Joint Consultative and Safety Committee noted this item on Tuesday 25 August 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
To note the report.
Report to Joint Consultative and Safety Committee
Subject: Current staffing issues (Standing Item)
Date: 25 August 2015
Author: Chief Executive Service Manager; Organisational Development
1. Purpose of the Report This is an information item highlighting to the Committee, any issues of particular interest that relate to the council’s workforce.
2. Summary of current issues The summer months see much activity in respect to employee-related projects and events all of which are extremely positive.
2.1As reported at the last JCSC, during March a survey was conducted across the whole workforce to find out about how our Performance and Development Review (PDR) scheme was working. The survey was produced in electronic format for those employees with and email address and ready access to a computer and in paper format for all other employees.
The survey showed that although the PDR system was being carried out well in most areas, there were “pockets” in the organisation where either PDRs weren’t being regularly conducted or if they were, the quality seemed to be poor.
As a result of this feedback Senior Leadership Team (SLT) considered a number of recommendations for change, one of which was to improve clarity about the period within which all PDRs will be carried out annually (April to June). This has now resulted in a PDR completion rate of almost 99%.
2.2A general employee survey takes place every two years with this year being a “survey year”. Forms have been issued to each employee personally either through email contact or as a paper-based version attached to payslips. Although too early to report findings, the response rate has again been extremely good which gives confidence that the results will be meaningful and changes that may be made as a result of the survey will reflect the comments of a high proportion of employees.
A summary of findings will be reported back to a future meeting of the JCSC together with proposed actions for improvement and change.
2.3The collaboration arrangements between Gedling, Newark and Sherwood, and Rushcliffe Borough Councils continue to work well in relation to the shared Masters of Public Administration programme. A joint event took place on 27 July to showcase the opportunity to employees of the three councils and to ascertain interest for participation in the second cohort of this three-year programme. From this event sufficient numbers have come forward across the three councils to run a second cohort of this programme.
The first cohort, one year into their three years, recently gave presentations to the Senior Leadership Team and Service Managers designed to give an insight into their personal and professional development resulting from the programme.
2.4At the last JCSC it was reported that the Chief Executive has been charged with conducting a review of the management arrangements for the Council and to bring forward proposals for improved ways of working and structural change.
It is now anticipated that an initial proposal will be brought to this committee in November to commence formal consultation. It is our practice to consult on major proposals over a 30-day period at the end of which time a final report would be brought back to this committee to ask that recommendations be made which will then be considered by the Appointments and Conditions of Service Committee prior to implementation.
The consultancy work conducted by the Hay Group running alongside the staffing review is still ongoing. Most recently interviews have been held with Service Managers to better understand the nature of their post and those within their team. Work has also been undertaken with Senior Leadership Team to help identify “job families” that might be considered when looking at pay grouping.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Current Staffing IssuesReport | 100 KB | DownloadRead as text |
Follow Joint Consultative and Safety Committee at Gedling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Aug 2026 | To approve, as a correct record, the minutes of the meeting held on 14 April 2026That the minutes of the above meeting, having been circulated, be deferred until the next available committee. | Deferred | Open |
| 25 Aug 2026 | Building Control Audit and Service UpdateRESOLVED to: 1) Note the contents of the report. | Noted | Open |
| 25 Aug 2026 | Annual Health and Safety report 2025/26RESOLVED to: 1) Agree the Corporate Health and Safety Annual Report 2025/26. | Agreed | Open |
| 25 Aug 2026 | Proposed Changes to Contracts of EmploymentRESOLVED that: The Joint Consultative and Safety Committee to considered feedback on the contract changes which inclu... | Decided | Open |
| 14 Apr 2026 | To approve, as a correct record, the minutes of the meetings held on 26 August 2025 and 17 February 2026That the minutes of the above meetings, having been circulated, be approved as a correct record. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.