(a) That the Mayor’s consultation on proposed revisions to the authorised borrowing limits for 2011-12, as set out in Appendix A of the report, be noted. (b) That authority be delegated to the Chairman of the ... view the full minutes text for item 10.
Word for word from the decision Greater London Authority published for this meeting.Source: meetings.london.gov.uk
1.1Under section 3 (3) of the Local Government Act the Mayor must consult with the London Assembly before amending the approved borrowing limits for the GLA’s functional bodies. The current limits for each functional body for 2011-12 were originally approved by the Mayor in March 2011 (Mayoral Decision 800) following consultation with the Assembly.
1.2The Budget and Performance Committee is now being consulted on proposed revisions to the authorised borrowing limits for 2011-12 - as set out in Appendix A – for Transport for London. This report invites the Committee to note the consultation and agree to delegate authority to the Chairman to respond by the deadline of 5pm on Wednesday 7 March 2012.
Recommendations
2.1That the Committee notes the Mayor’s consultation on proposed revisions to the authorised borrowing limits for 2011-12 - as set out in Appendix A and summarised below – for Transport for London: Authorised limit for 2011-12 to be increased by £326.0m to £7,848.6m Operational boundary for 2011-12 to be increased by £326.0m to £7,648.6m
2.2That the Committee delegates authority to the Chairman of the Committee to respond, in consultation with party Group Leads, to the Mayor’s consultation on these proposed amendments to the limits for borrowing by 5pm on Wednesday 7th March. The Mayor will then consider the response before considering whether to formally approve the revised limits for 2011-12.
Background
3.1The Mayor is required under Section 3 (2) of the Local Government Act 2003 (the ‚2003 Act‛) to set an Authorised Limit for external debt, which includes direct borrowing as well as other long-term liabilities, for the functional bodies and the GLA. Alongside these limits the Mayor is also required to City Hall, The Queen’s Walk, London SE1 2AA Enquiries: 020 7983 4100 minicom: 020 7983 4458 www.london.gov.uk approve the Prudential Indicators for the GLA and each functional body under the CIPFA Prudential Code. Under section 3 (3) of the 2003 Act he must consult with the Assembly before approving new limits or amending existing approvals. The Local Government (Capital Finance and Accounting) (England) Regulations 2003 require each functional body and the GLA to have regard to the CIPFA Prudential Code for Capital Finance in Local Authorities.
3.2The authorised limit referred to in this document is the statutory limit determined under section 3 of the 2003 Act. This is the expected maximum borrowing needed by each functional body with some headroom for unexpected developments such as unusual cash movements. The operational boundary for external debt referred to is based on the same estimates as the authorised limit. However it reflects an estimate of the most likely, prudent but not worst case scenario. It equates to the maximum level of external debt projected by the authority’s capital spending plan and excludes the headroom included within the authorised limit.
3.3The Assembly was consulted in December 2010 and February 2011 on the Mayor’s 2011-12 draft capital spending plan which included draft prudential indicators and proposed authorised borrowing limits to meet the requirements of the Local Government Act 2003. A summary of the final borrowing limits subsequently determined by the Mayor in Mayoral Decision 800 is provided in Appendix A to this report under the ‘Current Approved 2011-12’ columns for those functional bodies seeking amendments.
3.4The Mayor is now consulting the Assembly through the Budget and Performance Committee, and at the same time TfL on a revision to the limits in respect of TfL. The reasons for these proposed changes are set out in section 4. The Assembly was consulted separately in December 2010 on an amendment to the LFEPA limits for 2011-12.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Budget and Performance Committee at Greater London Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.