AI summaryGedling Cabinet approved the Annual Treasury Activity Report 2025/26, showing £749,332 in investment income and total external debt of £10.812m, and referred it to Full Council for approval.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedAnnual Treasury Activity Report 2025/26
Money£749,332 investment incomeEquated rate 4.06% on investments
What happens nextFull Council approvalRequired by regulations under the Local Government Act 2003
Who it affectsAll wardsCouncil-wide treasury position and future unitary transition

What was decided

Cabinet approved the Annual Treasury Activity Report for 2025/26, confirming the Council operated within all approved Prudential and Treasury Indicators throughout the year. Report P7, P51

The report was referred to Full Council for approval, as required by the regulations. Report 1.1, P7

Why

The Council is required by regulations issued under the Local Government Act 2003, the CIPFA Treasury Management Code, and the CIPFA Prudential Code to produce an annual review of treasury activity and outturn Prudential Indicators. Report 1.1

The report meets the requirement for an Annual Review describing 2025/26 activity compared to the strategy approved by Council on 5 March 2025. Report P9, P11

What happens next

The report is to be presented to Full Council for approval as the next stage of the statutory process. Report 1.4

Member training on treasury management continues to be delivered by the Chief Financial Officer and MUFG Asset Services as required. Report 1.5

The Government decision on the future unitary arrangement is expected in July 2026, with the Council continuing to manage budgets prudently in the interim. Report 8.1

The money

  • £10,812 Total external debt at 31 March 2026 (£000s) Report P22
  • £18,443 Capital Financing Requirement at 31 March 2026 (£000s) Report P22
  • £12,540 Total investments at 31 March 2026 (£000s) Report P23
  • £1,728 Net investment position at 31 March 2026 (£000s) Report P23
  • £749,332 Investment interest generated during 2025/26 (including £41,479 dividends) Report P46
  • £41,479 Dividend from CCLA Local Authority Property Fund for 2025/26 Report P44, P46
  • £5,448,183 Capital expenditure outturn for 2025/26 Report P53
  • £18,443,491 Projected closing CFR for 2025/26 Report P56
  • £893,935 Certified value of CCLA property fund investment at 31 March 2026 Report P45
  • £1,000,000 Initial CCLA LAPF investment made on 30 November 2017 Report P44

Options considered

  • Chosen: Approve the Annual Treasury Activity Report 2025/26 and refer it to Full Council. Required to comply with the Council's Treasury Management Strategy Statement and statutory regulations Report P7, 11.1
  • Rejected: Fail to present an Annual Treasury Activity Report. Would contravene the requirement of the Council's Treasury Management Strategy Statement Report 3.1

Implications

  • Financial: The Council operated within all approved Prudential and Treasury Indicators throughout 2025/26, with investment interest of £749,332 generated at an equated rate of 4.06%. Report P46, P51
  • Legal: The report is required under regulations issued under the Local Government Act 2003, the CIPFA Treasury Management Code, and the CIPFA Prudential Code. Report 1.1
  • Risk: The CCLA property fund investment fell in value by £59 during 2025/26, with a statutory override in place until 2028/29 neutralising the impact on the General Fund. Report P45, P83
  • Other: Local Government Reorganisation continues to create uncertainty for medium term planning, with the Government's decision on the future unitary arrangement expected in July 2026. Report 8.1
  • Other: There are no equalities or carbon reduction/environmental sustainability implications arising from the report. Report 6.1, 7.1

Who and where

  • All wards of Gedling Borough Council Report P1
  • Future unitary authority that Gedling Borough Council will become part of Report 8.1
  • Council taxpayers and service users, given the Council's continued internal borrowing and investment strategy Report P66, P67

Timeline

  • 30 November 2017: Initial £1m investment made in the CCLA Local Authority Property Fund Report P44
  • 13 February 2025: Cabinet considered the Annual Treasury Management Strategy Statement Report P9
  • 5 March 2025: Full Council approved the Treasury Management Strategy Statement for 2025/26 Report P9, P40
  • 2025/26: No new loans taken out, no loans redeemed, no temporary borrowing arranged, no PWLB rescheduling undertaken Report P32, P35, P36
  • 12 June 2026: Report approved by the Chief Financial Officer and Monitoring Officer Report P111, P112
  • 25 June 2026: Cabinet decision to approve and refer the report to Full Council
  • July 2026: Expected Government decision on future unitary arrangement Report 8.1

Plain English for the jargon

  • CFR: Capital Financing Requirement, the Council's underlying borrowing need for capital expenditure
  • TMSS: Treasury Management Strategy Statement
  • CIPFA: Chartered Institute of Public Finance and Accountancy
  • PWLB: Public Works Loans Board, a government body that lends to local authorities
  • MMF: Money Market Fund, a pooled highly diversified investment vehicle
  • CCLA LAPF: CCLA Local Authority Property Fund, a property investment fund for local government
  • MRP: Minimum Revenue Provision, a statutory annual charge for the economic consumption of capital assets
  • MUFG: MUFG Asset Services, the Council's treasury management advisers
  • IFRS 9: International Financial Reporting Standard 9, governing financial instruments accounting
  • CIES: Comprehensive Income and Expenditure Statement
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item122

Resolved

That: 1. Cabinet approved the Annual Treasury Activity Report for 2025/26 and referred it to Full Council for approval, as required by the regulations.
Word for word from the decision Gedling published for this meeting. Source: democracy.gedling.gov.uk

Follow this further

Built from Gedling's papers

What the report saysPro

Report to Cabinet

Wards affected

All

Purpose

To inform Members of the outturn in respect of the 2025/26 Prudential Code Indicators, and to advise Members of the outturn on treasury activity, both as required by the Council’s Treasury Management Strategy.

Key Decision

This is not a key decision.

Recommendation

That:

1. Members approve the Annual Treasury Activity Report for 2025/26 and refer it to Full Council for approval, as required by the regulations.

Background

1.1The Council is required by regulations issued under the Local Government Act 2003 to produce an annual treasury review of its activities, and the actual Prudential and Treasury Indicators for 2025/26. This report meets the requirements of both the CIPFA Code of Practice on Treasury Management (the Code) and the CIPFA Prudential Code for Capital Finance in Local Authorities (the Prudential Code). 1.2 For 2025/26 the minimum reporting requirements were that the Full Council should receive the following reports:

• An Annual Treasury Management Strategy Statement (TMSS) in advance of the year. This was considered by Cabinet on 13 February 2025 and subsequently approved by Full Council on 5 March 2025.

• A Mid-Year Treasury Update report. In accordance with best practice, Members will note that, as in previous years, triannual monitoring reports for treasury activity have been provided and that this exceeds the minimum requirements.

• An Annual Review following the end of the year describing the activity compared to the strategy. This report is in fulfilment of this requirement.

1.3The regulatory environment places responsibility on Members for the review and scrutiny of treasury management policy and activities. The Annual Treasury Activity Report provides details of the outturn position for treasury activities during the year, and highlights compliance with the Council’s policies, previously approved by Members.

1.4The Council has complied with the requirement under the Code to give prior scrutiny to all the above treasury management reports by submitting them to Cabinet before they are reported to Full Council.

1.5Member training on treasury management issues is undertaken by the Chief Financial Officer as it is needed in order to support Members’ scrutiny role. In addition, the Council’s treasury advisers, MUFG Asset Services (MUFG), periodically deliver more detailed training sessions for Members at the request of the Chief Financial Officer.

2 Proposal

2.1Summary of the economy and interest rates during 2025/26

2.1.1 During 2025/26, the UK economy remained weak but resilient, with only modest growth. Real GDP increased by around 0.1% quarter-on-quarter and 1.0% year-on-year, while retail sales showed some recovery towards the end of the period. Inflation remained above the Bank of England’s 2% target, with CPI at around 3.5%, peaking at 3.8% during the summer before easing slightly. Labour market conditions softened, with vacancies falling and wage growth slowing, although pay continued to rise faster than inflation. 2.1.2 In response to this backdrop, the Bank of England reduced Base Rate by 0.75 percentage points over the year, moving from 4.50% at the start of 2025/26 to 3.75% by December 2025. Rate cuts were made in May, August and December 2025, after which rates were held steady into early 2026 because of ongoing inflation concerns.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Annual Treasury Activity Report 2025/26Report 313 KB DownloadRead as text
PDF
Treasury Activity 2025/26Appendix 1 118 KB Download
PDF
Prudential and Treasury Management Indicators 2025/26Appendix 2 106 KB Download

At this meeting

Whole meeting

Who was there

7 of 15 attended
JC
Councillor John ClarkeChair, present
JH
Councillor Jenny HollingsworthVice-Chair, apologies
KF
Councillor Kathryn FoxCommittee Member, present
VM
Councillor Viv McCrossenCommittee Member, present
MP
Councillor Marje PalingCommittee Member, present
LP
Councillor Lynda PearsonCommittee Member, present
HW
Councillor Henry WheelerCommittee Member, present
KR
Councillor Kyle Robinson-PayneCommittee Member, present
MH
Mike HillOfficer, in attendance
FW
Francesca WhyleyOfficer, in attendance
NO
Natalie OseiOfficer, in attendance
ST
Sarah TromanOfficer, in attendance

All 15 on the meeting page

On this subject at Gedling

Search all
  1. Annual Treasury Activity Report 2025/26This decision
  2. Prudential Code Indicator Monitoring 2025/26 and Treasury Activity Report for the period ended 30 November 2025Noted
  3. Prudential Code Indicator Monitoring 2025/26 and Treasury Activity Report for the Period April 2025 to July 2025Noted
  4. Prudential Code Indicator Monitoring 2025/26 and Treasury Activity Report for the Period April 2025 to July 2025Noted
  5. Annual Treasury Activity Report 2024/25Approved
  6. Annual Treasury Activity Report 2024/25Approved

More from Gedling Cabinet

All decisions
MeetingDecisionOutcome
16 Jul 2026 To approve, as a correct record, the minutes of the meeting held on 25.06.26.That the minutes of the above meeting, having been circulated, be approved as a correct record. Approved Open
16 Jul 2026 Forward Plan1) To note the report. Noted Open
16 Jul 2026 Housing Strategy 2026-2030That Cabinet: 1) Noted the representations and comments received during the public consultation, together with the of... Noted Open
16 Jul 2026 Gedling BC Asset Management Plan 2026-2028THAT Cabinet: 1) Agreed to adopt the Asset Management Strategy 2026-2028 at appendix 1. 2) Approved the proposals for... Agreed Open
16 Jul 2026 Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies