RESOLVED to: 1) Note the progress against Improvement Actions and Performance Indicators in the 2020-23 Gedling Plan for the end of 2020/21 quarter 2; and 2) Approve the amendment to the performance indicator as set out in paragraph 2.7 of the report.
Word for word from the decision Gedling published for this meeting.Source: democracy.gedling.gov.uk
To inform Cabinet in summary of the position against Improvement Actions and Performance Indicators in the 2020-23 Gedling Plan at the end of 2020/21 quarter 2.
Key Decision
This is not a key decision.
Recommendation
THAT:
1. The progress against the Improvement Actions and Performance Indicators in the 2020-23 Gedling Plan for the end of 2020/21 quarter 2 be noted; and
2. The amendment to the performance indicator as set out in paragraph 2.7 be approved.
Background
1.1The Council has made a commitment to closely align budget and performance management. This is in line with accepted good practice.
1.2To deliver this commitment, systems to monitor performance against revenue and capital budgets, improvement activity and performance indicators have all been brought together and are now embedded in the way the Council works. Whilst the budget and performance information are presented in two separate reports, they are and will be reported to Cabinet together and will appear on the same agenda. 1.3 In addition, performance reports now focus more directly on the Council’s priorities and offer an “early warning” system of instances where targets may not be secured.
1.4As usual, comprehensive details about current performance against the Gedling Plan can be accessed through the following link on the Council's website:-
Members are recommended to view this document which provides valuable background detail to this summary paper. It provides a more in-depth review of indicators, actions and outcomes for 2020/21 quarter 2.
1.5A full set of papers that appear on the website have been printed and these reports are available in the Members’ Room. They contain explanations of variances from expected performance together with trend arrows for all the performance indicators within the Gedling Plan (note that an upward arrow indicates improved performance, irrespective of whether improvement is represented by a higher or lower value) and progress bars for all Gedling Plan actions showing progress made against project milestones.
1.6The assessment criteria used for actions and indicators is based on red, amber and green traffic light symbols. To be assessed as green performance indicators must be in line with their expected performance at this stage of the year, whilst actions must be on target against the “completed” or “in progress” milestones determined within the performance management system, Pentana.
2 Proposal
2.1It is proposed that Cabinet note the performance information for the Gedling Plan 2020-23 at the end of 2020/21 quarter 2 as set out below.
2.2Overall Performance
Overall performance at quarter 2 of 2020/21 against the Gedling Plan actions and indicators shows the following: Actions
2.3At this stage the 96 actions included in the Gedling Plan 2020-23, four are complete, the rest are either in progress or assigned to an Officer. Members will be aware that a number of actions are due to be delivered across the 3 years of the Plan, some are expected to be started and completed in year 1, whereas other actions are not due to commence until years 2 and 3. It must be noted that the data in this report refers to quarter 2 of 2020/21 and it is expected that the actions identified for the year will be met. Members will recall that, following review of the Gedling Plan in light of Covid-19, only two actions which were due to be started and completed in year 1 will not be achieved and these have been re-profiled for commencement in year 1 but completion in year 2.
Indicators
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.