Resolved
RESOLVED to: 1) Note the contents of the report. 2) Note the publication of the Infrastructure Funding Statement for 2021/22 as detailed at Appendix A.
Planning Committee noted this item on Wednesday 11 January 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to: 1) Note the contents of the report. 2) Note the publication of the Infrastructure Funding Statement for 2021/22 as detailed at Appendix A.
Borough-wide
Purpose
To provide Members with information on the monies collected through the Community Infrastructure Levy (CIL) and Section 106 Planning Obligations, how they are administrated and future expenditure priorities in relation to the monies collected.
To note the publication of the Infrastructure Funding Statement for 2021/22 attached in Appendix A.
Key Decision
This is a Key Decision as it is likely to be significant in terms of its effect on the communities living or working in an area comprising of two or more wards in the Borough.
Recommendation(s)
THAT Planning Committee:
1) Notes the contents of the report.
2) Notes the publication of the Infrastructure Funding Statement for 2021/22 as detailed at Appendix A. 1 Background
1.1Members will be aware that the Council can secure financial contributions and non-monetary contributions from developments through Section 106 Planning Obligations and the Community Infrastructure Levy (CIL). These contributions are to be expended on infrastructure within the Borough to mitigate against the impacts of local development.
1.2On the 1st September 2019, the Community Infrastructure Levy (Amendment) (England) (No. 2) Regulations 2019 were published which introduced a new requirement into the Community Infrastructure Levy Regulations 2010 (“the Regulations”) for all Charging Authorities to publish an annual document, known as the “Infrastructure Funding Statement”, before the 31st December each calendar year. This document must include an “Infrastructure List” listing the infrastructure or types of infrastructure the authority intends will be or may be wholly or partly funded by CIL, a “CIL Report” in relation to the previous financial year, and a “Section 106 Report” about planning obligations in relation to the previous financial year. The document must be published on the Council’s website.
1.3The attached Infrastructure Funding Statement 2021/22 at Appendix A includes details of the amount of CIL receipts received, expended and retained for the financial year 2021/22 (“the reported year”), a breakdown of cumulative CIL receipts since its adoption in 2015 and details of demand notices issued during the reported year. It also provides detail of CIL passed to parish councils.
1.4The Infrastructure Funding Statement 2021/22 at Appendix A also provides an update on financial contributions collected through Section 106 Planning Obligations, including details of new planning obligations which were agreed upon during the reported year, the amount of money which was received during the reported year, the monies which have either been allocated or expended within the reported year and the amount of monies retained at the end of the reported year. The report also gives a breakdown of any non-monetary obligations.
1.5In accordance with the Regulations an Infrastructure List is included at the end of the report to detail future infrastructure projects and how they will likely be funded through Planning Obligations. This Infrastructure List is taken from the Regulation 123 List which was adopted as part of the Charging Schedule by Gedling Borough Council on the 16th October 2015.
2 Proposals
2.1The Infrastructure Funding Statement 2021/22 at Appendix A has been prepared taking into account the requirements of the Regulations. It is proposed that members note the Infrastructure Funding Statement 2021/22 at Appendix A and approve publication of the Statement on the Council’s website in accordance with the Regulations.
3.1Failure to correctly identify and deliver on the S106 schemes would mean that contributions including any indexation may have to be paid back to the developer.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Infrastructure Funding Statement 2021/22Report | 149 KB | DownloadRead as text |
PDF |
Infrastructure Funding Statement 21-22.docxReport | 1 MB | Download |
Follow Planning Committee at Gedling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Oct 2026 | To approve, as a correct record, the minutes of the meeting held on 9 September 2026That the minutes of the above meeting, having been circulated, be approved as a correct record. | Approved | Open |
| 14 Oct 2026 | Application no. 2026/0501 - Richard Herrod Centre, Foxhill Road Central, Carlton, NottinghamshireTo Grant Planning Permission: Subject to the conditions listed for the reasons set out in the report. Conditions The ... | Approved | Open |
| 14 Oct 2026 | Appeal Summary Ref: 6014560 - 31 Mansfield Road, Daybrook, NottinghamshireTo note the information. | Noted | Open |
| 14 Oct 2026 | Appeal Summary Ref: 6013777 - 6 Pateley Road, Woodthorpe, NottinghamshireTo note the information. | Noted | Open |
| 14 Oct 2026 | Future planning applicationsTo note the information. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.