RESOLVED to 1) Authorise the Council to hold the grant monies and to distribute them in accordance with the successful ERASMUS + bid; 2) Authorise the Council to enter into contracts with European and Canadian partner organisations to deliver the programme contracts and ensure that the money is spent in accordance with the ERASMUS + grant agreement; and 3) Establish by virement the income and expenditure budgets for GBC’s share of the grant received from the European Union for the ERASMUS + programme as detailed in paragraph 4 of the report.
Word for word from the decision Gedling published for this meeting.Source: democracy.gedling.gov.uk
Following consultation with the Leader of the Council (decision ref D304 refers), the Council submitted a funding bid in March 2015 to the EU’s Erasmus+ programme to support development of apprenticeships in Small and Medium Sized Enterprises (SMEs). The Council is the lead coordinator/partner, working with partner organisations in the UK, Poland, Germany, Bulgaria and Canada. This is the first time the Council has bid for direct EU funds.
The project will involve learning from best practice in the area of SMEs employing apprentices in other parts of Europe and then sharing and practicing that good practice locally in year 2 and beyond, with the aim of improvements being self-sustaining once project funding ends. The main outcome will be more SMEs taking on apprentices - across the partnership the aim is for 270 SMEs to take on an apprentice over the three year programme, 90 of whom would be in the UK. There is a very strong fit with the Council’s priorities around youth unemployment and deprivation, its aspirations to help develop small businesses, and to improve the skills of our younger residents
Notification was received at the end of June that the bid had been successful. A maximum amount of €373,553 (£273,500 approximately based on current exchange rates) has been awarded to the partnership. This is less than the €433,207 (£320,500) bid for but still represents a major success for the Borough. It is however expected all the outputs and outcomes set out in the bid are delivered. The project will run for three years from 1 September 2015.
The funding will be paid to the Borough Council in three instalments of 40%, up to 40% and up to 20% respectively. The first payment will be made in advance; the second midway through the project and the final payment paid in arrears at the conclusion of the project. Conditions around outcomes being delivered to time are attached to the release of the second and third payments. The EU’s agency can reclaim funds if outputs are not secured and progress reports not submitted accurately and in a timely way.
As lead partner, the Council will need to enter into separate contractual agreements with each of the partner agencies and release appropriate proportions of the funds made available for partners to deliver the project. The Council will monitor the performance of each contractor against the outputs and outcomes required.
Since July, further negotiations have taken place with the EU agency managing the project and contracts between the Council and the agency have been signed.
This report seeks formal approval to enter into partnerships and funding agreements with partner organisations and for establishment of the associated budgets to allow the Council to progress is role as the lead partner for implementation of the programme.
2. Proposal and Risk Assessment
The Council’s financial regulations specify the key controls and responsibilities that govern the management of partnership arrangements and specifically requires a risk management appraisal to be prepared before entering into agreements with external bodies. Accordingly a risk appraisal of the proposed partnership for delivery of the ERASMUS + programme has been completed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.