schedule, agree that the Exceptional Circumstances Relief for CIL , as attached at Appendix C to the report, shall be offered and that the Corporate Director, in consultation with the relevant Portfolio Holder, be authorised to determine any applications for such relief
Word for word from the decision Gedling published for this meeting.Source: democracy.gedling.gov.uk
Purpose To request that Council adopt and subsequently implement the Gedling Borough Community Infrastructure Levy Charging Schedule as supported by the findings of the independent examination into the submission of the Revised Draft Charging Schedule.
Key Decision This is a key decision because it is likely to be significant in terms of its effect on communities living or working in an area comprising two or more wards of the Borough.
Background
1. The Community Infrastructure Levy is a charge levied on new buildings and extensions to buildings according to their floor area and the money raised from the development helps to pay for the infrastructure to ensure the Borough grows sustainably.
2. In setting the Community Infrastructure Levy rate the Borough Council has aimed to strike an appropriate balance between:- The desirability of funding from Community Infrastructure Levy (in whole or part) the actual and expected estimated total cost of infrastructure required to support the development of its area; and The potential effects of the imposition of Community Infrastructure Levy on the economic viability of development across its area.
Proposal
3. The submission of the Gedling Borough Revised Draft Charging Schedule to the Secretary of State comprised the start of the examination process by the appointed Planning Inspector. This examination took place on 3rd March 2015. Following this hearing session, the Inspector requested that the Council review the calculation of commercial Community Infrastructure Levy income; update the viability appraisal of the North of Papplewick Lane development site and supply a plan for the Gedling Colliery / Chase Farm development site.
4. These were provided to the Inspector and were consulted on between 9th and 23rd March 2015. One consultation response was received and the Borough Council’s own response to this was forwarded to the Inspector.
5. The Inspector issued her report on 14th May 2015 and a copy is attached as Appendix A. The report concludes that the “Gedling Borough Council Revised Draft Community Infrastructure Levy Charging Schedule provides an appropriate basis for the collection of the levy in the Borough. The Council has sufficient evidence to support the schedule and can show that the levy is set at a level that will not put the overall development of the area at risk.” The Inspector considered that the Borough Council had been realistic in terms of achieving a reasonable level of income to address an acknowledged gap in infrastructure funding, whilst ensuring that a range of development remains viable across Gedling Borough. The Inspector concluded that the Gedling Borough Council Revised Draft Community Infrastructure Levy Charging Schedule satisfies the requirements of section 212 of the Planning Act 2008 and meets the criteria for viability in the 2010 Regulations (as amended).
6. The charges and zones of the Gedling Borough Community Infrastructure Levy Charging Schedule as endorsed by the Inspector is attached as Appendix B. The charging rates as supported by the Inspector include differential charging rates for residential development, based on three geographical areas: zone 1 at £0 per square metre (sqm), zone 2 at £45 per sqm and zone 3 at £70 per sqm; and a Borough wide charge of £60 per sqm for retail developments. A zero rate will apply to all other uses.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies