Gedling Borough Council
Audit Committee, Tuesday 20 October 2026 at 5.30pm

BDO Internal Audit Progress Report

Noted Finance 3 papers

AI summaryGedling Audit Committee noted completion of the 2026/27 internal audit plan and approved BDO's conformance assessment against the new Global Internal Audit Standards. Two finalised reviews covered S106 and Community Infrastructure Levy, and the Digital Strategy.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNoted 2026/27 audit plan progress; approved BDO conformance
MoneyVarious sums reportedS106 and CIL balances and Digital Strategy capital cost
What happens nextFindings actions by April 2027Target dates range October 2026 to March 2027
Who it affectsPlanning, Digital, MembersOfficers, ward councillors and audit assurance

What was decided

The committee noted delivery of the 2026/27 internal audit plan, with executive summaries of the S106 and CIL report and the Digital Strategy report, all audits finalised. Report P4

The committee approved BDO's conformance assessment and an alternative condition for Standard 8.4 of the Global Internal Audit Standards, set out in Annex 1. Report P4

Why

BDO's overall assessment shows it is fully conforming with 8 of 9 essential conditions and generally conforming with one, relating to Standard 8.4 External Quality Assessment. Report P4

The Global Internal Audit Standards require the Chief Audit Executive to report periodically on the function's ability to fulfil the Purpose of Internal Auditing. Report P4

What happens next

Officers to develop a documented escalation and recovery process for overdue developer contributions, with a target date of April 2027. Report P29

Officers to consider bi-annual reporting to Ward Members on developer contributions, with a target date of April 2027. Report P30

Digital Strategy team to define the role of finance within governance, with a target date of November 2026, and develop succession planning, with a target date of March 2027. Report P45, P47, P48

The money

  • £1.095m S106 capital contributions collected by the Council in 2024/25 Report P19
  • £168,404 S106 revenue contributions collected by the Council in 2024/25 Report P19
  • £486,985 S106 capital contributions spent in 2024/25 Report P19
  • £53,009 S106 revenue contributions spent in 2024/25 Report P19
  • £3.849m S106 capital contributions retained at end of 2024/25 Report P19
  • £709,321 S106 revenue contributions retained at end of 2024/25 Report P19
  • £2.564m CIL receipts retained at end of 2024/25 Report P19
  • £2.013m CIL earmarked for strategic infrastructure in the Borough Report P19
  • £550,610 CIL neighbourhood portion held by the Council at end of 2024/25 Report P19
  • £1.987m Budgeted capital investment in Digital Strategy systems, 2024/25 to 2026/27 Report P37

Options considered

  • Chosen: Note progress and approve BDO's conformance assessment with alternative condition for Standard 8.4. BDO's Essential Conditions assessment and completion of the 2026/27 plan were presented for Audit Committee approval. Report P4

Implications

  • Risk: S106/CIL review: Moderate design and Substantial effectiveness, with one Medium finding on reliance on developer self-notification for trigger events and two Low findings on recovery of overdue contributions and reporting to Ward Members. Report P17, P18, P26, P29, P30, P32
  • Risk: Digital Strategy review: Substantial design and Moderate effectiveness, with three Medium findings on resource capacity, succession planning and finance sign-off at programme board. Report P35, P36, P44, P45, P48, P49
  • Governance: BDO is fully conforming with 8 of 9 Global Internal Audit Standards essential conditions; the alternative condition for Standard 8.4 relates to the External Quality Assessment covering all BDO clients rather than the Council alone. Report P4
  • Staffing: The Digital Strategy is heavily reliant on the Assistant Director of Digital, Data and Technology, with limited documented succession or handover arrangements. Report P45
  • Legal: Recommendation that the Council seek legal advice on using existing datasets for monitoring S106 trigger events, to confirm compliance with the Data Protection Act 2018. Report P26, P28
  • Other: Local government reorganisation has been paused by the Government following new legal advice, announced on 7 September 2026; local elections in May 2027 will proceed within existing boundaries. Report P56

Who and where

  • Community Infrastructure Levy and Principal Planning Officer, responsible for overseeing S106 and CIL agreements Report P19
  • Planning, Housing and Legal Services through the S106 Affordable Housing Monitoring Group Report P25
  • Elected Ward Members, who will receive bi-annual reporting on developer contributions Report P30
  • The Transformation Team, ICT team and the Director for Transformation overseeing the Digital Strategy Report P37
  • Integrated Care Boards and other healthcare providers receiving S106 healthcare contributions Report P25
  • Developers and applicants, who are subject to S106 and CIL obligations and recovery processes Report P19, P29

Timeline

  • October 2026: Audit Committee receives the BDO Internal Audit Progress Report Report P2
  • October 2026: Target date for updating the Digital Strategy RAID log on resource capacity Report P44
  • November 2026: Target date for defining finance role in Digital Strategy governance Report P48
  • December 2026: Infrastructure Funding Statement 2025/26 due to be published Report P19
  • End of 2026: BDO's External Quality Assessment due, with outcomes to be reported to the Audit Committee Report P70
  • January 2027: Draft Leisure Transformation report and planned work on Housing and Homelessness and Waste and Recycling Report P10, P11, P12
  • March 2027: Planned work on Main Financial Systems (Payroll and Treasury Management) and Local Government Reorganisation; succession planning actions for Digital Strategy Report P13, P14, P47
  • April 2027: Target dates for S106/CIL data use, recovery guidance and ward member reporting actions Report P28, P29, P30
  • May 2027: Local elections to proceed within existing council boundaries Report P56

Plain English for the jargon

  • S106: Section 106 legal agreements between local authorities and developers to mitigate the impact of new developments, often including financial contributions
  • CIL: Community Infrastructure Levy, a charge local authorities can levy on new developments to fund infrastructure projects
  • GIAS: Global Internal Audit Standards in the UK Public Sector
  • EQA: External Quality Assessment, an independent review of internal audit conformance required under Standard 8.4
  • CAE: Chief Audit Executive, the senior officer responsible for the internal audit function
  • RAID: Risk, Action, Issues and Dependencies log used to manage programme delivery
  • BTDA: Business Design and Technology Authority, an internal board that decides on system design across the Council
  • LGR: Local Government Reorganisation, the planned creation of new unitary authorities
  • ICB: Integrated Care Board, a healthcare body that may receive S106 healthcare contributions collected by the Council
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item20

Resolved

To note the progress (completion) of the delivery against the 2026/27 Internal Audit Plan, including executive summaries of the Section 106 and Community Infrastructure Levy Report and the Digital Strategy Report. 2. To agree and approve BDO’s conformance assessment and the alternative condition for conformance with Standard 8.4 of the GIAS in the Essential Conditions Report (Annex 1).
Word for word from the decision Gedling published for this meeting. Source: democracy.gedling.gov.uk

Follow this further

Built from Gedling's papers

What the report saysPro

Report to Audit Committee

OFFICIAL

Gedling Borough Council Internal Audit Progress Report October 2026 1 INTERNAL AUDIT PROGRESS REPORT

Summary of 2026/27 work

Internal Audit This report is intended to inform the Audit Committee of progress made against the 2026/27 internal audit plan. It summarises the work we have done, together with our assessment of the systems reviewed and the recommendations we have raised. Our work complies with Global Internal Audit Standards in the UK Public Sector. As part of our audit approach, we have agreed terms of reference for each piece of work with the risk owner, identifying the headline and sub-risks, which have been covered as part of the assignment. This approach is designed to enable us to give assurance on the risk management and internal control processes in place to mitigate the risks identified. Internal audit methodology Our methodology is based on four assurance levels in respect of our overall conclusion as to the design and operational effectiveness of controls within the system reviewed. The assurance levels are set out in Appendix 1 of this report and are based on us giving either ‘substantial’, ‘moderate’, ‘limited’ or ‘no’ opinion. The four assurance levels are designed to ensure that the opinion given does not gravitate to a ‘satisfactory’ or middle band grading. Under any system we are required to make a judgement when making our overall assessment. Internal audit plan 2026/27 We have now completed our delivery of the audit plan with all audit reviews finalised. We are pleased to present the following reports to this Audit Committee meeting:  Digital Strategy  Section 106 and Community Infrastructure Levy (S106 and CIL). Essential Conditions We have provided an annex which summarises our Essential Conditions for the Audit Committee’s approval. The new Global Internal Audit Standards require the Chief Audit Executive (CAE) to report to the Audit Committee and senior management periodically to outline the internal audit function’s ability to fulfil the Purpose of Internal Auditing. BDO’s assessment of its internal audit services has recommended that it is fully conforming with 8 out of the 9 essential conditions and is generally conforming with one. The one essential condition where it is not fully conforming relates to Standard 8.4 External Quality Assessment (EQA). This standard requires the CAE to develop a plan for an EQA and discuss the plan with the board. BDO has an EQA performed every 5 years, as required by the standards, however this is across all outsourced internal audit services that it provides across all of its clients, and it is not specific to only the Council. Annex 1 summarises the arrangements in place for conformance against each of the nine essential conditions in the Global Internal Audit Standards.

1 2 INTERNAL AUDIT PROGRESS REPORT

Review of 2026/27 work

AUDIT AUDIT PLANNING FIELDWORK REPORTING DESIGN EFFECTIVENESS COMMITTEE

Digital Strategy October 2026 S M

S106 and CIL October 2026 M S

Leisure January 2027 Draft Report Transformation

Housing and January 2027 Homelessness

Waste and January 2027 Recycling

Main Financial Systems (Payroll March 2027 and Treasury Management

Local Government March 2027 Reorganisation

2 3 INTERNAL AUDIT PROGRESS REPORT

S106 and CIL

CRR Reference: CR010 - PROJECTS Effectiveness Design Opinion S Substantial M Moderate Opinion

Recommendations 0 1 2

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
4a. BDO: Progress Report: October 2026Report 699 KB DownloadRead as text
PDF
4b. BDO: Essential Conditions Report: October 2026Report 509 KB Download
PDF
BDO Internal Audit Progress ReportReport 124 KB Download

At this meeting

Whole meeting

Who was there

0 of 15 attended
RM
Councillor Ron McCrossenChair, expected
RS
Councillor Ruth StrongVice-Chair, expected
SB
Councillor Stuart BestwickCommittee Member, expected
DB
Councillor David BrocklebankCommittee Member, expected
HG
Councillor Helen GreensmithCommittee Member, expected
PH
Councillor Paul HughesCommittee Member, expected
JN
Councillor Julie NajukCommittee Member, expected
JC
Jonathan CaustonCo-Optee, expected
TA
Tina AdamsOfficer, expected
CG
Cayte GoodallOfficer, expected
MH
Mike HillOfficer, expected
FW
Francesca WhyleyOfficer, expected

All 15 on the meeting page

On this subject at Gedling

Search all
  1. BDO Internal Audit Progress ReportThis decision
  2. Internal Auditors (BDO) - Progress ReportNoted
  3. BDO Internal Audit Plan 2025/26 - 2027-28Approved
  4. Internal Audit Progress Report (BDO)Noted
  5. Internal Audit Reports (BDO)Decided

More from Gedling Audit Committee

All decisions
MeetingDecisionOutcome
20 Oct 2026 To approve, as a correct record, the minutes of the meeting held on 23 June 2026That the minutes of the above meeting, having been circulated, be approved as a correct record. Approved Open
20 Oct 2026 Mazars External Audit Draft Annual Report and Audit Strategy Memorandum Report 31 March 2026To note the Audit Strategy Memorandum dated 20 October 2026 and the draft Auditor’s Annual Report for the year ended ... Noted Open
20 Oct 2026 Statement of Accounts 2025-26 and Annual Governance StatementTo note the Council’s unaudited Statement of Accounts for 2025-26 and the key financial matters set out in this repor... Noted Open
20 Oct 2026 Corporate Risk Management Review Period 1 April - July 2026To note the operation of the revised Risk Management Framework, the current corporate risk position and the controls ... Noted Open
23 Jun 2026 To approve, as a correct record, the minutes of the meeting held on 24 February 2026That the minutes of the above meeting, having been circulated, be approved as a correct record. Approved Open