That the Board approves: The principle of a programme to build social and affordable housing on Council owned land; initially over the next three years but with a long-term objective to build more, as set out in this report; § Associated capital costs to be added to the Capital Programme (for approval by Full Council on 5 th February 2020) of £7.5m; and § Officers to develop associated delivery mechanisms and, in particular, seek to appoint both project management and construction development providers to enable work to commence in the new financial year .
Word for word from the decision Gosport published for this meeting.Source: democracy.gosport.gov.uk
The principle of a programme to build social and affordable housing on Council owned land; initially over the next three years but with a long-term objective to build more, as set out in this report;
Associated capital costs to be added to the Capital Programme (for approval by Full Council on 5th February 2020) of £7.5m; and
Officers to develop associated delivery mechanisms and, in particular, seek to appoint both project management and construction development providers to enable work to commence in the new financial year.
Background
1.1Requirement
1.1.1 The Council already owns 3114 properties (and has a further 308 leasehold properties) as at 31 December 2019. The Council, however, has a significant waiting list of residents seeking homes in the Borough. The waiting list currently stands at almost 1000 households; predominantly centered on family dwellings, particularly two bedroomed properties. There are also specific, unmet, requirements for adapted dwellings for residents with disabilities.
1.1.2 More broadly, the Council also has a need for 170 new homes per annum as outlined in the current adopted Local Plan however this figure is likely to increase when the Local
-1- Plan is revised due to the Government’s new standard methodology for calculating housing need which identifies a requirement of 238 dwellings per annum.
1.1.3 Building new homes in the Borough also enables financial resilience for the Council by adding stock to our Council Tax baseline of properties as well as enabling a greater quantum of rents for the Housing Revenue Account (HRA) and providing resilience to the underlying HRA business plan. The building programme will also help enable the Council to access New Homes Bonus funding from central Government (and also the successor to the Bonus, which the Government will consult on in Spring 2020).
2.0REPORT
2.1Given our waiting list and the other advantages associated with increasing our stock of social and affordable housing, officers have been reviewing where the Council could build homes within the Borough. The Council does own a series of small land parcels across the Borough that could be utilised for this purpose and to enhance their economic value to the Council. The initial sites that will form the first tranche of approximately 30 dwellings to be built are detailed in Appendix A. This is an initial assessment only and will be subject to futher feasibility study both of potential housing density that could be achieved on each site but also any planning implications and risks that would need to be considered in the next stage of the programme.
2.2Our initial assessment is that the series of land parcels identified will provide sufficient capacity for 100 new dwellings to be built over the next three financial years. Officers will continue to review other Council owned land to form part of a longer-term pipeline of building.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Commemorative Bench Seat PolicyThat the Board approved the Commemorative Bench Seat Policy and provided delegated authority to the Head of Streetsce...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.