AI summaryPlanning Inspector dismisses appeal against refusal of retrospective permission for a Green Belt workshop at Abbey Quarry, Linby; the case now passes to the Council's Enforcement Officer.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
To note the information.
Report to Planning Committee Application Number: 2025/0107
Appeal Ref: APP/N3020/W/25/3369300 Site Address: Abbey Quarry, Quarry Lane, Linby, Nottingham NG15 8GA Application description: Retrospective permission for installation of workshop building (Use Class B8). Case Officer: Amy Schofield The planning application was refused permission on the 25th April 2025 for the reason outlined below:
1. The proposal has resulted in the construction of a new building in the Green Belt and fails to provide convincing evidence that it accords with any of the identified exceptions of development. It would therefore constitute inappropriate development which would be by its definition [be] harmful to the openness of the Green Belt and which should be given substantial weight in the determination of this application. It has not been demonstrated that very special circumstances exist for this proposal to outweigh such harm. As such, the proposal fails to accord with the NPPF and Policy 3 (The Green Belt) of the Aligned Core Strategy.
The proposal is a former quarry site within the Green Belt, primary used for domestic recreation and in association with a certification for five pitches from the Caravan and Motorhome Club (CMC). The proposal is for a large utilitarian workshop sited close to the site’s boundary with Quarry Lane. Main Issues
1. Whether the proposal was inappropriate development in the Green Belt
It was common ground that none of the exceptions which might otherwise allow for development in the Green Belt had been met and that consequently the building amounted to inappropriate development in the Green Belt, which by definition is harmful.
2. The effect of the proposal on the Green Belt
The Inspector agreed that the building had introduced a significant built form into an area previously free of structures, consequently that the bulk and mass of the building is detrimental to the openness of the Green Belt in spatial terms. They acknowledged that limited scope for public views of the building limited the perception of reduced openness in visual terms but that this nevertheless did not alter the spatial impact. The Inspector also noted that the effect of a proposal on the openness in the Green Belt is not a relative concept dependent on the overall size of the Green Belt. The Inspector concluded that, in addition to be deemed to be inappropriate development, there is an adverse effect on openness of the Green Belt as a result of the building. 3. Whether any harm was clearly outweighed by other considerations so as to amount to the very special circumstances required to justify the proposal
The Applicants attested that the building was essential storage for equipment necessary to maintain the site. However, the Inspector noted a duplication of function between this use and that already granted for a boathouse and storage structure in 2016, now built out on site. The Inspector also found that the type and capabilities of the machines stored seemed to be considerably more extensive and diverse than the list of maintenance operations required to maintain the site, as set out by the Appellant. Given no site changes since 2016 the Inspector concluded that it was unclear why the storage provided by the Boathouse should now be considered inadequate.
The Inspector also noted the Appellant’s statement that the machinery was required for maintain the CMC use but noted that while this certification has resulted in a change of use on the site which does not require planning permission, this does not justify inappropriate development in the Green Belt and that if additional storage areas were needed to facilitate the change of use, this should have been taken into account and the necessary permissions sought beforehand.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appeal Summary Ref: APP/N3020/W/25/3369300: Abbey Quarry, Linby, NottinghamshireReport | 174 KB | DownloadRead as text |
Follow Planning Committee at Gedling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Oct 2026 | To approve, as a correct record, the minutes of the meeting held on 9 September 2026That the minutes of the above meeting, having been circulated, be approved as a correct record. | Approved | Open |
| 14 Oct 2026 | Application no. 2026/0501 - Richard Herrod Centre, Foxhill Road Central, Carlton, NottinghamshireTo Grant Planning Permission: Subject to the conditions listed for the reasons set out in the report. Conditions The ... | Approved | Open |
| 14 Oct 2026 | Appeal Summary Ref: 6014560 - 31 Mansfield Road, Daybrook, NottinghamshireTo note the information. | Noted | Open |
| 14 Oct 2026 | Appeal Summary Ref: 6013777 - 6 Pateley Road, Woodthorpe, NottinghamshireTo note the information. | Noted | Open |
| 14 Oct 2026 | Future planning applicationsTo note the information. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.