Approved Committee 2 papers

AI summaryGosport Policy and Organisation Board approves amendments to the Design Supplementary Planning Document to update waste and recycling storage guidance in line with the Government's Simpler Recycling policy.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedUpdates to bin capacity and storage guidance
MoneyNoneNo financial implications identified
What happens nextUpdated SPD to be published onlineWith explanatory note of changes
Who it affectsPlanning applicants and decision makersIn Gosport Borough

What was decided

The Board approved amendments to the adopted Design Supplementary Planning Document as set out in Appendix 1.

The amendments are factual updates to reflect the Council's latest collection arrangements necessitated by Government policy, so no formal public consultation was required. Report 2.6, 3.2

Why

From April 2026 the Government's Simpler Recycling policy mandates changes to recycling, requiring additional bins and altering collection arrangements in the Borough. Report 1.4

The Design SPD needed updating so it reflects the latest bin requirements and collection arrangements, ensuring high quality development and assisting applicants and decision makers. Report 1.3, 3.1

Officers in Streetscene, Development Management and Planning Policy reviewed the SPD internally and proposed a small number of specific factual amendments. Report 2.4

What happens next

If approved, updates to the Design SPD will be made and published online along with an explanatory note setting out the changes made. Report 2.6, 4.1

The updated SPD will come into force immediately. Report 4.1

Options considered

  • Chosen: Approve the proposed amendments to the Design SPD. To ensure guidance reflects the latest collection arrangements and Government policy requirements. Report 2.6, 4.1
  • Rejected: Undertake formal public consultation on the amendments. The amendments are very specific factual updates reflecting the Council's latest collection arrangements, so no consultation was considered necessary. Report 2.6, 3.2

Implications

  • Other: The SPD will reflect changes to refuse and recycling collection in the Borough, helping applicants and decision makers plan for required storage. Report 3.1, 4.1
  • Climate: Recycling in line with the Government's Simpler Recycling policy will assist in reducing waste and lowering greenhouse gas emissions. Report P21
  • Equalities: No expected equality and diversity implications from the amendments. Report P20
  • Legal: No legal service comments; the SPD remains a material consideration when determining planning applications. Report 2.1, P19
  • Risk: The risk of not updating the guidance is that development proposals do not adequately plan for required refuse and recycling storage. Report 3.1

Who and where

  • Planning applicants submitting development proposals in Gosport Report 1.2, 2.1
  • Planning decision makers assessing applications Report 1.2, 2.1
  • Residents using waste and recycling collection services in the Borough Report 1.4, 2.5
  • Owners and developers of Houses in Multiple Occupation (HMOs) Report 2.5
  • Commercial sites (clarification that the local authority does not collect commercial waste and recycling) Report 2.5

Timeline

  • 6 February 2014: Original Design SPD adopted at the Economic Development Board following 2013 public consultation. Report 2.1, P24
  • 12 November 2025: Community and Environment Board considered an update on Simpler Recycling implementation progress. Report 1.4, P28
  • 26 November 2025: Policy and Organisation Board considered and approved the amendments to the Design SPD.
  • From April 2026: The Government's Simpler Recycling policy mandates changes to recycling and collection arrangements in the Borough. Report 1.4
  • Immediate on publication: Updated Design SPD will come into force once published online. Report 4.1

Plain English for the jargon

  • SPD: Supplementary Planning Document, a planning document that provides detailed guidance alongside the Local Plan.
  • NPPF: National Planning Policy Framework, the Government's national planning policy framework.
  • Simpler Recycling: Government policy mandating changes to recycling collections from April 2026, requiring additional bins.
  • HMO: House in Multiple Occupation.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item30

Resolved

That the Board approves the amendments to the adopted Design Supplementary Planning Document, as set out in Appendix 1.
Word for word from the decision Gosport published for this meeting. Source: democracy.gosport.gov.uk

Follow this further

Built from Gosport's papers

What the report saysPro

Report to Policy and Organisation Board

Background

1.1The National Planning Policy Framework (NPPF) sets out that the creation of high quality, beautiful and sustainable buildings and places is fundamental to what the planning and development process should achieve.

1.2The Council’s adopted Local Plan, in Policy LP10, recognises the importance of good design in development proposals and sets out general standards against which planning applications are assessed. The Council’s adopted Design Supplementary Planning Document (SPD) is linked to Policy LP10 and provides detailed design guidance alongside the Local Plan to guide applicants and decision makers.

1.3A key part of good design is ensuring waste and recycling storage is well- designed. The Council’s Design SPD seeks to ensure that waste and recycling storage is safe, accessible and convenient for the intended users and integrated into the built design. The SPD sets out detailed guidance for developments on the requirements for refuse and recycling storage and its collection.

1.4From April 2026, the Government’s Simpler Recycling policy mandates changes to recycling which will alter collection arrangements in the Borough and result in the requirement for additional bins. An update on progress made to implement the changes was recently considered at the Community and Environment Board (12 November 2025). To ensure the Design SPD reflects the latest arrangements, it is considered necessary to make amendments to the SPD (as set out in Appendix 1) and issue an updated version. 2.0 Report

Adopted Design SPD

2.1The Design SPD was adopted at the Economic Development Board of 6 February 2014 following a six-week public consultation in 2013. The SPD provides a planning framework to provide design guidance and is a material consideration when determining planning applications.

2.2The Design SPD can be distilled into sixteen ‘Key Design Principles’. Key Design Principle 12 relates to waste, recycling and cycle storage and states:

2.3The Access, Parking and Services chapter of the SPD, specifically pages 51 to 53, sets out design details for refuse and recycling and covers the following matters: • Council collection arrangements; • Waste/recycling storage capacity; • External storage requirements for single dwellings and communal properties; • Arrangements for collecting wheeled bins; • Road design to accommodate refuse freighters; and • Arrangements for commercial sites;

Proposed amendments

2.4Much of the adopted text covering refuse and recycling remains relevant with only a small number of changes proposed. The Design SPD has been reviewed internally by Officers in Streetscene, Development Management and Planning Policy and a number of amendments proposed.

2.5The amendments to the SPD can be summarised as: • Updates to the bin capacity requirements (this includes a third 240 litre container, a 7 litre kitchen caddy internally within the dwelling, and a 25 litre food waste recycling container); • Text to clarify the appropriate waste bins for communal waste (including limiting food bins to 140 litres due to the weight and density of food waste); • Text to clarify the requirements for Houses in Multiple Occupation (HMOs); • Updated refuse fleet dimensions; and • Clarification that the local authority does not collect commercial waste and recycling.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Amendments to the adopted Design Supplementary Planning DocumentSupplementary 195 KB DownloadRead as text
PDF
Proposed amendments (Final): showing changesAppendix 1 169 KB Download

At this meeting

Whole meeting

Who was there

8 of 8 attended
SP
Councillor Stephen PhilpottCommittee Member, present
PC
Councillor Peter ChegwynChairman, present
JH
Councillor Jamie HutchisonCommittee Member, present
RH
Councillor Robert HylandsVice-Chair, present
PR
Councillor Philip Raffaelli CB FRCPCommittee Member, present
MJ
Councillor Mrs June CullyCommittee Member, present
KC
Councillor Kirsty CoxCommittee Member, apologies, sent representative
SH
Councillor Stephen HammondCommittee Member, present as substitute

More from Gosport Policy and Organisation Board

All decisions
MeetingDecisionOutcome
15 Jul 2026 Transformation & Savings Task and Finish GroupThat That the Board: 1) Approves the establishment of a Transformation & Savings Task and Finish Group. 2) Approves t... Approved Open
1 Jul 2026 Minutes of the meeting of the board held on 23 March 2026That the minutes of the meeting held on 23 March 2026 be signed as a true and correct record. Decided Open
1 Jul 2026 Election of vice chairThat Councillor Meenaghan be Vice Chairman of the Policy and Organisation Board. Decided Open
1 Jul 2026 Interim Appointment of Director of Finance (Section 151 Officer (S.151))That the Board approves the appointment of the candidate found to most appropriately meet the requirements set out in... Approved Open
1 Jul 2026 Local Government Reorganisation (LGR) - Appointment to Joint Committees to support South East Unitary Authority preparationsThat the Board:- (a) appoints the Chairman of the Policy & Organisation Board to attend the Joint Committee for South... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies