CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Gedling Borough Council
Planning Committee, Wednesday 19 July 2017 at 6.00pm

Appllication No. 2017/0581 Gedling Country Park Visitor Centre Spring Lane Gedling

Agreed Planning 1 paper

Planning Committee agreed this item on Wednesday 19 July 2017. Below is the council's own wording, with the papers it was decided on.

Item39

Resolved

RESOLVED to Grant Conditional Planning Permission Conditions 1. The development hereby permitted shall be carried out in accordance with the following plans received by the Local Planning Authority on 8th May 2017; Site Location Plan Drawing No. 3100/17, Block Plan Drawing No. 3100/18, Landscape Strategy Drawing No. 1016/001 Rev A, Landscape Softworks West Drawing No. 1016/003 Rev D, Landscape Softworks East Drawing No.1016/004 Rev D, Landscape Softworks South Drawing No. 1016/005 Rev D which form part of this permission, unless otherwise agreed in writing by the Local Planning Authority. 2. The parking, turning and servicing areas are to be provided in accordance with the hereby approved plan; Block Plan Drawing No. 3100/18. The parking, turning and servicing areas shall not be used for any purpose other than parking, turning, loading and unloading of vehicles, and shall be retained for the lifetime of the development, unless otherwise agreed in writing by the Local Planning Authority. Reasons 1. For the avoidance of doubt and to define the terms of this permission. 2. In the interests of highway safety. Notes to Applicant Planning Statement - The Borough Council has worked positively and proactively with the applicant in accordance with paragraphs 186 to 187 of the National Planning Policy Framework. During the processing of the application there were no problems for which the Local Planning Authority had to seek a solution in relation to this application. The applicant is advised that all planning permissions granted on or after 16th October 2015 may be subject to the Community Infrastructure Levy (CIL). Full details of CIL are available on the Council's website. The proposed development has been assessed and it is the Council's view that CIL is not payable on the development hereby approved as the development type proposed is zero rated in this location. Air Quality Electric Vehicle (EV) Charging Infrastructure The applicant's attention is drawn to an informal planning guidance document which has been produced to try and define what sustainable development means in the context of air quality, and how we might help decrease levels by incorporating mitigation measures into scheme design as standard.(See http://www.gedling.gov.uk/planningbuildingcontrol/planningpolicy/emerginglocalplan/supplementaryplanningdocuments/)We would also ask therefore, that the applicant considers the commitment to incorporate provision for an EV (electric vehicle) charging point(s); to allow those accessing the facilities to charge electric/plug-in hybrid vehicles. Reference can be made to guidance produced by IET Code of Practice for EV Charging Equipment Installation for details of charging points and plugs specifications.
Word for word from the decision Gedling published for this meeting. Source: democracy.gedling.gov.uk

Follow this further

Built from Gedling's papers

What the report saysPro

Report to Planning Committee

Planning Report for 2017/0581 Report to Planning Committee

Application Number: 2017/0581

Location: Gedling Country Park Spring Lane Gedling Nottinghamshire

Proposal: Retention of new 36 space car park to replace provision previously approved as part of application 2016/0788.

Applicant: Gedling Borough Council

Agent: Allan Joyce Architects Ltd

Case Officer: Amy Cockayne

The applicant is Gedling Borough Council and therefore, in line with the Council’s Constitution, this application has been referred to Planning Committee.

Site Description

The application site relates to Gedling Country Park, which covers an area of approximately 110 hectares. Vehicular access to the existing car parking area within the Country Park is via Spring Lane to the north of the site; from this access the Visitors’ Centre is clearly visible.

The Park is located within an area identified for the protection of open space in the Gedling Borough Replacement Local Plan (Certain Policies Saved 2014); as well as Policy LPD 20 of the Gedling Local Plan Document (Part 2) Publication Draft published in May 2016.

The nearest residential properties are located to the north of the site along Spring Lane.

Proposed Development

The application seeks permission for the retention of a 36 space car park to replace provision previously approved as part of the original application for the Visitors’ Centre ref. 2016/0788. A coach turning facility will be created at the entrance of the previously approved car park. The new car park was constructed to the west of the existing car parks and accessed via Spring Lane. It is noted that the works for the creation of the proposed car park were substantially complete as of March 2017.

The hardstanding of the car park is limestone, and the boundary of the car park is delineated by a timber knee rail fence approximately 0.5m in height.

Consultations

A Site Notice was posted, and nearby residents were notified via letter. One letter of representation was made, comments include;  This is a retrospective application as carpark has already been built  Support the position of the proposed carpark as previously objected to the original position of the carpark  Volunteers have been informing the public that the original carpark would be used as a coach park and a butterfly bank would be created in the original position

Nottinghamshire County Council’s Nature Conservation Team was notified; it has been advised that there are no comments to be made in relation to this application.

Nottinghamshire County Council’s Landscape Team were notified; as of 4th July 2017 no comments have been received.

Nottinghamshire County Council (Highways Authority) were notified, and has advised that there are no objections in principle to the alternative location of the carpark as it has no highway related implications. A condition is recommended to be attached if the application is recommendation of approval for parking, turning and servicing areas to be provided in accordance with the submitted plan.

The Borough Council’s Parks and Street Care Service were notified and have raised no objection.

The Borough Council’s Public Protection Service was notified and has advised that an informative relating to Air Quality Electric Vehicle Charging Infrastructure should be included on any decision notice should approval be given.

Planning Considerations

The main planning considerations in the determination of this application are the impact upon the recreational purposes and quality of the public open space, the potential impact on the character and appearance of the locality, and the impact upon the residential amenity of neighbouring dwellings.

The application site is part of the Gedling Colliery Park (Policy ENV44) as identified on the Proposals Map of the Gedling Borough Replacement Local Plan (2005).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appllication No. 2017/0581 Gedling Country Park Visitor Centre Spring Lane GedlingReport 823 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 22 attended
JT
Councillor John TruscottChair, present
BM
Councillor Barbara MillerVice-Chair, present
MA
Councillor Michael AdamsCommittee Member, present
PA
Councillor Pauline AllanCommittee Member, present
CB
Councillor Chris BarnfatherCommittee Member, apologies
AB
Councillor Alan BexonCommittee Member, present
BC
Councillor Bob CollisCommittee Member, present
KD
Councillor Kevin DoyleCommittee Member, apologies
DE
Councillor David EllisCommittee Member, present
GG
Councillor Gary GregoryCommittee Member, present
ML
Councillor Meredith LawrenceCommittee Member, present
MP
Councillor Marje PalingCommittee Member, present

All 22 on the meeting page

More from Gedling Planning Committee

All decisions
MeetingDecisionOutcome
14 Oct 2026 To approve, as a correct record, the minutes of the meeting held on 9 September 2026That the minutes of the above meeting, having been circulated, be approved as a correct record. Approved Open
14 Oct 2026 Application no. 2026/0501 - Richard Herrod Centre, Foxhill Road Central, Carlton, NottinghamshireTo Grant Planning Permission: Subject to the conditions listed for the reasons set out in the report. Conditions The ... Approved Open
14 Oct 2026 Appeal Summary Ref: 6014560 - 31 Mansfield Road, Daybrook, NottinghamshireTo note the information. Noted Open
14 Oct 2026 Appeal Summary Ref: 6013777 - 6 Pateley Road, Woodthorpe, NottinghamshireTo note the information. Noted Open
14 Oct 2026 Future planning applicationsTo note the information. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies