Budget Monitoring and Virement Report – August to November 2025

Approved Executive 4 papers

AI summaryGedling Borough Council Cabinet approves £219,800 of earmarked reserves to cover a forecast General Fund overspend, removes £247,000 of undeliverable 2025-26 efficiency savings, and trims the capital programme by £3,126,100.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedIncludes removing £374,000 of efficiency savings
Money£3,126,100 net capital reductionPlus £219,800 from reserves for revenue
What happens nextNew efficiencies to be proposedFor 2026-27 budget report
Who it affectsBorough-wideAll council portfolios affected

What was decided

Cabinet approved £219,800 of earmarked reserves to be re-purposed to cover a forecast General Fund revenue overspend, keeping net spend at the approved £15,584,200. Report P19, P26

Cabinet approved removing £374,000 of approved efficiency savings, including £247,000 for 2025-26, leaving a revised in-year target of £378,500. Report P48, P50

Cabinet approved capital programme changes totalling a net reduction of £3,126,100, with new borrowing of £324,800 requested for Ambition Arnold Front Street works. Report P52, P54, P58, P59

Why

The General Fund is forecast to overspend by £219,800, mainly due to waste service agency and overtime costs of £195,000, redundancy and pension strain of £142,700, and lower investment income of £300,000. Report P19, P30, P34

Senior Leadership Team review found several efficiency schemes undeliverable, including leisure operations, waste round optimisation, parks service review and ICT practices reviews. Report P48, P50

Capital schemes have been rephased into 2026-27, including Digital Transformation, vehicle replacement, temporary accommodation purchases, Disabled Facilities Grant and Redhill gym equipment, as works are still in progress. Report P60

What happens next

Replacement achievable efficiencies are to be presented to Cabinet as part of the 2026/27 budget report. Report P49

The capital programme additions of £324,800 for Ambition Arnold Front Street public realm improvements are recommended to Council for approval, funded by prudential borrowing. Report P13, P58, P59

Medium-Term Financial Plan is being updated alongside 2026/27 budget forecasts and the provisional Local Government Finance Settlement. Report P51

The money

  • 15,584,200 Net Council Budget for 2025/26 approved on 5 March 2025 Report P22, P26
  • 219,800 Projected General Fund revenue overspend for 2025/26 Report P19, P24
  • (219,800) Proposed transfer from earmarked reserves to cover overspend Report P25
  • 701,500 Approved 2025/26 pay award budget based on £1,290 per FTE Report P41
  • (150,000) Budgeted saving from 3.2% NJC pay award increase from 1 April 2025 Report P41
  • 917,700 Total current approved efficiency programme for 2025/26 to 2026/27 Report P46
  • 374,000 Total efficiency savings proposed for removal Report P48
  • 247,000 Portion of removed efficiencies relating to 2025-26 Report P48, P50
  • 378,500 Revised 2025-26 efficiency programme after removals Report P50
  • 10,276,900 Current approved capital budget for 2025/26 at Period 8 Report P54
  • 324,800 Additions to capital programme for Ambition Arnold Front Street properties, funded by prudential borrowing Report P54, P58, P59
  • (3,126,100) Total proposed amendments to capital programme at November 2025 Report P52, P57
  • 7,150,800 Revised capital programme 2025/26 after amendments Report P57
  • 3,238,187 Actual capital expenditure to Period 8 2025/26 Report P57

Options considered

  • Chosen: Approve the virements, reserve re-purposing, efficiency removals and capital programme changes. Aligns budgets to current pressures and supports delivery of Council objectives Report 10.1
  • Rejected: Do not amend the original Council approved budgets during the year. Would not align to current budget pressures, would restrict medium-term planning and would not reflect latest performance information Report P69, P70, P71, P72, P73, P74, P75, P76

Implications

  • Financial: General Fund forecast overspend of £219,800 will be covered by re-purposing three earmarked reserves: £100,000 from IT Replacement, £80,400 from Economic Development, and £39,400 from Efficiency and Innovation. Report P19, P38, P39
  • Financial: Investment income is forecast £300,000 lower than budgeted, owing to Bank of England base rate cuts and deferral of capital receipts to 2026-27. Report P34, P42, P43
  • Staffing: Redundancy and pension strain payments of £142,700 arise from efficiency programmes and restructures, funded from earmarked reserves. Report P30
  • Financial: Waste and Street Care service overspent by £195,000 on agency and overtime due to sickness and annual leave cover; transformation review continues. Report P30, P37
  • Risk: Environmental Services remains at risk of further overspend in the remainder of 2025/26, with spend monitored through the Budget and Performance Board and Senior Leadership Team. Report P37, 4.1
  • Financial: Capital receipts income for 2025/26 is now expected at £571,300 rather than the original £1,654,400, owing to a delayed land sale; further receipts are expected in 2026-27. Report P55, 2.5
  • Legal: No legal implications arise directly from this report. Report 5.1
  • Equalities: No equalities implications arise directly from this report. Report 6.1

Who and where

  • Waste and Street Care service users, affected by higher agency and overtime costs of £195,000 due to sickness and leave cover Report P30, P37
  • Care Leavers in Gedling, due to additional £45,000 spend on the Council Tax reduction scheme from increased participation Report P30
  • Arnold town centre, with an additional £324,800 of borrowing requested for Ambition Arnold Front Street properties public realm works Report P13, P58, P59
  • Tenants requiring Disabled Facilities Grants, with £600,000 of grant budget deferred into 2026-27 Report P55, P60
  • Council tenants and homeless households, with £646,200 for temporary accommodation purchases deferred to 2026-27 Report P55, P60
  • Redhill leisure users, with replacement gym equipment deferred to May 2026 completion Report P55, P60

Timeline

  • 5 March 2025: Council approved the 2025/26 net revenue budget of £15,584,200 and capital budget of £6,413,400 Report P22, P54
  • 1 April 2025: 3.2% NJC pay award took effect on all pay points 1 and above, producing a £150,000 budgeted saving Report P41
  • 8 May 2025: Bank of England base rate reduced to 4.25% Report P42, P43
  • 7 August 2025: Bank of England base rate further reduced to 4.00% Report P42, P43
  • 30 November 2025: Budget monitoring data snapshot used for this report Report P18
  • December 2025: Bank of England base rate further reduced to 3.75% Report P42, P43
  • January 2026: Four further temporary accommodation property purchases scheduled to complete Report P60
  • May 2026: Replacement of Redhill Gym Equipment expected to complete Report P60
  • 2026-27: Replacement achievable efficiencies to be presented as part of the 2026/27 budget report; Medium-Term Financial Plan being updated Report P49, P51

Plain English for the jargon

  • Virement: An approved transfer of budget from one budget head to another within the Council's revenue budget.
  • Earmarked Reserve: Money set aside for a specific purpose, which can be re-purposed by Cabinet where sufficient balances remain.
  • General Fund: The main revenue account for the Council's day-to-day spending, separate from the Housing Revenue Account.
  • S106 Contributions: Payments from developers under Section 106 of the Town and Country Planning Act, used to fund infrastructure or services linked to a development.
  • UKSPF: UK Shared Prosperity Fund, a central government fund for local growth projects.
  • Prudential Borrowing: Borrowing by a local authority for capital purposes, governed by the Prudential Code, with repayment from revenue or capital receipts.
  • Minimum Revenue Provision: The amount a council must set aside from revenue each year to repay debt used to fund capital expenditure.
  • Period 8: The eighth budget monitoring period of the financial year, covering August to November 2025.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item75

Resolved

RESOLVED TO: 1) Approve the General Fund Budget virements set out in Appendix 1. 2) Approve the re-purposing of Earmarked Reserves as set out in section 2.1. 3) Note the use of reserves during August to November 2025 as detailed in Appendix 2. 4) Approve the removal of £374,000 of total efficiency savings, of which £247,000 relate to 2025-26 as set out in section 2.2. 5) Approve the changes to the Capital programme included in section 2.3.
Word for word from the decision Gedling published for this meeting. Source: democracy.gedling.gov.uk

Follow this further

Built from Gedling's papers

What the report saysPro

Report to Cabinet

Wards affected

Borough-wide

Purpose

To update Cabinet on the forecast outturn for Revenue and Capital Budgets for 2025/26. The budgets include all approved carried forward amounts from the 2024/25 financial year.

To request approval from Cabinet for the changes to the budget as set out in this report.

Key Decision

This is a key decision because the proposal includes financial implications that are above the threshold of £0.5m determined by Council for decisions to be regarded as a Key Decision.

Recommendation(s)

Cabinet are recommended to:

1. Approve the General Fund Budget virements set out in Appendix 1;

2. Approve the re-purposing of Earmarked Reserves as set out in section 2.1

3. Note the use of reserves during August to November 2025 as detailed in Appendix 2;

4. Approve the removal of £374,000 of total efficiency savings, of which £247,000 relate to 2025-26 as set out in section 2.2;

5. Approve the changes to the Capital programme included in section 2.3. 6. Recommend to Council the approval of £324,800 use of borrowing to fund the developments on Arnold Front Street as part of the Ambition Arnold Project.

Background

1.1The Council has made a commitment to closely align budget and performance management. This is in line with accepted good practice.

1.2To deliver this commitment, systems to monitor performance against revenue and capital budgets, improvement activity and performance indicators have all been brought together and are now embedded in the way the Council works

2 Proposal

2.1General Fund Revenue Budget Summary

The following table summarises the overall financial position of the General Fund Revenue Budget and the expected total spend for the year. This information has been compiled using the best information made available to Financial Services by the relevant spending officers as at 30 November 2025.

The Council’s General Fund outturn is projected to be overspent by £219,800. In order to ensure the position remains in line with the approved budget of £15,584,200 it is proposed that Cabinet approve re-purposing of earmarked reserves of £219,800 to fund the overspend.

General Fund Revenue Budget 2025/26 – Change Analysis

£

Net Council Budget for 2025/26 approved by Council 15,584,200 on 5 March 2025 and Cabinet’s Maximum Budget

Up to the end of November 2025 expenditure less income 7,006,861 totalled In the remaining 4 months of year we expect net 8,797,139 expenditure to be Total net revenue spend for the year is currently 15,804,000 expected to be

Total Projected Revenue (Under)/ Overspend 2025/26 219,800

Proposed Transfer from Earmarked Reserves for (219,800) Approval

Total net revenue spend for the year is expected to be 15,584,200

Appendix 1 outlines how the General Fund Revenue budget is divided between the Portfolios of the Council and includes a detailed variance analysis identifying the current proposed changes for the four month period against the approved budget for each Portfolio area. Cabinet is recommended to approve these changes.

The major variances detailed in Appendix 1 include:

Expenditure increases:

• Additional agency and overtime costs within the Waste & Street Care service £195,000 due to sickness levels and cover for annual leave. • Redundancy and pension strain payments arising from efficiency programmes and restructures of £142,700 funded by a contribution from earmarked reserves. • Additional spend on our Care Leavers Council Tax reduction scheme £45,000, due to increased participation. • Additional HR temporary business partner £43,000 due to increased workload in the department.

Expenditure reductions:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
. GF Revenue Budget Control Report August to November 2025Appendix 1 170 KB Download
PDF
. Use of Earmarked Reserves August to November 2025Appendix 2 148 KB Download
PDF
. Capital Monitoring 25-26: August to November 2025: FinalAppendix 3 126 KB Download
PDF
Budget Monitoring and Virement Report: August to November 2025Report 277 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 17 attended
JC
Councillor John ClarkeChair, present
JH
Councillor Jenny HollingsworthVice-Chair, present
DE
Councillor David EllisCommittee Member, present
KF
Councillor Kathryn FoxCommittee Member, present
VM
Councillor Viv McCrossenCommittee Member, present
MP
Councillor Marje PalingCommittee Member, present
LP
Councillor Lynda PearsonCommittee Member, present
HW
Councillor Henry WheelerCommittee Member, present
MH
Mike HillOfficer, in attendance
FW
Francesca WhyleyOfficer, in attendance
MA
Mike AveryOfficer, in attendance
TA
Tina AdamsOfficer, in attendance

All 17 on the meeting page

On this subject at Gedling

Search all
  1. Budget Monitoring and Virement Report – August to November 2025This decision
  2. Budget Monitoring and Virement Report for the period April to July 2025Approved
  3. Budget Monitoring and Virement Report – August to November 2024Approved
  4. Budget Monitoring and Virement Report – April to November 2024Approved
  5. Budget Monitoring and Virement Report for the period April to July 2024Approved
  6. Referral from Cabinet - Quarterly Budget Monitoring and Virement Report – Q3 Dec 2023Approved

More from Gedling Cabinet

All decisions
MeetingDecisionOutcome
16 Jul 2026 To approve, as a correct record, the minutes of the meeting held on 25.06.26.That the minutes of the above meeting, having been circulated, be approved as a correct record. Approved Open
16 Jul 2026 Forward Plan1) To note the report. Noted Open
16 Jul 2026 Housing Strategy 2026-2030That Cabinet: 1) Noted the representations and comments received during the public consultation, together with the of... Noted Open
16 Jul 2026 Gedling BC Asset Management Plan 2026-2028THAT Cabinet: 1) Agreed to adopt the Asset Management Strategy 2026-2028 at appendix 1. 2) Approved the proposals for... Agreed Open
16 Jul 2026 Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies