That the Committee agreed to carry out an investigation into the state of the London Underground, with the following terms of reference: · To explore the recent performance of the Tube and TfL’s progress with the upgrade ... view the full minutes text for item 7.
Word for word from the decision Greater London Authority published for this meeting.Source: meetings.london.gov.uk
1.1This report sets out a proposal for the Committee to undertake an investigation into the state of the London Underground.
2. Recommendation 2.1 That the Committee agrees to carry out an investigation into the state of the London Underground, with terms of reference as outlined at paragraph 4.15 of the report.
3. Background Overview of the proposed investigation
3.1The aim of this investigation would be to examine the recent performance of the Tube and progress with the programme to upgrade and maintain the Tube network with a view to identifying any actions that the Mayor and TfL should take to realise improvements. In recent months there has been a decline in the performance of the Tube and slippage with the upgrade programme.
3.2This investigation would follow on from the Committee’s past work on the London Underground. This includes various reports and meetings on the upgrade programme which started in 2002/3. The investigation would provide an opportunity for the Committee to reflect on the performance of the Tube eight years on from the start of this programme and roughly one year on from Transport for London (TfL) taking control of the entire programme. The Committee would identify what has been promised in relation to upgrading each London Underground line and what has been delivered to date.
3.3This investigation would not revisit in detail the Public Private Partnership (PPP) contracts which underpinned the upgrade programme until June 2010. Instead it would take as a starting point what was due to be delivered under the PPP contracts and then consider in detail TfL’s progress in delivering the upgrades since June 2010 and its plans for the future upgrade programme. This would include examining for each line: recent performance based on TfL information; progress with the upgrade; TfL’s expenditure on this work; and the implications for passengers in terms of disruption and closures. The Committee would make recommendations to the Mayor and TfL for
City Hall, The Queen’s Walk, London SE1 2AA Enquiries: 020 7983 4100 minicom: 020 7983 4458 www.london.gov.uk improvements on any or all these matters with a view to improving the performance of the Tube and the delivery of the upgrade programme.
3.4This investigation would take place in early summer 2011. The Committee would use its meetings in May and June 2011 to gather views and information before setting out its findings and recommendations in a report.
Background information on the London Underground
3.5TfL is responsible for the London Underground network which comprises 11 lines and 270 stations. This network is more than 140 years old and is the oldest underground system in the world. TfL took over responsibility for the Tube network from the government in 2003.
3.6Prior to TfL assuming control of the London Underground, the government adopted a PPP structure to secure investment in the Tube. Under the 30 year PPP contracts, three infrastructure companies (infracos) were responsible for the maintenance and renewal of London Underground's assets, ie its rolling stock, stations, tracks, tunnels and signals. Metronet was responsible for the infraco covering the Bakerloo, Central, Victoria and Waterloo & City lines and for the infraco covering the Circle, District, Hammersmith & City and Metropolitan (the ‘sub- surface’) lines. Tube Lines was the infraco covering the Jubilee, Northern and Piccadilly lines. The PPP contracts required the infracos to deliver a certain level of daily performance and upgrade the lines to increase capacity and improve capability in the long-term.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Transport Committee Work ProgrammeThat the Committee’s work programme , and the additional activity undertaken since its last meeting, namely the site ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.