Gloucestershire County Council
Cabinet, Thursday 20 March 2025 at 10.00am

M5 Junction 10 Improvements Scheme – Enabling Works

Approved Executive 2 papers

Cabinet approved this item on Thursday 20 March 2025. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

Cllr David Gray sought Cabinet approval to commence the enabling works (subject to the Development Consent Order being granted by the Secretary of State) for the M5 Junction 10 Improvements Scheme. Having considered all of the information, Cabinet RESOLVED to: Delegate authority to the Executive Director of Economy, Environment and Infrastructure, in consultation with the Cabinet Member for Environment and Planning to: 1. Amend the existing M5 J10 Early Contractor Involvement (ECI) contract via a Deed of Variation to allow for works to be committed under two discrete notices (Enabling works followed by Main works). 2. Thereafter commission the M5 Junction 10 enabling works contract to a maximum value of £25m via the amended M5 J10 ECI contract subject to the Secretary of State approving the Development Consent Order (DCO) and subject to GCC entering into a Deed of Variation to the Grant Determination Agreement with Homes England to allow the use of HIF funding to deliver the enabling works. 3. Approve the application of secured funding including CIL, s106 and / or other funding in so far as those sums are required alongside HIF funding to allow delivery of the M5 J10 enabling works as may be agreed by the Executive Director of Economy, Environment and Infrastructure in consultation with principal scheme funder Homes England. 4. Approve the movement of already allocated unspent GCC capital funding associated with Arle Court Transport Hub, to support delivery of the Housing Infrastructure Fund (HIF) programme of works (including either the A38/A4019 junction improvements at Coombe Hill or the M5 J10 Improvements Scheme) as agreed by the Executive Director of Economy, Environment and Infrastructure in consultation with principal scheme funder Homes England 5. Implement the programme as set out in the timeline section of this report.
Word for word from the decision Gloucestershire published for this meeting. Source: glostext.gloucestershire.gov.uk

Follow this further

Built from Gloucestershire's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
M5 J10 EqIA March CabinetReport 10 MB Copy on its way
PDF
M5 Junction 10 Improvements Scheme: Enabling WorksReport 147 KB Copy on its way

At this meeting

Whole meeting

On this subject at Gloucestershire

Search all
  1. M5 Junction 10 Improvements Scheme – Enabling WorksThis decision
  2. Junction 10 Improvements Scheme – Notice to proceed with Main WorksApproved
  3. M5 Junction 10 Improvements Scheme – Funding UpdateNoted

More from Gloucestershire Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Council Strategy Action Plan Update, and Finance, Performance and Risk Monitoring Report: Q1 2026/27Cllr Colin Hay provided an update to the Quarter 1 end of year forecast for the 2026/27 County Council’s Revenue and ... Noted Open
23 Sep 2026 Draft Gloucestershire Local Transport Plan (LTP), draft Rail Strategy, and draft Active Travel StrategyCllr Roger Whyborn sought Cabinet approval the draft Local Transport Plan (LTP) for public consultation and to delega... Approved Open
23 Sep 2026 Gloucestershire Local Transport Delivery Plan (LTDP)Cllr Roger Whyborn sought Cabinet approval to submit Gloucestershire's LTDP for 2026 /27 - 2029/30 to the Department ... Approved Open
23 Sep 2026 Annual Childcare Sufficiency Duty ReportCllr Ben Evans, on behalf of Cllr Linda Cohen, sought Cabinet approval for Gloucestershire's Childcare Sufficiency Du... Approved Open
23 Sep 2026 SEND Sufficiency Strategy 2026-2031 and Delivery PlanCllr Ben Evans, on behalf of Cllr Linda Cohen, sought Cabinet approval and adoption of the new Special Educational Ne... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies