Gravesham Joint Transportation Board noted this item on Wednesday 14 March 2018. Below is the council's own wording, with the papers it was decided on.
Resolved that the Board noted the information contained within the report and agreed the following: · The Gravesham District Manager provide further details on the Lion Roundabout Developer Funded Works and look into speeding vehicles from Dering Way · The Gravesham District Manager look into the coordination of works (drainage and road resurfacing) in Forge Lane, Shorne . · The Gravesham District Manager to come back to the Board with further details about the Cyclopark works.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
Summary: This report updates Members on the identified schemes approved for construction in 2017/18
1. Introduction
This report provides an update and summarises schemes that have been programmed for delivery in 2017/18
Footway and Carriageway Improvement Schemes – see Appendix A
Drainage Repairs & Improvements – see Appendix B
Street Lighting – see Appendix C
Transportation and Safety Schemes – see Appendix D Casualty Reduction Measures Externally funded schemes Local Growth Fund
Developer Funded Works – see Appendix E
Bridge Works – see Appendix F
Traffic Systems – see Appendix G
Combined Member Fund – see Appendix H
Conclusion
1. This report is for Members information. Contact Officers:
The following contact officers can be contacted on 03000 418181
Carol Valentine Highway Manager West Kent Earl Bourner Gravesham District Manager Alan Casson Senior Asset Manager Katie Moreton Drainage & Structures Asset Manager Sue Kinsella Street Light Asset Manager Toby Butler Traffic & Network Solutions Asset Manager Jamie Hare Development Agreements Manager Emma Green Schemes Programme Manager Appendix A – Footway and Carriageway Improvement Schemes
The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.
Machine Resurfacing – Contact Officer [name removed] Name Parish Extent of Works Current Status
Programmed 5th Cobham Street Gravesend Full length March 2018 Ridgeway Ave to Hever Programmed 23rd Singlewell Road Gravesend Court Road April 2018 Wrotham Road A227 Wrotham Programmed 6th Gravesend Roundabout junction with Road Roundabout May 2018 Coldharbour Lane
Footway Improvement - Contact Officer [name removed] the junction with Works Lower Road to limit of Lower Road Gravesend commenced and Industrial units (Seacon). on-going. (Footway Reconstruction). Entire length. Court Lodge Shorne Completed (Footway Protection). From the junction with The Street to o/s the property Tanyard Hill Shorne Completed “Inis Coillte”. (Footway Protection). Entire length Albion Road Gravesend Completed (Footway Protection).
From junction of Bader Cherrywood Drive Northfleet Completed Walk to Mulberry Road From junction Old Road Abbey Road Gravesend East to junction Rochester Completed Road Glen View Gravesend Whole Length Completed
Programmed for Prospect Place Gravesend Whole Length the 12th March 2018 for 2 days A227 Wrotham M2 interchange to No. 301 Gravesend Completed Road Istead Rise. Milroy Ave to No. 1 Hardy Hardy Avenue Gravesend Avenue (Excluding junction Completed with Snelling Avenue) Inn on the Lane to Harts Hill Thong Lane Shorne Completed Nurseries From junction with Cob Programmed for The Street Shorne Drive to junction with Court the 12th March Lodge 2018 for 1 day From Henhurst Road to Programmed for Jeskyns Road Cobham Road over Pedestrian path the 15th March (Tunnel) 2018 for 1 day From Old Road West to Singlewell Road Gravesend Postponed Cross Lane West Programmed for Junction with Hall Road to Gywnn Road Northfleet the 13th March junction with Water Dales 2018 for 2 days
Surface Dressing
Waterlow Road Vigo Whole Length Completed
From junction with Harvel Dean Lane Meopham Street to junction Completed Strawberry Hill Full length between Chandlers Road Meopham Priestwood Road to Dean Completed lane Full length between Dean Strawberry Hill Meopham Lane and Leywood Road Completed
Batts Road Cobham Gold Street to Henley Road Completed Appendix B – Drainage
Drainage Works – Contact Officer Katie Moreton
Road Name Parish Description of Works Current Status
No drainage works planned over £5000
Appendix C – Street Lighting
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.