Gravesham Borough Council
Community Services Cabinet Committee, Tuesday 13 November 2012 at 7.30pm

Swale Borough Council Audit Review of the South Thames Gateway Building Control Partnership

Noted Executive 2 papers

Community Services Cabinet Committee noted this item on Tuesday 13 November 2012. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

Resolved that the report be noted by the Committee.
Word for word from the decision Gravesham published for this meeting. Source: democracy.gravesham.gov.uk

Follow this further

Built from Gravesham's papers

What the report saysPro

Report to Community Services Cabinet Committee

Background

Building Control is an advisory and enforcement function which ensures that the construction of new buildings, and alterations and extensions to existing buildings, are completed in accordance with the health, safety and convenience of the people in and around the buildings. Private and commercial developers are required to obtain building regulations approval for building works. Successful applications are subject to works inspection at key stages, for which fees are payable.

A building control partnership was set up between Gravesham Borough Council, Medway Council and Swale Borough Council in October 2007. The Partnership, named the South Thames Gateway (STG) was originally agreed for a 5 year term and was extended in December 2011 for a further 5 years. The Partnership is hosted by Medway Council and all of staff have been transferred to Medway Council.

The Partnership brings together the main functions of the Building Control service - the building regulation service and a public protection service - and provides a consultancy service for advice relating to discretionary services such as energy, fire risk, access and Code for Sustainable Homes and Party Wall surveying work.

The STG Partnership is led by a Joint Authority Committee advised by a steering group of senior officers. The Committee will be chaired by Swale Councillor, Gerry Lewin from June 2012.

The income for the whole partnership from fees is estimated to be £1,102,052.

The annual cost of the STG Partnership for 2012/13 is estimated to be £352k. Swale Borough Council contributes 27% (£95k) towards this cost. The current partnership business case estimates that Swale’s contribution will reduce by 7.8% by 2014/15.

This audit will review the adequacy of arrangements in relation to Swale Borough Council’s responsibilities and commitments.

2. AUDIT OBJECTIVES

• To identify and evaluate the governance arrangements surrounding the building control partnership

• To consider the financial arrangements surrounding the building control partnership (fee and non fee earning services)

• To establish whether the building control service provided through the partnership enables the Council to meet its statutory responsibilities

• To establish whether the building control service provided through the partnership enables the Council to meet its non-statutory, fee earning, value for money and customer care performance objectives

1 3. MANAGEMENT SUMMARY

The review considered the adequacy of the governance arrangements surrounding the building control partnership; the adequacy of the financial arrangements surrounding the building control partnership and whether the partnership enables the Council to meet its statutory and non statutory responsibilities for building control.

It is concluded that the controls surrounding the Building Control Partnership provides a substantial level of assurance. This assurance level has been awarded because there are strong controls in place but a few minor improvements would be beneficial. (See appendix B for definitions of assurance levels.)

Recommendations have been made within the report to ensure that the Council continues to fulfil its statutory obligations for the building control function in the future. The main issues arising are:

• The provision of the building control service through a partnership arrangement has not been fully risk assessed from Swale’s perspective.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
STG audit Appx 2Report 210 KB DownloadRead as text
PDF
Swale Borough Council Audit Review of the South Thames Gateway Building Control PartnershipReport 73 KB Download

At this meeting

Whole meeting
11MinutesOn the agenda 13Performance Update - Quarter Two 2012-13 (July 2012 – September 2012)On the agenda 5Appendix 1On the agenda
14Swale Borough Council Audit Review of the South Thames Gateway Building Control PartnershipThis decision

More from Gravesham Community Services Cabinet Committee

All decisions
MeetingDecisionOutcome
5 Jun 2018 Local Air Quality Management (LAQM)Officers commence the process of stakeholder and public consultation necessary for the revocation of the AQMA declara... Decided Open
5 Mar 2015 Review of current Statement of Policy for Hackney Carriage and Private Hire LicensingThe draft statement of policy for hackney carriage (taxi) and private hire licensing, as put before Business and the ... Approved Open
26 Jan 2015 Gravesham Communities and Neighbourhoods (CAN) Grant Scheme Second Tranchethat the list of applications and grant funding allocation recommendations, as set out in the schedule attached to th... Decided Open
26 Jan 2015 Review of current Statement of Policy for Hackney Carriage (Taxi) and Private Hire LicensingIt was agreed that the draft statement of policy for hackney carriage (taxi) and private hire licensing, with the ame... Agreed Open
2 Sep 2014 Gravesham CAN Grant Scheme Awards (2014/15 Tranche 1)that the decisions suggested by the Panel regarding the list of applications and grant funding allocation, as detaile... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies