Resolved
RESOLVED to: 1) Support the proposed modifications to Eagle Square; and 2) Note the intention to accept the winning tender for the works subject to this falling within the estimated cost.
Cabinet noted this item on Thursday 7 September 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to: 1) Support the proposed modifications to Eagle Square; and 2) Note the intention to accept the winning tender for the works subject to this falling within the estimated cost.
Ernhale
Purpose
To seek Cabinet support for works to Eagle Square which will provide flexibility for events space and to report the outcome of public consultation on the proposals.
Key Decision
This is not a key decision.
Eagle Square, located at the southern tip of Arnold Town Centre, was the focus for the Christmas Light switch on in 2016. Although this event was successful, the physical layout of the space and presence of the brick planter restricted full use of the area.
To build on the success of last year’s event and improve the image and offer of the town centre, officers have reviewed the current limitations of the square and considered whether simple modifications could be made to improve its appearance and function.
Proposal
Colleagues in Parks and Street Care (PASC) have undertaken preliminary surveys and commissioned concept designs for a scheme which is anticipated to:
increase pedestrian accessibility;
increase the visibility of existing retail units; improve the functionality of Eagle Square particularly with regard to the Christmas Lights event; and
enhance the general attractiveness and vibrancy of the town centre.
An indicative scheme of works showing removal of the planter is shown at appendix 1. In summary the scheme includes:
Removal of brick planter, shrubbery and trees within the planter;
Simple repaving in matching blockwork across the area to provide an extended space for events;
Introduction of removable wooden planters with appropriate tree species to attractively enclose the space and act as vehicular barriers and new smaller planter with street tree;
Regrading to remove differences in level (as far as can be achieved across the site); and
Provision of circular seating with removable elements to provide an appropriate location for the Christmas tree and additional seating near High Street.
The scope of the scheme is relatively modest and is aimed to improve the flexibility of the space in the short term. Funding opportunities for more comprehensive improvements for both Arnold and Carlton centres are currently being explored.
A large scale plan of the proposed works will be circulated at the meeting. The cost of the work is estimated to be approximately £85,000 - £90,000 including removal and disposal of soil and rubble off site.
Technical Consultation
As the land is designated as highway, PASC have liaised with Nottinghamshire County Council about the improvements and they are supportive. The County Council will require an update as to when the works will be carried out so they can display the necessary highways notifications and ensure that no bookings are taking for this area during the term of the works.
PASC have liaised with Development Management to ensure there are no TPOs on the trees to be removed and that environmental and planning regulations are adhered to (planning permission is not required as the work is regarded as permitted development).
Utilities and plans have been reviewed and no obstructions to the improvement works have been identified.
Public Consultation
Retailers within Arnold Town Centre have been invited to share their views on the proposal by either:
reviewing proposals online and completing an online survey;
meeting officers to discuss proposals at consultation sessions held at the Bonnington Theatre; or
directly contacting the Economic Growth Team
Consultation has also taken place via ‘Keep Me Posted’ alerts with information available on the Council’s website. Respondents were also invited to share their views on Arnold Town Centre more generally.
The online questionnaire resulted in 341 responses from businesses and residents with 67% of businesses and 54% of residents in support of the planed works.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Eagle Square ImprovementsReport | 106 KB | DownloadRead as text |
PDF |
Enc. 1 for Eagle Square ImprovementsReport | 2.3 MB | Download |
PDF |
Enc. 2 for Eagle Square ImprovementsReport | 59 KB | Download |
Follow Cabinet at Gedling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | To approve, as a correct record, the minutes of the meeting held on 25.06.26.That the minutes of the above meeting, having been circulated, be approved as a correct record. | Approved | Open |
| 16 Jul 2026 | Forward Plan1) To note the report. | Noted | Open |
| 16 Jul 2026 | Housing Strategy 2026-2030That Cabinet: 1) Noted the representations and comments received during the public consultation, together with the of... | Noted | Open |
| 16 Jul 2026 | Gedling BC Asset Management Plan 2026-2028THAT Cabinet: 1) Agreed to adopt the Asset Management Strategy 2026-2028 at appendix 1. 2) Approved the proposals for... | Agreed | Open |
| 16 Jul 2026 | Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.