Construction of Coastal Defence Scheme at Alverstoke

Approved Committee 1 paper

AI summaryGosport's Community and Environment Board has approved restarting the Alverstoke coastal defence scheme, now fully funded by the Environment Agency at £7.6M extra, with completion expected by end of 2029.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedDelivery resumes, updates at milestones
Money£8.7M total scheme cost£7,631,604 new EA grant, no council funds
What happens nextProject initiation stage beginsThree year programme to complete by end 2029
Who it affects130 properties in AlverstokeProtected from 1 in 100 year flood for 50 years

What was decided

The Board approved restarting delivery of the Alverstoke coastal defence scheme, with the project team reporting back to the Board at key project milestones.

Why

Construction was paused in 2022 after buried high voltage cables, cost inflation and material supply problems pushed the forecast beyond the £1,105,000 budget, and the funding gap could not be closed at that time. Report 1.4, 1.5, 1.6

The need for the scheme was reinforced in April 2024 when Storm Pierrick flooded around 65 homes and five commercial properties in Alverstoke. Report 1.8

The Environment Agency approved an updated business case on 18 March 2026, unlocking £7,631,604 of additional Flood Defence Grant in Aid and closing the funding gap, so no Gosport Borough Council capital funds are needed. Report 2.1, 4.2

What happens next

A project initiation stage will start, covering set up, financial controls, programme management, design review and community re-engagement through an updated communications plan. Report 2.4, 2.5

The project will then move through design updates, site investigations, buried utility work, new licensing and consenting including a planning application, and procurement before construction. Report 2.6

A detailed delivery plan will be produced during initiation; the scheme is expected to take three years and be built by the end of 2029, with progress reports to the Board at key stages. Report 2.7

The money

  • £1,105,000 Original total scheme budget including contingency set in 2021 Report 1.3
  • £907,629 Spent since 2018 on development, design, licensing, consenting and previous construction period Report 1.7
  • £7,631,604 Additional Flood Defence Grant in Aid funding from the Environment Agency following March 2026 business case approval Report 2.1
  • £8.7M Forecast total scheme cost including spend to date and risk contingency Report 2.2, 4.2
  • £111,800 Estimated operation and maintenance costs over a 50-year period Report 2.3

Options considered

  • Chosen: Approve restart of the Alverstoke coastal defence scheme and receive progress reports at key milestones. Funding gap now closed by Environment Agency grant, scheme reduces flood risk to 130 properties, no council capital funds required Report 2.1, 4.2

Implications

  • Financial: No Gosport Borough Council capital funds are required for construction; the scheme sits within the current approved Capital Programme. Report 2.1, 4.2
  • Risk: A live risk register carries forward lessons from the previous construction phase; key risks are buried services, below-ground conditions, environmental consenting, community reaction and local government reorganisation. Report 3.0, 3.1, 3.2, P21
  • Equalities: The completed scheme will maintain and enhance public access along the causeway and reduce negative financial and mental health impacts of flooding on the community. Report P25
  • Climate: The scheme will reduce tidal flood risk to residents and the impact of sea level rise, and will include environmental enhancements. Report P25
  • Legal: New licensing, consenting and a new planning application will be needed, which may take additional time under local government reorganisation. Report 2.6, P21
  • Other: Crime and disorder: no change expected, as there is no change in use and no new non-flood infrastructure. Report P25

Who and where

  • 130 properties in Alverstoke benefiting from reduced flood risk over the next 50 years Report 1.1, 2.1
  • The Alverstoke community, including 65 homes and five commercial properties flooded during Storm Pierrick in April 2024 Report 1.8
  • Causeway users, who will keep and see enhanced public access Report P25
  • Gosport Borough Council, as scheme client and operator of the road flood gate Report 2.3

Timeline

  • 2018: Outline business case approved by the Environment Agency Report 1.3
  • 10 February 2021: Preferred works contractor approved by the Community Board Report 1.3
  • January 2022: Construction of the scheme started, estimated at six months Report 1.3
  • April 2022: Decision taken to pause construction works to avoid exceeding approved budget Report 1.5
  • August 2022: Site reinstated to pre-works condition and reopened to the public Report 1.6
  • 1 March 2023: Board report confirmed £907,629 spent on the project to date Report 1.7
  • 8 April 2024: Storm Pierrick caused flooding of around 65 homes and five commercial properties in Alverstoke Report 1.8
  • 27 February 2026: Board told additional Environment Agency funding had been allocated and updated business case submitted Report 1.9
  • 18 March 2026: Environment Agency approved the updated business case, unlocking £7,631,604 of grant funding Report 2.1
  • 17 June 2026: Community and Environment Board approved restart of the scheme
  • End of 2029: Scheme expected to be built, subject to a three-year delivery programme Report 2.7

Plain English for the jargon

  • 1 in 100-year flood event (1% Annual Exceedance Probability): A flood level with a 1% chance of being exceeded in any given year, the design standard for the scheme.
  • Flood Defence Grant in Aid: Central government funding administered by the Environment Agency for flood and coastal erosion risk management projects.
  • Shoreline Management Plan (2010): Strategic document setting out long-term policy for managing the coastline from which the Alverstoke scheme is derived.
  • Optimism bias: An allowance added to cost estimates under HM Treasury guidance to counter the systematic tendency to understate costs.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

That the Board approved the restart of delivery of the Alverstoke Coastal Defence scheme and that the project team reports back to the Board at key project milestones.
Word for word from the decision Gosport published for this meeting. Source: democracy.gosport.gov.uk

Follow this further

Built from Gosport's papers

What the report saysPro

Report to Community & Environment Board

Background

1.1The proposed scheme will provide protection against a 1 in 100-year flood event (1% Annual Exceedance Probability) to reduce flood risk to 130 properties in Alverstoke over the next 50 years. The scheme comprises provision of a new flood wall and road flood gate.

1.2Strategically, the scheme is an important part of Gosport Borough's adopted plans under two main strategic documents, and from which the scheme is derived - the Shoreline Management Plan (2010) and the River Hamble to Porchester Flood and Erosion Risk Management Strategy (2016).

1.3An outline business case for the scheme was approved by the Environment Agency in 2018. The scheme then progressed through detailed design stage, full consenting and works procurement. A preferred works contractor was approved by the Community Board on 10 February 2021. The total scheme budget including contingency was set at £1,105,000. Construction of the scheme started in January 2022, with an estimated six-months’ duration.

1.4During construction several risks were realised including buried high voltage cables which significantly impacted the safety of the construction, delayed the programme and increased costs. The site work also coincided with unprecedented challenges from cost inflation and supply of construction materials. These increased the forecast outturn cost, and which would have exceeded the approved budget, including the risk contingency.

1.5Risk mitigation could not identify a viable alternative to keep the project within the approved budget. A decision was taken in April 2022 to pause construction works on site to ensure the approved budget was not exceeded, to protect the council. Extra funding was sought from the Environment Agency to close the funding gap.

1.6In August 2022, the site was reinstated back to a pre-works condition and was reopened to the public as the funding gap had not been closed.

1.7Further updates were given to the Community and Environment Board in 2022 whilst the scheme remained on pause. A report was provided to the Board on 1 March 2023 to provide further details on the project expenditure to date and funding. That report confirmed that £907,629 had been spent since 2018 on the project development stage, detailed design, historic licensing, consenting and the previous construction period.

1.8On the 8 April 2024, the need for the flood scheme was reinforced when an area of the Alverstoke community was flooded due to an exceptionally high tide from Storm Pierrick. Around 65 homes and five commercial properties were flooded with many vehicles written off. The flooding led to overnight evacuation of many homes, causing significant distress and disruption to the community.

1.9At the Community and Environment Board on 27 February 2026, it was reported that the scheme had been allocated additional Environment Agency funding and an update to the 2018 business case had been submitted to secure £7.6M of additional funding.

2.0Report: Alverstoke Coastal Defence Scheme update

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Construction of Coastal Defence Scheme at AlverstokeReport 121 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 11 attended
JW
Councillor Julie WesterbyCommittee Member, present
TF
Councillor Thomas FinnCommittee Member, present
SR
Councillor Stevyn RickettsCommittee Member, present
RB
Councillor Robbie BeechCommittee Member, present
CB
Councillor Clare BondCommittee Member, present
TJ
Councillor Tony JessopCommittee Member, present
TK
Councillor Taylor KirkhamCommittee Member, apologies, sent representative
PS
Councillor Philip SparrowCommittee Member, present
MZ
Councillor Mrs Zoe Huggins BEMex-Officio, in attendance
KB
Councillor Kirsten BradleyCommittee Member, present
CT
Councillor Colin TowellCommittee Member, present as substitute

More from Gosport Community & Environment Board

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the meeting of the board held on 17 June 2026 and 15 July 2026That the minutes of the meetings held on 17 June 2026 and 15 July 2026 were signed as a true and correct record. Decided Open
16 Sep 2026 Project Integra Joint Municipal Waste management Strategy- A Resources and Waste Strategy for HampshireThat the Board approved: i) The revised project Integra Joint Municipal Waste Management Strategy 2026 to 2035 (A Res... Approved Open
17 Jun 2026 Election of ChairmanThat Councillor Ricketts is elected as Chairman for the municipal year 2026-2027 Decided Open
17 Jun 2026 Election of Vice ChairmanThat Councillor Bond was elected as Vice Chairman for the municipal year 2026-2027 Decided Open
17 Jun 2026 Minutes of the meeting of the board held on 25 February 2026That the minutes of the meeting held on 25 February were signed as a true and correct record. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies