To GRANT PLANNING PERMISSION: Subject to the owner entering into a planning obligation secured through a s106 legal agreement with the Borough Council as the Local Planning Authority and the County Council to secure affordable housing, education improvements; healthcare enhancements; bus stop installations; library improvements and a Local Labour Agreement; and subject to the conditions listed for the reasons set out in the report. Conditions 1. The development herby permitted shall commence before the expiration of 3 years from the date of this permission. 2. The development authorised by this permission shall be carried out in complete accordance with the approved drawings and specification listed below: Site Location Plan Plan Ref: 3424-01 A2 received 02 Feb 2021 Planning Layout Plan Ref: REDH-SK-001-I-A1 26 September 2023 Materials Layout Plan Ref: 02352 - 005-A-A1 received 02 Feb 2024 Open Space Plan Plan Ref: Redh-SK-002-A1 received 13 September 2023 Proposed House Type M2 604 24/Three Plan Ref: P243-22017-001 -A2 received 19 April 2023 ... view the full minutes text for item 90.
Word for word from the decision Gedling published for this meeting.Source: democracy.gedling.gov.uk
1.1We are advised that the site extends to 6.79 Ha (16.78 acres) on a gross basis with a net developable area of 3.92 Ha (9.69 acres). The current planning application under reference 2021/0072 comprises: “Proposal for 157 dwellings with associated landscaping, public open space, highways and infrastructure on land west of the A60 Redhill, Nottingham”
1.2Acting on behalf of the applicant, Turner Morum (“TM”) submitted a viability review in Aug 2022. At that time, TM concluded that the scheme “…only becomes viable when the affordable housing provision is reduced to 0%”.
1.3Acting upon the instruction of the Council we undertook an independent viability assessment of the scheme in Mar 2023. We concluded that the scheme could viably deliver 30% onsite affordable housing, plus S106 costs totalling £727,632. We reached a different outcome to TM owing to the following adjustments:
1 1.4. On 26th May 2023 TM raised a number of challenges to our viability review. Following our initial review, we noted that the overall square footage of the proposed development was different to TM’s original assessment (originally this totalled 144,000 sq ft, whereas in TM’s latest appraisal it totalled 145,809 sq ft). We subsequently requested further information from the applicant / TM in order to enable us to provide further comments to the Council (including confirmation of the schedule of accommodation to be provided on site).
1.5Following receipt of additional information, on 29th June 2023 we submitted an updated appraisal, which was based on the latest ‘Revision E’ mix. This totalled 144,318 sq ft. This included the following appraisal assumptions:
- Total gross development value came to £38,660,467 (with a market value average of £291 per sq ft) - Plot costs £118.62 per sq ft - Externals £3,998,136 - Contingency £860,840 (3.30% of above) - Abnormals / site specific infrastructure totalling £4,968,984
Independent Viability Experts RICS Regulated Firm Company No. 10377118 Written in Confidence - Professional fees 7% of standard plot costs / externals - S106 £864,000 - Marketing / disposal 2.5% on revenue - Debit interest 7.5% - Developer profit: 18.5% on market value, 15% First Homes, 6% affordable - Benchmark land value £1,258,357
1.6Based on the above assumptions, we concluded that the viability pressure had increased significantly. With 15% onsite affordable housing (plus 15% ‘non S106’ affordable units) the residual land value was £955,090. This was shortfall of £303,267 from the benchmark land value and therefore unviable.
1.7However, we noted that a key driver in this outcome was the increase in abnormals / site specific infrastructure costs associated with the site (which had increased from the original testing). We therefore indicated to the Council that it would be prudent to seek specialist advice on these costs.
1.8On 29th Jun 2023 the Council indicated that they were looking to engage a third-party Quantity Surveyor to review the abnormal / site specific infrastructure costs used in TM’s appraisal (which had increased from £4,678,733 in Aug 22 to £5,217,931 in Jun 23). Bentley Project Management (“BPM”) were subsequently instructed to undertake the review on behalf of the Council.
1.9In Jan 2024 the final agreed abnormal / site specific infrastructure costs between the applicant’s cost advisors (Cora) and BPM were circulated. The agreed figures can be summarised as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.