RESOLVED to: 1) Note the D2N2 decision to include the Hill Crest Business Park extension onto the LEP Capital Programme; 2) Approve an increase in the Hill Crest Business Park project budget of £146,000 to be funded from the UK SPF grant which creates an overall budget of £1,534,000; 3) Approve officers to continue with the completion of the D2N2 Final Business Case submission and therefore proceed with the design development to RIBA 4 at a cost of £78,000 and Employer Agents costs of £18,000 both of which are included in the proposed new budget envelope; and 4) Delegate authority to the Chief Executive in consultation with the Legal Services Manager and Portfolio Holder for Sustainable Growth and Economy, to sign off the final business case submission and enter into a legal agreement with the D2N2 LEP to deliver the scheme, should the business case be successful.
Word for word from the decision Gedling published for this meeting.Source: democracy.gedling.gov.uk
To seek approval to proceed with the design and development of 4 additional small business units for SMEs at the Hill Crest Business Park in Calverton (the Site).
Key decision
This is a key decision as it is likely to incur expenditure in excess of £500,000.
Recommendations
THAT Cabinet:
1. Notes the D2N2 decision to include the Hill Crest Business Park extension onto the LEP Capital Programme.
2. Approves an increase in the Hill Crest Business Park project budget of £146,000 to be funded from the UK SPF grant which creates an overall budget of £1,534,000.
3. Approves Officers to continue with the completion of the D2N2 Final Business Case submission and therefore proceed with the design development to RIBA 4 at a cost of £78,000 and Employer Agents costs of £18,000 both of which are included in the proposed new budget envelope.
4. Delegates authority to the Chief Executive in consultation with the Legal Services Manager to sign off the final business case submission and enter into a legal agreement with the D2N2 LEP to deliver the scheme should the business case be successful.
1 1 Background
1.1On 30 June 2023 the Council submitted a funding application to D2N2 to support the extension of the existing Hill Crest Business Park. The overall project value was anticipated to be £1.388m project and included the development of 4 additional industrial units, PV panels on the new and existing 8 units and electrical charging points. 1.2 The funding application built on previous unsuccessful ERDF/LEP bids where planning approval had been secured (but subsequently expired) and a high-level cost plan had been developed. The Council prior to submitting a new funding application undertook a desk top exercise to test the business case assumptions to ensure that the scheme continued to support the Council’s priorities. This desk top exercise reviewed the local commercial market using the CoStar system, which evidenced a continued lack of suitable industrial/business space to support SMEs and Start Up businesses within the Borough.
1.3The Council also appointed independent consultants who reviewed the earlier cost plan and Value for Money assessment prior to the Council submitting its application in June 2023. The assessment concluded that based upon the additional floor space to be delivered and the evidence of existing units, 18 jobs could be created generating over £800,000 GVA pa.
1.4The Council were notified on 30 July 2023 that the funding application had been shortlisted for approval and would be submitted to the Investment Board on 7 September 2023. The D2N2 funding conditions required works to commence prior to 31 March 2024. Therefore, the Council proceeded to secure Planning approval for the scheme and to prepare a business case that was approved by Cabinet on 7 September 2023 in readiness for confirmation of D2N2 decision.
1.5In December 2023 the Council received confirmation that the Hill Crest Business Park extension had been formally adopted onto its Capital Programme with an allocation of £642,457. This award being subject to the Council submitting a compliant Final Business Case (Appendix A Final Business Case requirements). This includes the requirement to undertake pre-construction work, including technical design to RIBA stage 4.
1.6Although the previous D2N2 grant funding conditions stipulated that construction works must commence within the current financial year, this requirement has now been relaxed and works can commence in 2024/25.
2. Proposal
2.1The September 2023 Cabinet Report recommended a procurement approach via compliant framework due to the funding constraints that required a scheme to commence prior to 31 March 2024. Although the delivery timescales have been relaxed there remains an urgency for this project to proceed at pace in view of the future of
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.