AI summaryGedling Planning Committee approves proposed constitutional amendments for the new national planning delegation scheme, to be considered by full Council on 30 September.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedAmendments to Section 10 and Section 19b
MoneyNo new costMet from existing budgets
What happens nextFull Council on 30 SeptemberFinal approval needed by 31 October 2026
Who it affectsPlanning applicants and committee membersCommittee to reduce from 16 to 12 members
What was decided
The Committee approved the proposed amendments to the Planning Committee Rules in Section 10 of the Constitution and to the Planning delegations in Section 19b, and recommended them to Council for approval. Report 2.1
The Committee will reduce from 16 to 12 members, made up of 7 Labour, 2 Conservative, 1 Liberal Democrat and 1 from each of the two Independent groupings. Report 2.4, P33, P34
The Chair of Planning Committee, or the Vice Chair in their absence, will be the Nominated Member, and the Director of Place, or equivalent officer, will be the Nominated Officer. Report 2.5, P38, P40
Why
The Government is introducing a National Scheme of Delegation through new regulations that take effect on 31st October 2026, and local planning authorities must have new arrangements in place by that date or risk decisions being ruled unlawful. Report 1.1, 1.3, 5.1, P53
The reforms restrict planning committees to no more than 13 members, introduce mandatory member training, and group applications into Schedule 1 (delegated to officers) and Schedule 2 (referable to committee if the Gateway Test is met). Report 1.4, 1.5, 1.6, 1.7, 1.8
The Gateway Test requires either a significant economic, social or environmental issue for the local area, or a significant planning matter having regard to the development plan and other material considerations. Report 1.9, 1.10, P15, P16
What happens next
The recommendations will go to the full Council meeting on 30 September, where further amendments to the proposals can be proposed and debated. Report 3.1, P50
The new arrangements must be in place by 31st October 2026, when the Town and Country Planning (Discharge of Local Planning Authority Functions) (England) Regulations 2026 come into force. Report 1.3, 5.1, P53
A written record of every application considered by the Nominated Member and Nominated Officer for referral to committee will be maintained and reported in the next available Planning Committee agenda. Report 2.5, P41
Options considered
Chosen: Refer the proposed amendments to full Council on 30 September for approval, with the option for further amendments to be proposed there. Required to meet the 31st October 2026 deadline and comply with the new regulations Report 2.1, 3.1, P50
Implications
Legal: Decisions taken after 31st October 2026 that are not in accordance with the new Regulations may be considered unlawful and susceptible to challenge through the courts. Report 1.3, 5.1, P53
Financial: No financial implications: the changes are being met from existing budgets. Report 4.1
Equalities: No equalities implications: the legislation will be applied across all local planning authorities in England. Report 7.1
Climate: No carbon reduction or environmental sustainability implications at this stage; these will be considered in the determination of individual planning applications. Report 8.1, P56
Other: A consistent approach to determining planning applications will be adopted by authorities ahead of Local Government Reorganisation. Report 6.1
Who and where
Members of Gedling Planning Committee, reducing from 16 to 12 Report 2.4, P33, P34
Applicants for planning permission, listed building consent, advertisement consent and tree preservation order consent Report 1.6, 1.7, P12
Council planning, legal and democratic services officers involved in the Working Group Report 1.13
Residents and other parties who would have engaged with committee decision making on smaller applications now handled by officers Report 1.6, 1.7, P44
Timeline
15 July 2026: Planning Committee approved establishment of a politically balanced Working Group Report 1.12, P22
6 August 2026: Working Group met with members and officers to discuss proposed amendments Report 1.13
5pm on 17 August 2026: Deadline for Working Group members to provide further comments on revised drafts Report 1.14
9 September 2026: Planning Committee meeting at which this decision was taken
31st October 2026: New Regulations come into force; new arrangements must be in place by this date Report 1.3, 5.1, P53
Plain English for the jargon
Schedule 1: Planning functions that must be delegated to officers for a decision, unless the application is an own-interest application.
Schedule 2: Planning functions that may be referred to a planning committee only if the Gateway Test is met, or it is an own-interest application and the nominated officer and nominated member agree.
Gateway Test: Statutory test in Regulation 5 requiring at least one of two criteria: a significant economic, social or environmental issue for the local area, or a significant planning matter having regard to the development plan and other material considerations.
Nominated Member: A member of the council nominated to act under Regulations 5 and 6 for considering referrals and own-interest applications; here the Chair of Planning Committee, or the Vice Chair in their absence.
Nominated Officer: An officer of the council nominated to act under Regulations 5 and 6; here the Director of Place, or equivalent officer with extensive professional planning experience.
Own-interest application: A planning application in which the local planning authority itself is the applicant, handled under Regulation 6.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item27
Resolved
RESOLVED to: Agree the proposed amendments to the Planning Committee Rules within Section 10 of the Constitution and to the Planning delegations within Section 19b Scheme of Delegation of the Constitution and recommends to Council for approval. Recorded Vote Title Type Recorded Vote text Result Ad-Hoc Carried View Recorded Vote for this item
Word for word from the decision Gedling published for this meeting.Source: democracy.gedling.gov.uk
1.1Government is introducing a National Scheme of Delegation through the Town and Country Planning (Discharge of Local Planning Authority Functions) (England) Regulations 2026 (“the Regulations”). Sections 319ZZC–319ZZF have been inserted into the Town and Country Planning Act 1990 (as amended) to empower the Secretary of State to define which functions are delegated to officers and which are reserved for planning committees or sub-committee.
1.2Its purpose is to provide greater clarity and consistency about which planning functions are decided by officers and which require committee oversight, reducing variation and uncertainty across Local Planning Authorities
1.3Local Planning Authorities are expected to have the new arrangements for decision-making in place by 31st October 2026. Decisions taken on or after that date must be taken in accordance with the Regulations and if not, could be considered by the Courts to have been unlawful.
1.4The reforms will include a restriction on the number of elected members on Planning Committees to not exceeding 13 and mandatory training will be introduced for members of Planning Committees.
1.5The introduction of a National Scheme of Delegation which will group planning applications into 2 schedules;
1.6Schedule 1 of the Regulations sets out all the functions which must be delegated to officers for a decision (unless it is an own-interest application). These include a number of categories of applications for planning permission for:
- householder development (as defined in the Town and Country Planning (Development Management Procedure) (England) Order 2015) - minor commercial development (as defined in the Town and Country Planning (Development Management Procedure) (England) Order 2015) - minor residential development which is defined in the Regulations as: - development that includes only dwellings and development for the purposes incidental to the enjoyment of dwellings, comprises at least one but not more than nine dwellings, and is to be carried out on a site having an area smaller than 0.5 hectares - development of a building containing flats, or development within the curtilage of such a building, for any purpose incidental to the enjoyment of the flats or any of them but excludes development in respect of a building containing flats, or development within the curtilage of such a building, that involves either or both of a change of use or change to the number of flats - an application for any consent, agreement or approval required by or under a planning permission, development order or local development order for minor residential applications.
Along with a range of other consents which include:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.