That the minutes of the meeting held on 26 March 2026 were signed as a true and correct record. A Member queried the minute under Any Other Business as he felt that it did not reflect fully what was said by the previous Chairman . It was agreed to seek advice from the Borough Solicitor and Monitoring Officer.
Word for word from the decision Gosport published for this meeting.Source: democracy.gosport.gov.uk
Public Document Pack Standards & Audit Sub Board 26 March 2026
A MEETING OF THE STANDARDS & AUDIT SUB BOARD WAS HELD ON 26 MARCH 2026
Councillors Cox, [name removed], Hutchison, Hylands, Meenaghan and Raffaelli (Substituting for Philpott)
40. APOLOGIES FOR NON ATTENDANCE
Apologies for non-attendance were received from Councillor Philpott who was substituted by Councillor Raffaelli.
41. DECLARATIONS OF INTEREST
There were none
42. MINUTES OF THE MEETING OF THE SUB BOARD HELD ON 22 JANUARY 2026
RESOLVED: That the minutes of the meeting held on 22 January 2026 were signed as a true and correct record.
In answer to a Members question regarding the People’s Park officers advised that a report would be taken to P&O Board once updated costs from contractors had been received.
43. DEPUTATIONS- STANDING ORDER 3.4
There were none
44. PUBLIC QUESTIONS - STANDING ORDER 3.5
There were none
45. DATA BREACH REPORT JAN 1-DEC 31 2025
Consideration was given to a report by the Data Protection Officer (DPO) informing the Sub Board of data breaches that occurred between January 1st 2025 and December 31st 2025, and updating on the remedial actions taken to prevent future incidents.
The DPO introduced his report by advising that the results for GBC were consistent with authorities of similar size. The breaches that occurred were low impact, contained quickly with none needing to be reported to the ICO. In line with other authorities human error accounted for all of the breaches.
Members were advised that some of the breaches had led to improvements in policy and procedures and a new data protection Sharepoint site had resulted in better reporting of breaches.
In answer to a Member’s question, the DPO advised that he felt the increase in breaches against the same period in the previous year was mainly due to an improvement in
1 Standards & Audit Sub Board 26 March 2026
recording. He explained that he had been holding in person training, which had received excellent feedback, and created posters explaining how to report breaches that had already had a positive impact with only 2 breaches reported so far in 2026.
Members were advised that housing run a number of systems, none of which can create email direct from the data held, so clients email addresses have to be entered manually. With many residents sharing surnames the system was open to mistakes. The DPO explained that over a test period of 180 days, housing had received on average 2,126 emails per day.
In answer to a Members question asking if it was possible to apply any extra labels or rules to emails that would reduce the risks associated with breaches due to incorrect information being sent by email, officers advised that there are tools in the new Microsoft licensing that could be investigated when this is implemented.
Members wished to thank the DPO for the training he has delivered and to recognize that it seems to have had an impact.
RESOLVED: That the Standards and Audit Sub Board:
1. Noted that there were twenty data breach incidents that occurred during the period January 1st 2025 and December 31st 2025, as referenced in appendix A. This is an increase in incidents from the previous year (14). 2. Noted that no incidents required notification to the Information Commissioners Office (ICO)
46. INTERNAL AUDIT PROGRESS REPORT 1 APRIL 2025 TO 19 FEBRUARY 2026
Consideration was given to a report by the Chief Internal Auditor (CIA) updating the Sub Board on the progress of the Audit Plan 2025/26 agreed March 2025 to the Members with responsibility for governance.
The CIA introduced his report by updating the figures to show that 25 audits have been issued and I is in draft. The Waste Contract audit has been moved to the 2026-2027 plan to reflect the new requirements.
It was agreed to invite the Head of Housing to address the next meeting and advise on progress of audit actions.
Members were advised that the team was on course to complete the plan by the end of the period 2025/26.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.