Overview and Scrutiny Committee, Monday 12 January 2026 at 5.30pm

Gedling Plan Q2 2025/26 performance update

Noted Scrutiny 3 papers

AI summaryGedling Overview and Scrutiny Committee noted Q2 2025/26 performance: 33 of 69 planned milestones completed and 12 of 30 indicators met or exceeded target. Sickness absence and housing benefit processing times missed target.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedProgress against Performance Indicators and Annual Delivery Plan noted
MoneyNo financial implications reported
What happens nextQ3 monitoring and SLT resourcing report73 milestones expected in Q3; resourcing report due November
Who it affectsBorough widePerformance covers all of Gedling Borough

What was decided

The committee noted progress against Improvement Performance Indicators for Q2 of 2025/26. Report P7

The committee noted progress against Annual Delivery Plan Actions. Report P8

Why

The report ensures members are informed of performance against the Annual Delivery Plan and Gedling Plan. Report 13.1

Performance reporting is part of the council's commitment to align budget and performance management and acts as an early warning system. Report 1.1, 1.2, 1.3

What happens next

Completion rate is expected to increase in Q3 as green-status milestones are delivered. Report 2.6

A resourcing report addressing team leader and admin vacancies in Housing Benefits/Council Tax Reduction is due at SLT in November. Report P51, P52

Demolition of the waste depot shed is due for completion in Q3. Report P30

Options considered

  • Chosen: Present the Q2 performance update. Ensures members are aware of performance against the Annual Delivery Plan and Performance Indicators. Report P6, P7, P8, 13.1
  • Rejected: Do not present a quarterly performance update. Members would not be aware of performance against the current Annual Delivery Plan and Performance Indicators. Report 6.1

Implications

  • Financial: No financial implications arising from the report. Report 7.1
  • Legal: No legal implications arising from the report. Report 8.1
  • Equalities: No equalities implications arising from the report. Report 9.1
  • Climate: No carbon reduction or sustainability implications arising from the report. Report 10.1
  • Staffing: Resource challenges in Housing Benefits/Council Tax Reduction after loss of a team leader and one admin team member; long-term sickness in Environmental Services is driving up sickness absence days. Report P51, P52, P58, P59
  • Risk: One milestone is off track: 'Create an action plan to drive delivery' under the digital inclusion approach action; corrective action is being implemented. Report 2.5

Who and where

  • Residents across Gedling Borough Report P1
  • Waste service customers (75% of complaints related to Waste Services in Q2) Report P65
  • Planning applicants (Minor applications processed at 80.95% against 86% local target) Report P55
  • Council staff, particularly in Environmental Services and Housing Benefits Report P58, P59, P51, P52

Timeline

  • Q1 2025/26: 30 Annual Delivery Plan milestones completed. Report 2.6, P23
  • Q2 2025/26 (July to September 2025): 33 of 69 planned milestones completed; 36 realigned to Q3 or Q4. Report 2.4, 2.6, P23
  • September 2025: Local Plan Issues and Options consultation concluded with over 1,500 responses. Report P28
  • November 2025: Resourcing report on Housing Benefits/Council Tax Reduction to be considered by SLT. Report P51, P52
  • Q3 2025/26: 73 milestones expected; demolition of waste depot shed due for completion. Report P23, P30
  • Q4 2025/26: 53 milestones expected. Report P23

Plain English for the jargon

  • SLT: Senior Leadership Team of the council.
  • ADP: Annual Delivery Plan, the set of 52 actions across 6 themes agreed by Cabinet in March 2025.
  • Q2 2025/26: Quarter 2 of the 2025/26 financial year, covering July to September 2025.
  • RAG: Red, Amber, Green traffic light system used to assess indicator performance.
  • SLA: Service Level Agreement, here the 40-second target for answering customer service calls.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item36

Resolved

RESOLVED to: 1) Note the progress against Improvement Performance Indicators for quarter 2 of 2025/26; and 2) Note the progress against Annual Delivery Actions.
Word for word from the decision Gedling published for this meeting. Source: democracy.gedling.gov.uk

Follow this further

Built from Gedling's papers

What the report saysPro

Report to Overview and Scrutiny Committee

Wards affected

Borough wide

Purpose

To inform Members in summary of the position against Performance Indicators and Annual Delivery Plan Actions in Quarter 2 of 2025/26.

Key Decision

This is not a key decision.

Recommendation

THAT:

The progress against Improvement Performance Indicators for quarter 2 of 2025/26 be noted.

The progress against Annual Delivery Plan Actions be noted

Background

1.1The Council has made a commitment to closely align budget and performance management. This is in line with accepted good practice.

1.2To deliver this commitment, systems to monitor performance against revenue and capital budgets, improvement activity and performance indicators have all been brought together and are now embedded in the way the Council works.

1.3In addition, performance reports focus directly on the Council’s priorities and offer an “early warning” system of instances where targets may not be secured.

1.4The assessment criteria used for indicators is based on red, amber and green traffic light symbols. To be assessed as green, performance indicators must be in line with their expected performance at that stage of the year determined within the performance management system.

1.5This report reflects a change to the usual format in that progress against the Annual Delivery Plan is now reported and replaces the previous section on the Gedling Plan actions.

2 Proposal

2.1It is proposed that Members note the current performance information for Quarter 2 of 2025/26 as set out below –

2.2Annual Delivery Plan Actions

In March 2025 Cabinet agreed to the annual delivery plan with 52 actions spanning 6 themes -

 Customer Experience and Communities Programme  Smarter Working Programme  Depot Modernisation Programme  Gedling Growth  Leisure Transformation  Governance Control Framework

2.3Milestones have been identified under each action to assist the monitoring of progress against the delivery plan, of which there are a total of 189 covering all themes for 2025/26.

2.4For Q2 there were originally 69 milestones recorded as planned for delivery during July to September. 33 have been completed (please see appendix A for more details) and 36 were realigned to Q3 or Q4 as more information on these projects were made available and dependencies became known.

2.5Of the 36 milestones that have been realigned, 34 are ‘on track’ (signifying that milestones are progressing as planned – status green) and 2 milestones are being closely monitored, 1 has been identified as ‘at risk’ where there are issues or concerns that could impact delivery but are being addressed or mitigated. 1 has been identified as ‘off track’ where issues do exist that are I acting progress, and corrective action is being implemented to meet the year-end deadline. The milestone ‘off-track’ is ‘Create an action plan to drive delivery’ and is related to the Annual Delivery Plan action – ‘Created a digital inclusion approach to support customers and employees’.

2.6There were 30 milestones completed in Quarter 1 and 33 completed in quarter 2 against 189 due for the whole year. This represents a cumulative completion rate of milestones of 33.33% (the number of completed and expected milestones below). The completion rate is expected to significantly increase in quarter 3 as the milestones tracking ‘Green’ are completed.

Quarter 1 Quarter 2 Quarter 3 Quarter 4 Completed Completed Expected Expected 30 33 73 53

2.7

3 Achievements

3.1Focussed on deliverables from the Annual Delivery Plan, key achievements identified for particular attention during quarter 2 include:

 Between July and August 2025, our programme consultants, Mutual Ventures led a targeted engagement and consultation campaign with key stakeholders to support the development of themes, proposals and interventions for our 4-year investment plan.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gedling Plan Appendix A: Completed Milestones Q2Appendix 307 KB Download
PDF
Gedling Plan Appendix B: Performance Indicators Q2Appendix 337 KB Download
PDF
Gedling Plan Q2 2025/26 performance updateReport 258 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 20 attended
CP
Councillor Catherine PopeChair, present
DB
Councillor David BrocklebankVice-Chair, present
MA
Councillor Michael AdamsCommittee Member, present
PA
Councillor Pauline AllanCommittee Member, present
RA
Councillor Roy AllanCommittee Member, present
JC
Councillor Jim CreamerCommittee Member, present
AD
Councillor Andrew DunkinCommittee Member, present
RE
Councillor Rachael EllisCommittee Member, present
DM
Councillor Darren MaltbyCommittee Member, present
RM
Councillor Ron McCrossenCommittee Member, present
GP
Councillor Grahame PopeCommittee Member, present
SS
Councillor Sam SmithCommittee Member, present

All 20 on the meeting page

On this subject at Gedling

Search all
  1. Gedling Plan Q2 2025/26 performance updateThis decision
  2. Gedling BC Asset Management Plan 2026-2028Agreed
  3. The Gedling Visitor Economy Destination Management PlanApproved
  4. Gedling Plan Q4 Performance 2025/2026 ReportNoted
  5. Gedling Plan Annual Report 2025/2026Approved
  6. Gedling Local Development Plan - publication draftApproved

More from Gedling Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
12 Oct 2026 To approve, as a correct record, the minutes of the meeting held on 27 July 2026.That the minutes of the above meeting, having been circulated, be approved as a correct record. Approved Open
12 Oct 2026 Update on Local Government Reorganisation (LGR).To note the update on Local Government Reorganisation. Noted Open
12 Oct 2026 Response to the Fly Tipping, Litter and Waste Management Recommendations.To note Cabinet’s response to the recommendations of the Fly Tipping, Litter and Waste Management Working Group. Noted Open
12 Oct 2026 Scrutiny Work Programme.To note the Scrutiny Work Programme. Noted Open