That the Head of Development and Place, in conjunction with the Head of Governance and Customer Services, be authorised to take all relevant planning enforcement action including the service of any necessary enforcement notices and issue of proceedings through the courts, if required, to ensure the cessation of the unauthorised change of use of the site as an events venue and removal of all associated structures and facilities including 2 no. joined tipi tents, wooden framed stage, trailer mounted timber cabin, WC trailer, seating, tables and wooden archway.
Word for word from the decision Gedling published for this meeting.Source: democracy.gedling.gov.uk
1.1In August 2020, the Council received a complaint alleging the site was being used for events without planning permission with associated buildings having been constructed and the access widened.
1.2Upon investigation, the officer concluded that the events being undertaken met the parameters permitted under Schedule 2 Part 4 Class B of the General Permitted Development Order (GPDO) 2015, such that the temporary use of the land for events had not exceeded 56 days. The number of permitted days had temporarily increased from 28 days to 56 until 31st December 2020 under the Town and Country Planning (Permitted Development and Miscellaneous Amendments) (England) (Coronavirus) Regulations 2020. Furthermore, the officer concluded that the structures on site were temporary and moveable and were permitted under the GPDO. It was also concluded that a new access had not been created, but an old one reinstated. The file was closed due to there being no identified breach of planning control.
1.3During the process of the 2020 enforcement investigation, planning application 2020/0552 was pending consideration. This application sought the change of use of the land to a 20 pitch campsite, a mobile WC block, communal tipi and alterations of existing access for a period up to 2023 (see below planning history).
1.4On 13th April 2021, the Planning Officer dealing with a subsequent application (2021/0338) seeking permission for a change of use of the land and temporary siting of a double tipi and a WC trailer between May 31st and Oct 31st, emailed the owner of the site to clarify permitted development rights in relation to siting of the tipi and associated structures as part of a temporary use. 1.5 In May 2021, application 2021/0338 was refused and an appeal lodged in June 2021.
1.6In June 2021 the Council received complaints relating to the erection of a tipi tent on site on 14th June. The Town and Country Planning (General Permitted Development) (England) (Amendment) Regulations 2020 extended the 56 day permitted development allowance until 31st December 2021. As such, the development was considered permitted until such time as the 56 days had expired. Until such time there would be no breach of planning control.
1.7On 9th August 2021, the Council received confirmation from the complainant that the tipi tent was still present on site meaning it had been on site for 58 days. Between 14th June and 9th August, the Council had received regular updates from the complainant regarding the on-going presence of the tipi tent.
1.8On 16th September 2021, the appeal against the refusal of application 2021/0338 was dismissed. The Inspector concluded that the proposals for the siting of the tipi, WC trailer and other associated features would have a degree of permanence and would have a moderate harmful effect on openness and also that the development would significantly harm highway safety. They also concluded that very special circumstances did not exist with regards to the proposals.
1.9No further events are understood to have taken place on the site during 2021 after the date of the appeal decision.
1.10On 11th February 2022, a planning application was received for change of use of land to form seasonal, green, carbon negative, wedding venue (1st June - 31st August inclusive) including the siting of two linked tipis, WC trailer and renewable energy system (2022/0172). The proposals were very similar in nature to those proposed in the 2021/0388 application. The only differences being the proposed use of a renewable energy trailer and the dates of use for the site.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.