That the Service Manager, Development Services be authorised to serve a Breach of Condition Enforcement Notice requiring the developer to complete the development in accordance with the approved plans and conditions, and issue any necessary enforcement proceedings through the courts, in conjunction with the Director of Organisational Development & Democratic Services.
Word for word from the decision Gedling published for this meeting.Source: democracy.gedling.gov.uk
1.1On the 8th June 2006 planning permission was granted to erect 12 apartments on land now known as Fletton Court, The Old Brickyard, Carlton, subject to a number of conditions.
1.2The conditions included;
Condition 7 – “the proposed boundary treatments shall be implemented before the development hereby permitted is first occupied and shall thereafter be retained unless alternative means of enclosure are agreed in writing by the Borough Council”.
Condition 8 - “the approved landscaping scheme shall be carried out in the first planting season following the substantial completion of the development and any planting material which becomes diseased or dies within five years of the completion of the development shall be replaced in the next planting season by the applicants or their successors in title”.
Condition 9 – “the proposed cycle stores shall be provided before any of the apartments are first occupied and shall thereafter remain available for the storage of cycles at all times”.
Condition 10 – “the proposed parking spaces shall be provided before any of the apartments are first occupied and shall thereafter remain available for the parking of cars at all times”.
Condition 11 – Development shall not begin until a scheme to deal with contamination of the site has been submitted to and approved in writing by the Borough Council as the local planning authority. The scheme shall include an investigation and assessment to identify the extent of the contamination and the measures to be taken to avoid risk to the public and buildings when the site is developed.
Condition 12 – No individual unit shall be occupied until the measures approved in the scheme have been implemented and the measures required shall be monitored and certified as being in compliance with the approved scheme by a firm of consulting engineers who shall carry suitable and sufficient professional indemnity insurance and whose appointment has been previously agreed in writing by the Borough Council’s Head of Planning. The consultant’s certificate shall be given to the developer and to the Council and in so certifying the consultants shall confirm that they owe a duty of care to both parties.
1.3Although details to discharge conditions 7 – 10 were submitted in October 2008 and approved by the Council on 21st January 2009, the agreed works have never been carried out. In addition, conditions 11 and 12 also remain outstanding as insufficient details were submitted to enable officers to discharge condition 11 and the Council has not been advised of any measures implemented in relation to the possible contamination identified on the site as required by condition 12.
1.4Recent visits to the site have shown that old furniture and waste has been dumped in the car parking area and a builder’s compound containing bricks and other items remains on the site.
1.5Letters have been sent to the developer requesting that they comply with the conditions and finish off the development as approved but the requests have been ignored.
1.6In May 2016, there was a meeting between Council officers and the developer. At the meeting the developer advised officers that they considered it ‘a waste to dig up the existing concrete and then tarmac the car park and plant the trees and shrubs for the soft landscaping’. The developer was advised that they needed to apply to vary the conditions and submit an amended landscaping plan if they no longer wished to comply with the existing conditions and the approved plan.
1.7Despite the negative response, the developer agreed at the meeting that they would clear the furniture and waste dumped on the site together with the fenced compound and the bricks left on the site. However, to date none of this work has been carried out and the Council has not received an application to vary the conditions.
2 ASSESSMENT
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.