Planning and Regeneration Cabinet Committee approved this item on Thursday 24 September 2015. Below is the council's own wording, with the papers it was decided on.
To adopt option 1 (apply tariff of £223.58 per dwelling for all planning applications which will result in net increase in dwellings within 6km of the SPA/ Ramsar site and for larger developments beyond 6km), both in the interim and once the formal strategic approach is in place, noting that this tariff can change over time. This may require the production of a Supplementary Planning Document on the issue, for adoption by the Council, once a formal approach is adopted; To support the setting up of formal partnership/governance arrangements, including a potential Project Board and Steering Group; To write to Medway Council to formally request their policy support for the strategic approach to mitigation in accordance with Natural England’s advice; To write to Dartford Borough Council to formally request their policy support for the strategic approach to mitigation in accordance with Natural England’s advice prior to confirming Dartford Borough Council’s role in any future formal governance of the strategic mitigation measures; To write to Ebbsfleet Development Corporation to formally invite them to join the North Kent Environmental Planning Group and to become a partner on any potential Project Board and Steering Group
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
Report to Planning and Regeneration Cabinet Committee
Classification: Public Key Decision: No
Gravesham Borough Council
Report to: Business Development + Planning and the Environment Cabinet Committee
Date: 24 September 2015
Reporting officer: Director (Housing and Regeneration)
Subject: North Kent Marshes – Biodiversity Issues, Future Management and Implications for Determining Planning Applications Purpose and summary of report: This report sets out information on the biodiversity interest of the North Kent Marshes and how this is being affected by new development. It outlines the Council’s legal responsibilities and sets out the work being taken forward to mitigate the impacts of new development, the need to produce a delivery mechanism and the implications for determining planning applications. It makes a number of recommendations in relation to implementing a strategic approach to mitigation, supporting the setting up of formal governance arrangements and contacting other local planning authorities and Ebbsfleet Development Corporation to clarify their support for the approach. Recommendations: That a decision be taken to adopt option 1 (apply a tariff of £223.58 per dwelling for all planning applications which will result in a net increase in dwellings within 6km of the SPA/Ramsar site and for larger developments beyond 6km), both in the interim and once the formal strategic approach is in place, noting that this tariff can change over time. This may require the production of a Supplementary Planning Document on the issue, for adoption by the Council, once a formal approach is adopted.
That a decision be taken to support the setting up of formal partnership/governance arrangements, including a potential Project Board and Steering Group.
That a decision be taken to write to Medway Council to formally request their policy support for the strategic approach to mitigation in accordance with Natural England’s advice.
That a decision be taken to write to Dartford Borough Council to formally request their policy support for the strategic approach to mitigation in accordance with Natural England’s advice prior to confirming Dartford Borough Council’s role in any future formal governance of the strategic mitigation measures.
That a decision be taken to write to Ebbsfleet Development Corporation to formally invite them to join the North Kent Environmental Planning Group and to become a partner on any potential Project Board and Steering Group. 1. Introduction
1.1This report sets out the biodiversity interest of the North Kent marshes and the Council’s legal responsibilities in relation to biodiversity. It outlines evidence which has been gathered in relation to the impact of new development on this biodiversity interest and potential mitigation measures to address this. It sets out the implications for planning policy and planning applications, including formal advice from Natural England. It then includes a section on moving forward which gives different options for implementing a strategic approach to mitigation, future governance arrangements and garnering the level of commitment to the approach from other local planning authorities and Ebbsfleet Development Corporation.
2. Biodiversity Interest of the North Kent Marshes
2.1Large parts of the marshes alongside the River Thames extending from the north east of Gravesend and into Medway Council’s area are of significant national and international biodiversity interest. This means that they are the biodiversity equivalent of World Heritage Sites such as Stonehenge and Canterbury Cathedral. The Thames Estuary and Marshes are designated as a Site of Special Scientific Interest, a Ramsar Site and a Special Protection Area, further details of which are given below. A map showing the areas of Gravesham affected by these designations is included as Appendix 2.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning and Regeneration Cabinet Committee at Gravesham and we tell you when its next papers are published, before the meeting rather than after it.
Review of Taxi Tariff for Gravesham1) Subject to the statutory advertising and consultation process; to replace the current two-tier taxi tariff structu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.