Annual Delivery Plan and Performance Reporting

Noted Committee 2 papers

AI summaryGedling Borough Council notes the 2026/27 Annual Delivery Plan and approves a Legacy Plan wording change, shifting performance reporting from quarterly to four monthly to align with budget monitoring.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedPerformance reporting wording changed from quarterly to four monthly
MoneyNoneNo financial implications from the report
What happens nextFour monthly performance reporting to CabinetRisk reporting to follow the same cycle subject to approval
Who it affectsCouncil committee reporting cyclesCabinet, Overview and Scrutiny, and Audit Committee

What was decided

Council noted the Annual Delivery Plan actions set out at Appendix 1 for 2026/27, the first year of the Gedling Legacy Plan. Report 1.2, P2

Council approved a wording change in the Legacy Plan so that 'Progress update will be published via four monthly reporting' replaces the previous quarterly reference. Report 2.1, P11, P12, P13

Why

Cabinet had already agreed to align budget and performance reporting on a four monthly basis, but the Legacy Plan document still referred to quarterly reporting and so needed updating. Report 1.6, 2.1

A new monthly Budget, Performance and Risk Board has been set up to give more regular oversight, and Overview and Scrutiny Committee had asked for more timely performance information. Report 1.4, P14

The Legacy Plan was adopted in March 2026 in preparation for Local Government Reorganisation, and the Annual Delivery Plan for 2026/27 was approved by Cabinet in April 2026. Report 1.1, 1.2, P21, P22

What happens next

Performance and budget reports will be presented to Cabinet and, where required, Council on a four monthly basis rather than quarterly. Report 1.6, 2.1, P16

Risk management reporting is proposed to follow the same four monthly cycle, subject to review by Audit Committee and approval by Cabinet. Report 1.7

Internal Audit has been advised of the reporting change and raised no objection. Report P14

Options considered

  • Chosen: Approve the Legacy Plan wording change to four monthly performance reporting. Aligns with existing four monthly budget reporting, supports more timely information to committees, and had no objection from Internal Audit Report 1.4, 1.6, 2.1, P14
  • Rejected: Do not approve the Legacy Plan wording change. Four monthly budget reporting is already in place and Overview and Scrutiny Committee preferred more timely performance reporting Report P14

Implications

  • Financial: The report states there are no financial implications arising from it. Report P15
  • Legal: Changes to the Legacy Plan must be decided by Council as the adopting body, while ongoing performance reporting is an executive function reported to Cabinet. Report P16
  • Equalities: An Equality Impact Assessment was prepared for the Gedling Legacy Plan and is in the background papers. Report P17
  • Climate: A Carbon Impact Assessment was prepared for the Gedling Legacy Plan and is in the background papers. Report P18, P19
  • Risk: Risk management reporting is proposed to align with the same four monthly cycle, subject to Audit Committee review and Cabinet approval. Report 1.7
  • Other: The Legacy Plan has been drawn up having regard to Local Government Reorganisation and the Annual Delivery Plan supports LGR preparation. Report P24, P25

Who and where

  • Cabinet, as the recipient of the new four monthly performance and budget reports Report 1.6, P16
  • Overview and Scrutiny Committee, which previously received quarterly performance reports after a delay Report 1.3, P14
  • Audit Committee, which is to consider aligning risk reporting to the same cycle Report 1.7
  • The new monthly Budget, Performance and Risk Board providing oversight Report 1.4
  • Internal Audit, which has been informed of the change Report P14

Timeline

  • March 2026: Council adopted the new Gedling Legacy Plan as part of budget setting Report 1.1, P22
  • 23 April 2026: Cabinet approved the Annual Delivery Plan for 2026/27 Report 1.2, P21
  • 10 June 2026: Council noted the Annual Delivery Plan and approved the Legacy Plan wording change Report P1, P2

Plain English for the jargon

  • Gedling Legacy Plan: The council's priorities document for the next two years, adopted in March 2026 ahead of Local Government Reorganisation
  • Annual Delivery Plan: The yearly plan setting out detailed actions, KPIs and milestones that deliver year one of the Legacy Plan
  • Local Government Reorganisation (LGR): The process of restructuring local government, which the council is preparing for
  • Budget, Performance and Risk Board: A new internal board that meets monthly to oversee performance, budget and risk together
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item24

Resolved

That Council: 1. Note the Annual Delivery Plan actions at Appendix 1 2. Approve minor changes to the Legacy Plan to reflect changes in reporting of performance and budget as detailed within the report
Word for word from the decision Gedling published for this meeting. Source: democracy.gedling.gov.uk

Follow this further

Built from Gedling's papers

What the report saysPro

Report to Council

Recommendation

That Council:

1) Note the Annual Delivery Plan actions at Appendix 1 2) Approve minor changes to the Legacy Plan to reflect changes in reporting of performance and budget as detailed within the report

Background

1.1In March 2026 as part of the Council’s budget setting, Council adopted a new Gedling Legacy Plan which sets out the Council’s priorities for the next two years as the organisation prepares for Local Government Reorganisation.

1.2Sitting underneath the Gedling Legacy Plan is the Council’s Annual Delivery Plan. The Annual Delivery Plan for 2026/27 sets out how the Council intends to deliver on year one of the Gedling Legacy Plan through more detailed actions which are underpinned by key performance indicators and milestones. The Annual Delivery Plan and associated actions provide the golden thread from the Legacy Plan to each service area to ensure the organisation is working towards the Council’s key priorities at an operational level. The Annual Delivery Plan was approved by Cabinet in April 2026.

1.3Updates on the actions, KPIs and milestones have previously been reported quarterly to Cabinet and Overview and Scrutiny committee. Often, quarterly reports are received by Overview and Scrutiny Committee some time after the quarter has ended which can make it difficult to provide up to date feedback.

1.4Currently budget reporting is undertaken every 4 months to Cabinet and where 1.5 required Council. As part of governance improvements the Council has established a Budget, Performance and Risk Board to better align performance and budget monitoring with risk management, this board meets monthly to ensure more regular oversight and responsive performance, budget and risk management.

1.6Cabinet agreed, as part of the Annual Delivery Plan process to align budget and performance reporting on a four monthly basis in order to ensure more detailed effective reporting in a more timely manner to relevant committees. This change in reporting requirements is not currently reflected in the Legacy Plan document which still references quarterly reporting of performance.

1.7As part of the current review of the Council’s Risk Management Strategy, reporting on risk will also, subject to review by Audit Committee and approval by Cabinet be aligning with budget and performance reporting on a four monthly basis. Risk management reports are taken to Audit and Overview and Scrutiny Committees.

2 Proposal

2.1It is proposed that Council note the contents of the Annual Delivery Plan at Appendix 1 and agrees minor amendments to the Legacy Plan to reflect changes to reporting of performance from quarterly to four monthly. This alignment of budget and performance monitoring with increased oversight from the Budget, performance and Risk Board will ensure better, more timely and accurate reporting. 2.2 The final page of the Legacy Plan document under the heading “How we will measure our performance” currently states as follows:

“Progress update will be published via quarterly reporting”

It is proposed that Council approve the wording as follows:

“Progress update will be published via four monthly reporting”

Alternative options

Members could determine not to approve the changes to the Legacy Plan to reflect performance reporting changes, however, four monthly reporting of budget has already been in place for some time and feedback from Overview and Scrutiny Committee was that more timely reporting of performance to Committees was preferred. Internal Audit have been advised of the proposed changes and had no objection to the change in approach.

Financial implications

There are no financial implications arising out of this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Annual Delivery Plan and Performance ReportingReport 219 KB DownloadRead as text
PDF
Annual Delivery Plan Actions 2026-27Appendix 1 265 KB Download

At this meeting

Whole meeting

Who was there

34 of 46 attended
SB
Councillor Sandra BarnesMayor, present
PA
Councillor Pauline AllanDeputy Mayor, present
MA
Councillor Michael AdamsCommittee Member, present
RA
Councillor Roy AllanCommittee Member, present
JA
Councillor Jane AllenCommittee Member, present
SB
Councillor Stuart BestwickCommittee Member, present
DB
Councillor David BrocklebankCommittee Member, present
JC
Councillor John ClarkeCommittee Member, present
JC
Councillor Jim CreamerCommittee Member, present
AD
Councillor Andrew DunkinCommittee Member, present
BE
Councillor Boyd ElliottCommittee Member, present
DE
Councillor David EllisCommittee Member, present

All 46 on the meeting page

On this subject at Gedling

Search all
  1. Annual Delivery Plan and Performance ReportingThis decision
  2. Performance Indicators and Annual Delivery Plan 2026/27Approved
  3. Housing Delivery Action Plan 2022Noted
  4. Gedling Borough Housing Delivery Action Plan and Five Year Housing Land Supply Assessment 2019Noted
  5. Gedling Borough Housing Delivery Action Plan and Five Year Housing Land Supply Assessment 2019Approved
  6. Health and Wellbeing Delivery PlanNoted

More from Gedling Council

All decisions
MeetingDecisionOutcome
10 Jun 2026 To approve, as a correct record, the minutes of the meeting held on 20 May 2026That the minutes of the above meeting, having been circulated, be approved as a correct record. Approved Open
10 Jun 2026 Gedling Local Development Plan - publication draft1) That Council approve the Publication Draft Gedling Local Development Plan (Appendix 1) and Sustainability Appraisa... Approved Open
10 Jun 2026 Appointment of Independent Person and Reserve Independent PersonThat Members: 1. Approve the appointment of David Walsh as Independent Person and John Baggaley as Reserve Independen... Approved Open
10 Jun 2026 Changes to the ConstitutionThat Members approve amendments to the Constitution as shown at Appendix 1. Approved Open
20 May 2026 To elect a Mayor for the ensuing yearThat Councillor Barnes be elected Mayor for the Borough of Gedling for the ensuing year. The Mayor adjourned the meet... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies