Future Community and Accommodation-Based Support (CABS) Service Model and Associated Procurement and Commissioning Decisions

Approved Executive 2 papers

AI summaryCabinet approves new Community and Accommodation-Based Support service model, with contracts for 329 bedspaces and a two-month extension of current services until May 2027.

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeApprovedAdopted as the preferred commissioning approach, based on Option 3 of the report.
MoneyNot stated
What happens nextProcurement via call-off contractsUnder the existing Gloucestershire CABS Light Touch Open Framework Agreement.
Who it affectsVulnerable people in GloucestershireIncluding young people aged 16+, adults 18+, care leavers and people facing homelessness.

What was decided

Cabinet adopted the Future CABS Service Model set out in Option 3 of the report as the preferred commissioning approach for CABS services in Gloucestershire.

Cabinet delegated authority to the Director of Public Health and Communities, in consultation with the relevant Cabinet Members, to procure and award call-off contracts for 131 ABS bedspaces for young people aged 16+, 190 ABS bedspaces for adults aged 18+, 8 assessment bedspaces, and countywide Community-Based Support services including specialist floating support for homelessness and vulnerable people.

Cabinet approved a two-month extension of the current CABS contracts from April 2027 to May 2027 to provide continuity pending implementation of the new model.

Why

The decision was sought to approve the future CABS service model, enable procurement of required call-off contracts through the existing framework, and commission further accommodation-based support bedspaces for care leavers and vulnerable young people.

What happens next

The Director of Public Health and Communities will lead implementation, consulting the Cabinet Member for Public Health, Communities and Fire and the Cabinet Member for Children's Safeguarding and Care.

Each awarded call-off contract will run for an initial two years, with options to extend for up to two further periods of one year each (2+1+1 years).

Current CABS contracts will continue under a two-month extension from April 2027 to May 2027 to bridge to the new arrangements.

Options considered

  • Chosen: Option 3: Future CABS Service Model combining revised Community-Based Support and Accommodation-Based Support provision

Implications

  • Legal: Authority to procure and award call-off contracts is delegated to the Director of Public Health and Communities, subject to consultation with named Cabinet Members.
  • Equalities: Service provision explicitly covers care leavers, vulnerable young people, people facing homelessness and individuals in vulnerable circumstances.
  • Staffing: New contracts will operate on a 2+1+1 year term structure, with implications for provider staffing and continuity during the extension period.
  • Risk: A two-month extension of current contracts (1 April to May 2027) is intended to manage continuity risk before the new model begins.

Who and where

  • Young people aged 16+ needing accommodation-based support (131 bedspaces to be commissioned)
  • Adults aged 18+ needing accommodation-based support (190 bedspaces to be commissioned)
  • Care leavers and vulnerable young people (further 50 bedspaces referenced for commissioning)
  • People needing assessment support (8 assessment bedspaces to be commissioned)
  • People facing homelessness or in vulnerable circumstances needing community-based or floating support

Timeline

  • 2026-09-23: Cabinet decision taken to approve the Future CABS Service Model and delegate procurement authority.
  • April 2027 to May 2027: Two-month extension of current CABS contracts to provide continuity pending implementation of the new model.

Plain English for the jargon

  • CABS: Community and Accommodation-Based Support, the council's combined support service framework.
  • ABS: Accommodation-Based Support, providing bedspaces and associated support to people in need.
  • CBS: Community-Based Support, including specialist floating support for homelessness and vulnerable people.
  • Light Touch Open Framework Agreement: A procurement arrangement under which the council can award call-off contracts without a full new tender each time.
  • Call-off contract: A contract awarded under a framework agreement to deliver specific services or provision.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

Cllr Paul Hodgkinson sought Cabinet approval of the future Community and Accommodation-Based Support (CABS) Service Model, including a two-month extension of the current CABS contracts to provide continuity pending implementation of the new model. The report also seeks delegated authority to procure and award a number of call-off contracts required to deliver the approved Future CABS Service Model through the Gloucestershire Community and Accommodation-Based Support (CABS) Light Touch Open Framework Agreement. In addition, it seeks approval to commission a further 50 Accommodation-Based Support bedspaces for care leavers and vulnerable young people. Having considered all of the information, Cabinet noted the report and RESOLVED to: 1. Approve and adopts the Future CABS Service Model set out in Option 3 of this report, comprising revised Community-Based Support Services and Accommodation-Based Support provision, as the preferred commissioning approach for the future delivery of Community and Accommodation-Based Support (CABS) services in Gloucestershire . 2. Delegate authority to the Director of Public Health and Communities, in consultation with the Cabinet Member for Public Health, Communities and Fire and the Cabinet Member for Children’s Safeguarding and Care, to implement the above Future CABS Service Model by: (a) Procuring and awarding as many call-off contracts under the Gloucestershire Community and Accommodation Based Support Light Touch Open Framework Agreement as may be necessary to provide: i. 131 Accommodation-Based Support (ABS) bedspaces for young people aged 16+; ii. 190 Accommodation-Based Support (ABS) bedspaces for adults aged 18+; and iii. 8 assessment bedspaces, Each such call-off contract shall continue for an initial period of two years with options to extend its term for up to two additional periods of one year each (2+1+1 years). (b) Procuring and awarding as many call-off contracts as may be necessary under the Gloucestershire Community and Accommodation Based Support Light Touch Open Framework Agreement to provide countywide Community-Based Support (CBS) services, including specialist floating support for homelessness and individuals in vulnerable circumstances. Each such call-off contract shall continue for an initial period of two years with options to extend its term for up to two additional periods of one year each (2+1+1 years). 3 . Approves a two-month extension to the current CABS contracts between 1 st April 2027 and 31 st May 2027 to provide continuity within service pending implementation of the Future CABS Services model.
Word for word from the decision Gloucestershire published for this meeting. Source: glostext.gloucestershire.gov.uk

Follow this further

Built from Gloucestershire's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
For Cabinet: EqIA: Future CABS Services and Call-Offs 2026_FINALa: CopyReport 460 KB Copy on its way
PDF
Future Community and Accommodation-Based Support (CABS) Service Model and Associated Procurement and Commissioning DecisionsDecisions 238 KB Copy on its way

At this meeting

Whole meeting
2MinutesOn the agenda 4Questions at Cabinet MeetingsOn the agenda 5Council Strategy Action Plan Update, and Finance, Performance and Risk Monitoring Report: Q1 2026/27Noted 6Draft Gloucestershire Local Transport Plan (LTP), draft Rail Strategy, and draft Active Travel StrategyApproved 7Gloucestershire Local Transport Delivery Plan (LTDP)Approved 8Annual Childcare Sufficiency Duty ReportApproved 9SEND Sufficiency Strategy 2026-2031 and Delivery PlanApproved 10Adoption West: New ContractApproved 11Procurement of a support provider to deliver Supported Accommodation at Trevone HouseApproved 12Gloucestershire WorkWell ProgrammeApproved
13Future Community and Accommodation-Based Support (CABS) Service Model and Associated Procurement and Commissioning DecisionsThis decision
14Commission an Expert by Experience (EBE) led Quality Assurance (QA) Programme for health & social care commissioned services for whole adult market.Approved 15Procurement of a Jointly Commissioned Service for Women Experiencing Severe and Multiple DisadvantageApproved 16Replacement of Wheelchair Access Vehicles (WAVS) for Adults and Children’s ServicesApproved 17Extension of Garden Waste Composting ContractsApproved 18Rural Strategic Estate Plan (SEP) 2016-2030 Refresh & Rural Task and Finish Group 2025 UpdateApproved 19Microsoft License RenewalApproved 20Children & Families Capital Programme UpdateApproved 21Agency supply of temporary and permanent staffApproved 22Procurement of breathing apparatus for Gloucestershire Fire and Rescue Service (GFRS)Approved 23Schedule of Proposed DisposalsApproved

More from Gloucestershire Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 Council Strategy Action Plan Update, and Finance, Performance and Risk Monitoring Report: Q1 2026/27Cllr Colin Hay provided an update to the Quarter 1 end of year forecast for the 2026/27 County Council’s Revenue and ... Noted Open
23 Sep 2026 Draft Gloucestershire Local Transport Plan (LTP), draft Rail Strategy, and draft Active Travel StrategyCllr Roger Whyborn sought Cabinet approval the draft Local Transport Plan (LTP) for public consultation and to delega... Approved Open
23 Sep 2026 Gloucestershire Local Transport Delivery Plan (LTDP)Cllr Roger Whyborn sought Cabinet approval to submit Gloucestershire's LTDP for 2026 /27 - 2029/30 to the Department ... Approved Open
23 Sep 2026 Annual Childcare Sufficiency Duty ReportCllr Ben Evans, on behalf of Cllr Linda Cohen, sought Cabinet approval for Gloucestershire's Childcare Sufficiency Du... Approved Open