That the Board approves a contribution of £20,000 towards the stand and seating to be provided at subject to the completion of proper financial due diligence to the satisfaction of the Council’s Section 151 Officer and agreement on the timeframe for implementation of the works.
Word for word from the decision Gosport published for this meeting.Source: democracy.gosport.gov.uk
1.1Having been promoted to the Wessex League, there is a requirement for the Club to provide improved facilities. The Club will be demoted if these improvements are not in place (or committed to, at least), by the end of March 2023. In addition to adult use, the Club currently runs ten youth teams (increasing to fourteen next year) and provides facilities for varied community uses, including children’s parties.
1.2A previous Neighbourhood Community Infrastructure Levy (CIL) grant for £27k was received by the club from the Council in 2019, linked to levering in other external funding, including £100k from the Football Foundation to provide a new pavilion.
1.3Planning permission was granted (ref 20/00061/FULL) in April 2020 to demolish the existing pavilion and erect a single storey replacement pavilion with associated changing rooms together with six new floodlight columns.
1.4Progress has been made towards implementing the facilities, the subject of these earlier awards and the above permission. Floodlighting has been delivered whilst the plans were being progressed for the permanent changing provision and new pavilion. The installation of the floodlights means that the pavilion remains capable of implementation under the existing planning permission. 1.5 The project ran into difficulties during the pandemic due to unforeseen complications with utility connections and ground conditions which have caused delay and increased costs. To avoid losing the £100k, temporary changing facilities were constructed in the interim with the timetable for providing the new pavilion extended by two years.
1.6The temporary changing facilities do not have the benefit of separate planning permission, however, the Council’s Development Manager does not consider that formal enforcement action is expedient as the structure is not considered to cause harm.
1.7In addition to the above, the Club are also now required to provide a stand containing 100 seats. This is estimated to cost £35-£40k, depending on options chosen and including the cost of installation and associated pathways. The club estimate that they can raise around £15k towards these works.
1.8The new stand will require planning permission and there will be a lead in time of 6-8 weeks between order and delivery, therefore, noting the March deadline, the Club have requested assistance from the Council in the form of a £20k contribution in order that it can demonstrate to the League that the required facilities will be in place.
1.9The Club are also in discussions with other organisations with regard financial assistance for the pavilion and the Ministry of Defence with regard securing the ownership of the land on which they are located.
2.0Report
2.1The Neighbourhood element of the Community Infrastructure Levy is intended for use for capital expenditure on the improvement of community facilities and there is £62,990 currently available in the Neighbourhood CIL Fund which is sufficient to provide the level of financial support requested.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.