Resolved
That the Board noted the progress of the following project activities: · Procurement of the contractor · Update to the financial position · Planning and Environmental Licences acquisition
Community & Environment Board noted this item on Wednesday 19 June 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Board noted the progress of the following project activities: · Procurement of the contractor · Update to the financial position · Planning and Environmental Licences acquisition
1.1The Stokes Bay Seawall Replacement Project is required to replace 135m of failed seawall at Stokes Bay, Gosport and protect key infrastructure, including a public highway (managed by Hampshire Council Council), from flooding and erosion risk (see Appendix A for location plans). The benefits of the project include:
Reducing flood and erosion risk impacts to important infrastructure, including a local road. Addressing long-term and ongoing health and safety risks. Supporting sustainable investment and mitigating the need for reactive, unsustainable emergency maintenance. Reinstatement of public amenities, recreation, and access for a strategic open area in accordance with the Gosport Borough Local Plan. Improve physical and mental health and well-being.
The project also aligns with the Stokes Bay Feasibility Study's preferred design option for this section of Stokes Bay’s frontage. Therefore, the works are considered the implementation of the appraisal’s initial urgent recommendation and the first stage of delivering a solution to reduce the risk of flooding and erosion within the wider Stokes Bay frontage.
1.2The Community and Environment Board previously received a report on January 10th, 2024, where approval was gained for authority to be delegated to the Chief Executive: a) to undertake the procurement of the construction works and the evaluation of bids received, and b) in consultation with the Section 151 Officer, to award a contract for the construction works to the preferred bidder, subject to sufficient funding, and c) agree on project financial tolerances with the delivery officer for the purpose of administering the construction contract, and d) to undertake the construction stage of the project.
1.3This report provides an update on project progress, covering the financial summary, environmental licencing and consents, procurement, and the planned construction programme. Additionally, it includes an update on the Stokes Bay Feasibility Study.
2.0Report
2.1Progress Update:
Since January 2024, the project team has: Completed the tender process and appointed a Contractor, Suttle Projects. Awarded the Construction Contract. Submitted documentation to discharge all planning pre-commencement conditions. Received the draft Marine Licence and conditions. Updated the detailed design to mitigate a clash between the existing seawall and the new sheet pile seawall. Updated the project website, installed “advance notice of works” signage on site and issued letters to residents and businesses in proximity to the site.
2.2Finance:
The project has spent £129,987 to date. The spend has funded project critical activities including detailed design, financial analysis, Local Levy submission, project reporting, project and contract management, procurement, and stakeholder engagement.
The project budget totals £1,259,317. This consists of contributions of £450k and £50k from Gosport Borough Council and Hampshire respectively and £759,317 of Local Levy funding.
Suttle Projects have been appointed as the Contractor and the forecast outturn has been updated with the Construction Contract Price. The project is currently forecast to be delivered within budget.
The project is currently considered fully funded and the financial position is summarised in Tables 1 and 2 below:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Stokes bay Seawall Replacement ProjectReport | 458 KB | DownloadRead as text |
Follow Community & Environment Board at Gosport and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Minutes of the meeting of the board held on 17 June 2026 and 15 July 2026That the minutes of the meetings held on 17 June 2026 and 15 July 2026 were signed as a true and correct record. | Decided | Open |
| 16 Sep 2026 | Project Integra Joint Municipal Waste management Strategy- A Resources and Waste Strategy for HampshireThat the Board approved: i) The revised project Integra Joint Municipal Waste Management Strategy 2026 to 2035 (A Res... | Approved | Open |
| 17 Jun 2026 | Election of ChairmanThat Councillor Ricketts is elected as Chairman for the municipal year 2026-2027 | Decided | Open |
| 17 Jun 2026 | Election of Vice ChairmanThat Councillor Bond was elected as Vice Chairman for the municipal year 2026-2027 | Decided | Open |
| 17 Jun 2026 | Minutes of the meeting of the board held on 25 February 2026That the minutes of the meeting held on 25 February were signed as a true and correct record. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.