20251233 - Land At Rose Farm Downs Road Istead Rise Gravesend Kent
AgreedPlanning4 papers
AI summaryGravesham Planning Committee delegates to the Head of Planning the issuing of two Listed Buildings Consents for St Andrews Arts Centre, Royal Pier Road, a Grade II listed building.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedSubject to conditions and informatives
MoneyNot stated
What happens nextHead of Planning to issue the consents. With conditions and informatives attached
Who it affectsSt Andrews Arts Centre, Royal Pier Road. A Grade II listed building
What was decided
The Head of Planning is given delegated authority to issue two Listed Buildings Consents, application references 20260658 and 20260659, and to impose conditions and informatives. Report 9.1
Application 20260658 is granted with five conditions covering the three-year time limit, approved plans, recording of historic fabric exposed on stage removal, specialist stained glass and door work, and prior approval of radiator samples and fixings. Report P2, P3, P7, P9, P11
Application 20260659 is granted with eight conditions covering the three-year time limit, approved plans, sample panels, fixing method details, panel material approval, reversible fixings, photographic recording of the ceiling, and ongoing maintenance of the acoustic panels. Report P13, P15, P18, P20, P22, P24, P25, P27
Why
The conditions are needed to protect the significance of the Grade II listed building, in line with Policies CS19 and CS20 of the Gravesham Local Plan Core Strategy (2014) and saved Policy TC2 of the Gravesham Local Plan First Review (1994). Report P8, P10, P12, P19, P21, P23, P24, P26, P27
The three-year commencement deadline follows Section 18 of the Planning (Listed Buildings and Conservation Areas) Act 1990. Report P3, P14
What happens next
The Head of Planning will issue the two Listed Buildings Consents with the agreed schedules of conditions and any informatives. Report 9.1
The approved works for each application must begin within three years of the consent being granted. Report P3, P14
Implications
Legal: Both consents must include a three-year time limit under Section 18 of the Planning (Listed Buildings and Conservation Areas) Act 1990. Report P3, P14
Other: Stained glass and external door works for application 20260658 must be carried out by accredited conservators using the Croudace method statement (ref L-04-26-Q). Report P9, P10
Other: Application 20260659 requires all fixings for the acoustic baffles to be fully reversible, with no fixings into moulded ceiling ribs, cornices or other historic decorative fabric. Report P20, P21, P24
Who and where
St Andrews Arts Centre, Royal Pier Road (a Grade II listed building) Report P8, P10, P12, P19, P21, P23, P24, P26, P27
Applicants and contractors carrying out the works Report P3, P14, P9, P18, P20
Timeline
2026-10-21: Planning Committee resolves to delegate the issuing of the two consents to the Head of Planning. Report 9.1
Within three years of the consent being granted: The approved development must begin. Report P3, P14
Plain English for the jargon
Listed Building Consent: Permission required from the council to carry out works that affect a listed building.
Delegated authority: The committee allows an officer, here the Head of Planning, to formally issue the decision and add conditions and informatives.
Grade II listed: A building of special interest, warranting protection under planning law.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item19c
Resolved
RESOLVED that the Head of Planning in consultation with the Chair and Vice Chair is given delegated authority to issue the planning permission subject to: - Imposition of planning conditions and informatives ; - Completion of a legal agreement under s106 of the Town and Country Planning Act 1990. The Head of Planning is given delegated authority to make changes to the wording of the Committee’s decision (such as to delete, vary or add conditions, informatives , planning obligations or reasons for the decision) prior to the decision being actioned, provided that the Head of Planning is satisfied that any such changes could not reasonably be regarded as deviating from the overall principle of the decision reached by the Committee nor that such change(s) could reasonably have led to a different decision having been reached by the Committee. In the event that the Section 106 Legal Agreement remains unsigned six months after this resolution, the application is to be reviewed by the Head of Planning, in consultation with the Chair of the Committee, and if no progress is being made, delegated authority is given to the Head of Planning to refuse the application in the absence of an agreed S106 Agreement.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
SUMMARY REPORT Application Ref: 20251233 Land At Rose Farm Downs Road Istead Rise Gravesend Kent Site Address: Outline planning application for the demolition of 64 Downs Road and Application erection of up to 154No. residential dwellings (including affordable Description: housing), with all matters reserved except for access. Creation of a new access from Downs Road. Applicant: Esquire Developments Ltd
Agent: Esquire Developments Ltd
Ward: Istead Rise, Cobham and Luddesdown Ward
Parish: -
Decision due date: 10.03.2026
Publicity expiry date: 06.02.2026
Decision Level: Planning Committee
Reason for referral: Discretion of Head of Planning and numerous Member call-ins. The Recommendations are that the Head of Planning in consultation with the Chair and Vice Chair is given delegated authority to issue the planning permission subject to:
Imposition of planning conditions and informatives; Completion of a legal agreement under s106 of the Town and Country Planning Act 1990;
That the Head of Planning is given delegated authority to make changes to the wording of the Committee’s decision (such as to delete, vary or add conditions, informatives, planning obligations or reasons for the decision) prior to the decision being actioned, Recommendation: provided that the Head of Planning is satisfied that any such changes could not reasonably be regarded as deviating from the overall principle of the decision reached by the Committee nor that such change(s) could reasonably have led to a different decision having been reached by the Committee.
In the event that the Section 106 Legal Agreement remains unsigned six months after this resolution, the application is to be reviewed by the Head of Planning, in consultation with the Chair of the Committee, and if no progress is being made, delegated authority is to be given to the Head of Planning to refuse the application in the absence of an agreed S106 Agreement.
_______________________________________________________________________________________________ Summary of Reasons for Recommendations
This report relates to an outline planning application for up to 154 dwellings, including 50% affordable housing, public open space, associated infrastructure and a new vehicular access from Downs Road, with all matters reserved except access.
The proposal has been assessed against the Development Plan, the National Planning Policy Framework (2026) and other material considerations. The Council is currently unable to demonstrate a five-year supply of deliverable housing land and is experiencing significant housing and affordable housing shortfalls. As a result, the presumption in favour of sustainable development applies, and substantial weight is attributed to the delivery of market and affordable housing. The scheme would contribute up to 154 dwellings, including up to 77 affordable homes, thereby assisting in meeting identified housing needs within the Borough.
The site lies within the Metropolitan Green Belt. However, it is considered that the proposal satisfies the requirements of NPPF Policy GB7 relating to development on Grey Belt land. The site is assessed as Grey Belt land, there is evidenced unmet housing need, the location is considered sufficiently sustainable when account is taken of the proposed mitigation measures, and the proposal complies with the Golden Rules through the provision of 50% affordable housing, infrastructure improvements and publicly accessible open space. The development is therefore not considered inappropriate development in Green Belt terms.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.