Resolved
RESOLVED to: 1) Approve the General Fund Budget virements set out in Appendix 1 to the report; and 2) Note the use of reserves and funds during quarter one as detailed in Appendix 2 to the report.
Cabinet approved this item on Thursday 6 August 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to: 1) Approve the General Fund Budget virements set out in Appendix 1 to the report; and 2) Note the use of reserves and funds during quarter one as detailed in Appendix 2 to the report.
Borough-wide
Purpose
To update Cabinet on the forecast outturn for Revenue and Capital Budgets for 2020/21. The budgets include all approved carried forward amounts from the 2019/20 financial year. To request approval from Cabinet for the changes to the budget as set out in this report.
Key Decision
This is a key decision.
Recommendation(s)
Members are recommended to:
1) approve the General Fund Budget virements set out in Appendix 1;
2) note the use of reserves and funds during quarter one as detailed in Appendix 2.
1.1The Council has made a commitment to closely align budget and performance management. This is in line with accepted good practice.
1.2To deliver this commitment, systems to monitor performance against revenue and capital budgets, improvement activity and performance indicators have all been brought together and are now embedded in the way the Council works. Whilst the budget and performance information is presented in 2 separate reports, they are reported to Cabinet together and will appear on the same agenda. 2. Proposal
2.1General Fund Revenue Budget Summary
The following table summarises the overall financial position of the General Fund Revenue Budget and the expected total spend for the year. This information has been compiled using the best information made available to Financial Services by the relevant spending officers as at 30 June 2020. The Council’s General Fund outturn is projected to be overspent by £420,600 and this is primarily due the budgetary implications arising from the Covid-19 pandemic as detailed in paragraph 2.2.
Due to the significant uncertainties surrounding the ongoing and full impact of the Covid-19 pandemic, and to ensure Cabinet’s budget is maintained within its maximum, it is proposed that Cabinet approve a transfer of £420,600 from earmarked reserves, including: the Leisure Strategy Reserve £237,000; the Efficiency and Innovation Reserve £100,000; and the Transformation Reserve £83,600. These reserves have been reviewed and are confirmed as available for application as proposed. The impact of Covid-19 will continue to be closely monitored throughout the year and further adjustments may be recommended in order to maintain a balanced budget and appropriate allocation of resources. A review of the Council’s Medium Term Financial plan considering the impact of the Covid-19 pandemic on the resources available for the continued delivery of the Gedling Plan will be presented to Cabinet in the near future.
General Fund Revenue Budget 2020/21 – Change Analysis
£
Net Council Budget for 2020-21 approved by Council 11,602,700 on 5 March 2020 and Cabinet’s Maximum Budget is:
Up to the end of June 2020 expenditure less income 1,892,200 totalled In the remaining 9 months of year we expect net 10,131,000 expenditure to be Total net revenue spend for the year is currently 12,023,300 expected to be
Total Projected Revenue (Under) / Overspend 2020/21 420,600 Proposed Transfer From Earmarked Reserves For Approval (420,600) Total net revenue spend for the year is expected to be 11,602,700 Appendix 1 outlines how the General Fund Revenue budget is divided between the Portfolios of the Council and includes a detailed variance analysis identifying the current proposed changes for quarter one against the approved budget for each Portfolio area. Cabinet is recommended to approve these changes.
The major variances detailed in Appendix 1 include:
Expenditure:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Varaince Analysis: RQBCAppendix 1 | 100 KB | Download |
PDF |
VirementsAppendix 2 | 430 KB | Download |
PDF |
Capital Programme2Appendix 3 | 37 KB | Download |
PDF |
Quarterly (Q1) budget monitoring and virement reportReport | 652 KB | DownloadRead as text |
Follow Cabinet at Gedling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | To approve, as a correct record, the minutes of the meeting held on 25.06.26.That the minutes of the above meeting, having been circulated, be approved as a correct record. | Approved | Open |
| 16 Jul 2026 | Forward Plan1) To note the report. | Noted | Open |
| 16 Jul 2026 | Housing Strategy 2026-2030That Cabinet: 1) Noted the representations and comments received during the public consultation, together with the of... | Noted | Open |
| 16 Jul 2026 | Gedling BC Asset Management Plan 2026-2028THAT Cabinet: 1) Agreed to adopt the Asset Management Strategy 2026-2028 at appendix 1. 2) Approved the proposals for... | Agreed | Open |
| 16 Jul 2026 | Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.