that the Economic Development Board a gree: 1. The long leasehold disposal of approx. 5.70 acres of land outlined red on the plan at Appendix A of this report in lieu of the approx 5 acres recommended for disposal at Appendix A of the September 2018 Report (attached herewith at Appendix B). 2. To authorise the Chief Executive Officer to enter into a Deed of Variation with the Defence Infrastructure Organisation (DIO), to vary the wording of the existing restrictive covenant affecting the site to permit the site to be used as a retail garden centre and Gateway into the Alver Valley Country Park.
Word for word from the decision Gosport published for this meeting.Source: democracy.gosport.gov.uk
This report is supplemental to the report dated 19th September 2018 and recommends that the Economic Development Board agree:
1. The long leasehold disposal of approx. 5.70 acres of land outlined red on the plan at Appendix A of this report in lieu of the approx 5 acres recommended for disposal at Appendix A of the September 2018 Report (attached herewith at Appendix B).
2. To authorise the Chief Executive Officer to enter into a Deed of Variation with the Defence Infrastructure Organisation (DIO), to vary the wording of the existing restrictive covenant affecting the site to permit the site to be used as a retail garden centre and Gateway into the Alver Valley Country Park. 1.0 Background
1.1The Report to the Economic Development Board report on 19th September 2018 sets out the background content.
1.2The Council's various inter-related and abutting property matters at Grange Farm continue to move forward and complete with a formal Lease now granted to C17th Village and the Rowner Regeneration Scheme Phase 1B residential development and new access road into the site substantially built and on programme for completion at the end of January 2020.
2.0Report
2.1As a result of the marketing of the garden centre opportunity it was identified that operators would require slightly more land for the garden centre than that approved for disposal at the September 2018 Economic Development Board. This slightly greater area of approx. 5.7 acres is shown at Appendix A of this report.
2.2The Council's preference was to dispose of the site on a long leasehold basis. The Council's only capital cost is the provision of an adequate power supply to the site, the cost of which has already been budgeted. Bearing in mind the garden centre operating company will bear all other design and construction costs together with all operating costs going forward, the Council's external valuer recommended that the Council seek an annual rent of £10,000 pa with 5 yearly rent reviews for a term of 99 years OR if greater in any year, 2% of the annual turnover.
2.3The cost of all repairs going forward is the responsibility of the garden centre operating company. There will be no recurring Landlord's costs under the lease. The preceding terms were set out in the marketing particulars and are now agreed with the prospective garden centre operating company.
2.4The Council's Planning team have been involved in discussions and meetings at all stages and are supportive in principle of the enlarged garden centre proposal arising from the change in land area.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.