Budget Monitoring Report 2013/14 (Out-turn)

Agreed Finance 1 paper

Finance and Audit Committee agreed this item on Tuesday 15 July 2014. Below is the council's own wording, with the papers it was decided on.

Item17

Resolved

Agreed carried forward items totalling £180k within the General Fund Revenue to 2014/15, as detailed in section 3.9 of the report; · Working Balances as at 31 March 2014 totalling £5.6m, including the £3.25m minimum working balances as determined in the Council’s Medium Term Financial Strategy; · Final Balance of Specific Reserves Items totalling £2.3m; · Housing Revenue Account (HRA) showing shortfall of £1,500,000 against the Original Budget. Key variances are detailed in section 7 of the report including the financing of the PV Panels capital project not included in the original forecast budget and accounts for much of the deficit in the year; · Housing Capital Monitoring account showing an underspend of £1.2m, details of spend shown in section 8 of the report. At the request from Members, the Service Manager (Finance) agreed to detail in future Budget Reports the Working Balances, Carry Forward Items and Specific Reserves for the Housing Revenue Account. Following a question from Members, the Service Manager (Finance) agreed to confirm and circulate to Members, the actual compensation amount received from Network Rail, as mentioned in section 3.5.1 of the report. Members noted the Final Budgeting Monitoring report 2013/14 and the information contained within the report.
Word for word from the decision Gravesham published for this meeting. Source: democracy.gravesham.gov.uk

Follow this further

Built from Gravesham's papers

What the report saysPro

Report to Finance and Audit Committee

Background

1.1This report provides the final budget outturn for the year, summarising variances from the 2013-14 Original Budget reported to the Cabinet on 4 February 2013 and approved by Full Council on 21 February 2013. The report complements the draft 2013-14 Financial Statements for the authority, which will be considered by the Finance & Audit Committee at its meeting on 15 July 2014.

1.2The Original Budget for 2013-14 represented a net revenue budget of £13,200,190 for the General Fund, with this fully funded from Central Government Grant (in the form of Revenue Support Grant (RSG) and Localised Support for Council Tax Grant), retained National Non-Domestic Rates, Council Tax, and Fees & Charges.

1.3The table in Section two of the report summarises the variances against Original Budget by directorate, with more detailed explanations of any major variances given in the narrative that follows.

1.4Section seven details the management actions that have contributed to the council producing a surplus in 2013-14. 2. 2013-14 General Fund Revenue Budget Outturn Position

2.1The final position of the General Fund Revenue Budget is shown in the table below. Variance between Original Final Budget & Final Budget Out-turn Out-turn Directorates 2013-14 2013-14 (Under)/Over- £ £ Spend £

DIRECTORATES Chief Executive 889,550 977,751 88,201 Housing and Regeneration 2,974,420 2,409,377 (565,043) Communities 3,222,400 3,207,605 (14,795) Finance and Environment 4,401,560 3,883,697 (517,863) Net transfers to/(from) Reserves 696,200 1,068,528 372,328 Capital expenditure funded by Balances and Reserves 0 107,287 107,287 Reversal of Grants/Contributions 0 206,856 206,856 Below the line accounting transactions 182,880 (217,387) (400,267) Appropriation to Balances 833,180 739,080 (94,100) Slippage Items Carried Forward to 2014-15 0 179,855 179,855

Total 13,200,190 12,562,649 (637,541)

Table 1: General Fund Revenue Variances: Directorates

2.2It should be noted that both the budgets and actual outturns detailed above have been adjusted to remove the effects of accounting adjustments required at the end of the year, and therefore may not be directly comparable to figures provided in previous Budget Monitoring reports. However, these outturn figures do correspond to those included within the Explanatory Foreword to the Draft Statement of Accounts that will be considered by the Finance & Audit Committee at its meeting on 15 July 2014.

3. Explanation of significant variances to the Original Budget

3.1ALL DIRECTORATES

3.1.1 Employee Costs (favourable variance) – The policy of holding vacant posts empty and requiring Management Team approval to recruit continued during 2013-14 with a savings target for the year set at £350,000. Expenditure on payroll-related costs and vacancy data has been reported to Management Team monthly throughout the year. This has enabled decisions on recruitment and staffing to be closely examined and discussed and ensures that savings on this budget line are delivered. The actual net payroll-related savings achieved across the Council during the year was £512,400.

3.1.2 Running Expenses - Supplies and Services (favourable variance) – the Council has maintained robust control over purchasing activity. At the start of the year, all purchase orders were authorised by a Director or Assistant Director, though this control was passed to Service Managers following recommendations made in the report of the LGA Peer Review. Savings on expenditure relating to supplies and services totalled approximately £50,000 across all directorates in 2013-14.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget Monitoring Report 2013/14 (Out-turn)Report 145 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Gravesham

Search all
  1. Budget Monitoring Report 2013/14 (Out-turn)This decision
  2. 2026/27 Q1 Budget Monitoring (General Fund)Decided
  3. General Fund Budget Monitoring Report - Q2 2025/26Noted
  4. General Fund Budget Monitoring Report 2025/26 - Quarter TwoApproved
  5. General Fund Budget Monitoring Reports Q1Agreed
  6. General Fund Budget Monitoring - Q3 2023/24Approved

More from Gravesham Finance and Audit Committee

All decisions
MeetingDecisionOutcome
14 Jul 2026 The Audit Plan for Gravesham Borough Council - Year ending 21 March 2026It was agreed this be taken back to Grant Thornton to advise on how assurances could be provided for this asset. Asse... Agreed Open
25 Feb 2026 Statement of Accounts 2024/25 and Letter of RepresentationResolved that Members: considered the Statement of Accounts for 2024/25 and agreed that the Chair of the Finance and ... Agreed Open
25 Feb 2026 Review of Accounting Policies for 2025/26Resolved that Members endorsed the use of the Accounting Policies as outlined at Appendix One to this report, subject... Decided Open
25 Feb 2026 IA Charter ReviewResolved that Members approved the Charter presented at appendix two. Approved Open
25 Feb 2026 Internal Audit Plan 2026/27 (Q1-Q2)Resolved that Members approved the Internal Audit Plan 2026-27 (Q1-Q2) presented at appendix two. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies