CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Gosport Borough Council
Community Board, Wednesday 23 January 2019 at 6.00pm

Lee on the Solent Splash Park - Request for Section 106 Funding

Agreed Committee 1 paper

Community Board agreed this item on Wednesday 23 January 2019. Below is the council's own wording, with the papers it was decided on.

Item31

Resolved

That use of developer contributions secured through Section 106 agreements to contribute towards the funding for the Lee on the Solent Splash park project be approved.
Word for word from the decision Gosport published for this meeting. Source: democracy.gosport.gov.uk

Follow this further

Built from Gosport's papers

What the report saysPro

Report to Community Board

Recommendation

That the Board authorises the use of developer contributions secured through Section 106 agreements to contribute towards the funding for the Lee on the Solent Splash park project.

Background

1.1At the meeting of 27 June 2018 the Community Board approved locating the proposed new Splash Park in Lee on Solent in the northern corner of the Beach Road Car Park.

1.2At the meeting of 7 November 2018 the board noted the proposed design and were advised as to the anticipated project timescales.

2 Report

2.1Competitive tenders have been sought in line with the Council’s Financial Standing orders, with two compliant tenders being received as follows:

1. Tender A: £466,035 2. Tender B: £856,005

Subject to the approval of additional funding and Planning consent Tender A, Ustigate Waterplay Ltd. has been confirmed as the Council’s preferred contractor. Officers considered the preferred contractor’s tender submission to be the best submission both in terms of price and quality.

2.2The projected cost of the project, overall, is as follows:

Splash Park tender: £466,035 Relocation of Skate Park: £ 40,960 Installation of utilities: £ 20,000 Installation of Pumping station: £ 20,000 Fees: £ 5,000 TOTAL: £551,995

2.3The existing allocated funding for the project is as follows:

Splash Park capital (6309): £400,000 Public Conveniences capital (6214): £ 30,000

This leaves a funding shortfall of: £121,995

2.4This additional funding is currently available through developer contributions secured by Section 106 Agreements specifically for the provision of open space. It is considered that this proposal is an appropriate use of these funds as it will help to provide a new open air recreational facility that will be available for use by the wider Gosport community and encourage more visitors to the Lee on the Solent seafront.

3 Risk Assessment

3.1If these additional funds are not approved then the project will not be able to proceed in its current form; the scheme would need to be re- designed and reduced in scale which would result in major delays to project delivery.

4 Conclusion

4.1By approving this additional funding the board will enable the project to proceed in its current form and provide a high quality play area for Lee on the Solent and the wider Gosport community.

Financial Services comments: A sum of £400,000 is included within the current capital programme to fund this scheme. The additional funding will be met by transferring £30,000 from the approved Capital Public Conveniences refurbishment programme and £121,995 from unallocated S106 Developer contributions. Legal Services comments: None Crime and Disorder: The local crime prevention officer will be consulted during the design phase of the project in order to reduce the risk of anti- social behaviour. Equality and Diversity: See below EIA: It is considered that no inequalities or discrimination will take place as a result of this project. Service Improvement Plan None implications: Corporate Plan: This project will focus on the strategic priorities to: • Enhance the environment, • Deliver effective services & • Develop the economy. Risk Assessment: See Section 3 Background papers: None Appendices/Enclosures: None Appendix ‘A’ Report author/ Lead Officer: Andrew Morton

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Lee on the Solent Splash Park: Request for Section 106 FundingReport 60 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 16 attended
GB
Councillor Graham BurgessCommittee Member, present
KC
Councillor Kevin CaseyCommittee Member, present
RE
Councillor Richard EarleCommittee Member, present
KF
Councillor Keith FarrCommittee Member, present
SH
Councillor Stephen HammondCommittee Member, present
DK
Councillor David Keith HerridgeCommittee Member, present
MH
Councillor Mark Hookex-Officio, present as substitute
ML
Councillor Mrs Lynn HookCommittee Member, present
MZ
Councillor Mrs Zoe HugginsCommittee Member, present
JH
Councillor Jamie HutchisonCommittee Member, present
RH
Councillor Robert HylandsCommittee Member, present
TJ
Councillor Tony JessopCommittee Member, present

All 16 on the meeting page

On this subject at Gosport

Search all
  1. Lee on the Solent Splash Park - Request for Section 106 FundingThis decision
  2. Lee Hub - Independent Community Library (Lee Hub), 14 High Street, Lee on Solent - Surrender of Existing Lease and Grant of new 26 Year Lease.Approved
  3. Concessions policy & Ice Cream Concessions on Stokes Bay and Lee-on-the-SolentApproved
  4. Acquisition of Lee on Solent and Elson Libraries from Hampshire County Council and Granting Leases of Part of both to Lee-on Solent and Elson Community HubsApproved
  5. Lee-on-the-Solent Splash ParkApproved

More from Gosport Community Board

All decisions
MeetingDecisionOutcome
8 Mar 2022 Minutes of the previous meeting of the Community Board held on 5 January 2022That the minutes of the meeting held on 5 January 2022 be signed as a true and correct record. Decided Open
5 Jan 2022 Minutes of the previous meeting of the Community Board held 3 November 2021that the minutes of the meeting held on 3 November 2021 be signed as a true and correct record. Decided Open
5 Jan 2022 Joint Municipal Waste Management StrategyThat the Board approved the Joint Municipal Waste Management Strategy (JMWMS) Approved Open
3 Nov 2021 Minutes of the previous meeting of the Community Board held on 8 September 2021that the minutes of the meeting held on 8 September 2021 be signed as a true and correct record. Decided Open
3 Nov 2021 Commemorative Bench Seat PolicyThat the Board approved the Commemorative Bench Seat Policy and provided delegated authority to the Head of Streetsce... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies