Finance and Audit Committee, Tuesday 9 April 2013 at 7.30pm

Corporate Risk Register

Noted Finance 3 papers

Finance and Audit Committee noted this item on Tuesday 9 April 2013. Below is the council's own wording, with the papers it was decided on.

Item114

Resolved

Resolved that (i) Members noted the updated Risk Management Strategy; (ii) Members considered the 2013-14 with the above amendments.
Word for word from the decision Gravesham published for this meeting. Source: democracy.gravesham.gov.uk

Follow this further

Built from Gravesham's papers

What the report saysPro

Report to Finance and Audit Committee

Classification: Part 1 – Public

Key Decision: No

Gravesham Borough Council

Report to: Finance & Audit Committee

Date: 9 April 2013

Reporting officer: Julie Gibbs, Assistant Director (Finance)

Subject: Strategic Risk Management – Risk Management Strategy and Corporate Risk Register 2013-14

Purpose and summary of report:

To present the Council’s Risk Management Strategy and draft Corporate Risk Register for 2013-14 to Members for consideration.

Recommendations: Members are requested to:

1. Note the updated Risk Management Strategy attached at appendix two, and; 2. Consider the Corporate Risk Register 2013-14 attached at appendix three, providing comments/suggestions as necessary to the Cabinet.

1. Introduction

1.1Members will be conscious of the continued emphasis on good corporate governance within public organisations and that sound risk management arrangements are a key component of good governance. This report presents Cabinet Members with the outcomes from the annual review of the council’s strategic risk management arrangements in the shape of the updated Risk Management Strategy and the draft Corporate Risk Register for 2013-14.

1.2As in previous years the Risk Management Strategy and Corporate Risk Register will be published on the council’s website.

Finance & Audit Committee – 9 April 2013 Strategic Risk Management – Risk Management Strategy and Draft Corporate Risk Register 2013-14 2. Risk Management Strategy

2.1The Risk Management Strategy sets out the council’s intentions for managing risk, the primary intention being to ensure that the council does not expose itself to risks above an acceptable level. The strategy is reviewed and updated each year to reflect any changes in the council’s strategic risk management arrangements.

2.2On 1st April 2012 the Financial Services Department became responsible for administering the Risk Management Framework on behalf of the authority.

2.3The Risk Management Strategy for 2013-14 has been updated to include full details along with any supporting tools that are relevant to the councils risk management arrangements so that they are incorporated within one document. Therefore the strategy includes the following additional information:

2.3.1 An explanation of why “Good” risk management is important.

2.3.2 Details of the Risk Management process that has been adopted by the authority.

2.3.3 How the authority’s governance arrangements link to the councils Risk Management Strategy.

2.3.4 Brief outline of the major elements of Strategic and Operations risks facing Gravesham Borough Council.

2.3.5 A copy of the Risk Matrix used to score risks.

2.3.6 A copy of the Guidance used for assessing the likelihood and impact of risks.

2.3.7 A table illustrating the roles and responsibilities of various key individuals and groups in relation to risk management.

2.3.8 Details of the annual risk management reporting programme.

2.4The Risk Management Strategy therefore sets out the approach that has been adopted for identifying, evaluating, managing and recording risks to which the council is exposed. The strategy will continue to be reviewed and updated each year to reflect any future changes in the councils risk management arrangements.

2.5Grant Thornton’s December 2012 publication - “Towards a Tipping Point” states that local authorities must improve their efficiency and productivity, reduce their costs and have sustainable medium term financial plans to ensure their financial health remains robust during austerity.

2.6In response to these findings the main aim of Financial Services department is to promote risk management as the central part of Strategic, Operational and Financial management. This aim is to be achieved by utilising the results of the recent Risk Audit undertaken by Zurich Municipal which will be circulated to Management Team and Service Managers responsible for all departments that were involved in the audit. The results will be used to:

2.6.1 Recognise what can go wrong and thereby cause losses.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
DRAFT Corporate Risk Register 2013-14: version for FA: 090413Appendix Three 448 KB Download
PDF
Risk Management Strategy 2013-14: version for FA: 090413Appendix Two 139 KB Download
PDF
Corporate Risk RegisterReport 86 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Gravesham

Search all
  1. Corporate Risk RegisterThis decision
  2. Development of the Corporate Risk Register 2026-2027Approved
  3. Corporate Risk Register 2026/27Approved
  4. Corporate Fraud Risk RegisterDecided
  5. Development of the Corporate Risk Register 2024-2025Approved
  6. Corporate RiskApproved

More from Gravesham Finance and Audit Committee

All decisions
MeetingDecisionOutcome
14 Jul 2026 The Audit Plan for Gravesham Borough Council - Year ending 21 March 2026It was agreed this be taken back to Grant Thornton to advise on how assurances could be provided for this asset. Asse... Agreed Open
25 Feb 2026 Statement of Accounts 2024/25 and Letter of RepresentationResolved that Members: considered the Statement of Accounts for 2024/25 and agreed that the Chair of the Finance and ... Agreed Open
25 Feb 2026 Review of Accounting Policies for 2025/26Resolved that Members endorsed the use of the Accounting Policies as outlined at Appendix One to this report, subject... Decided Open
25 Feb 2026 IA Charter ReviewResolved that Members approved the Charter presented at appendix two. Approved Open
25 Feb 2026 Internal Audit Plan 2026/27 (Q1-Q2)Resolved that Members approved the Internal Audit Plan 2026-27 (Q1-Q2) presented at appendix two. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies