Development of the Corporate Risk Register 2022-2023

Decided Finance 4 papers

Finance and Audit Committee decided this item on Tuesday 8 March 2022. Below is the council's own wording, with the papers it was decided on.

Item148

Resolved

Resolved that Members are requested to review the draft Corporate Risk Register for 2022-23 prior to ... view the full minutes text for item 148.
Word for word from the decision Gravesham published for this meeting. Source: democracy.gravesham.gov.uk

Follow this further

Built from Gravesham's papers

What the report saysPro

Report to Finance and Audit Committee

Recommendations

1. Members are requested to review the draft Corporate Risk Register for 2022-23 prior to presentation to Cabinet.

Key Implications: Item Implications

Legal There is a specific risk within the Register, which highlights the potential issues associated with proposed legislative changes that may affect the council moving forward. Senior Management are being kept up to date with legislative change to ensure that they are able to be fully aware of potential changes proposed to assess how these may affect the council. Finance and Value for There are no financial or value for money implications arising from Money the Corporate Risk Register itself. ‘Ongoing financial viability of the Council’ is one of the key corporate risks identified within the Corporate Risk register and a specific update against this risk is included within appendix two. Corporate Plan The council’s arrangement to identify, assess and monitor strategic risks contribute to the delivery of Corporate Plan Objective #3: Progress: drive service improvement and corporate governance. Climate Change N/A 1. Introduction and Background

1.1Gravesham Borough Council pursues a forward-looking and dynamic approach to delivering services to the local community and in doing so, the council is exposed to risk both in terms of threats and loss of opportunities. The council recognises that risks are inevitable and in practice, cannot be entirely avoided. Resultantly, the council will tolerate a certain degree of risk when pursuing objectives, executing strategies and delivering services.

1.2Responsibility for risk management runs throughout the council and specific roles and responsibilities have been identified so that risk management is embedded in the culture of the council. Finance & Audit Committee have responsibility for monitoring the effective development and operation of risk management through:

 Reviewing any changes that have been made to the Risk Management Strategy, prior to presentation to Cabinet for approval.  Reviewing the annual Corporate Risk Register, prior to presentation to Cabinet for approval.  Considering progress made during the year, in managing or mitigating risks contained within the Corporate Risk Register.  Identifying potential risks for inclusion in the annual Corporate Risk Register.

2. Risk Management Strategy 2022-23

2.1The Risk Management Strategy sets out the approach that has been adopted by the council for identifying, evaluating, managing and recording risks to which it is exposed. The primary intention of the strategy is to ensure that risk management is embedded into the daily operations of the council. The strategy recognises that good risk management will lead to good management, good performance, good stewardship of public money, good public engagement and ultimately, good outcomes for citizens and service users.

2.2In March 2011, it was agreed by Cabinet that the Risk Management Strategy would be reviewed on an annual basis and, where necessary, presented to Cabinet for approval if it was subject to updates and amendments resulting in material changes to the strategy.

2.2.1 The Risk Management Strategy has been reviewed and there have been no substantial updates or amendments made to it. The strategy will therefore not be presented for approval but is appended to the report as Appendix 1 for information.

3. Desktop review of the corporate risk register

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2a. Appendix 1 Gravesham Borough Council Risk Management Strategy 2022-2023Appendix 243 KB Download
PDF
2b. Appendix 2 Risk Analysis DocumentAppendix 150 KB Download
PDF
2c. Appendix 3 Draft Corporate Risk Register 2022-2023Appendix 185 KB Download
PDF
Development of the Corporate Risk Register 2022-2023Report 132 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Gravesham

Search all
  1. Development of the Corporate Risk Register 2022-2023This decision
  2. Development of the Corporate Risk Register 2026-2027Approved
  3. Development of the Corporate Risk Register 2024-2025Approved
  4. Development of the Corporate Risk Register 2023-2024Approved
  5. Development of the Corporate Risk Register 2023-2024Approved
  6. Development of the Corporate Risk Register 2022-2023Decided

More from Gravesham Finance and Audit Committee

All decisions
MeetingDecisionOutcome
14 Jul 2026 The Audit Plan for Gravesham Borough Council - Year ending 21 March 2026It was agreed this be taken back to Grant Thornton to advise on how assurances could be provided for this asset. Asse... Agreed Open
25 Feb 2026 Statement of Accounts 2024/25 and Letter of RepresentationResolved that Members: considered the Statement of Accounts for 2024/25 and agreed that the Chair of the Finance and ... Agreed Open
25 Feb 2026 Review of Accounting Policies for 2025/26Resolved that Members endorsed the use of the Accounting Policies as outlined at Appendix One to this report, subject... Decided Open
25 Feb 2026 IA Charter ReviewResolved that Members approved the Charter presented at appendix two. Approved Open
25 Feb 2026 Internal Audit Plan 2026/27 (Q1-Q2)Resolved that Members approved the Internal Audit Plan 2026-27 (Q1-Q2) presented at appendix two. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies