(a) That the terms of reference and scope of the investigation, as set out in Appendix 1 of the report, be noted; (b) That the report and discussion be noted; and (c) That it be noted that the site visit which was originally planned to take place on 3 July, will now take place on 2 July.
Word for word from the decision Greater London Authority published for this meeting.Source: meetings.london.gov.uk
Subject: Demolition and Refurbishment of London’s Social Housing Estates Report to: Housing Committee
Report of: Executive Director of Secretariat Date: 17 June 2014
This report will be considered in public
1. Summary 1.1 This report sets out the background information and context for the first part of the Committee’s investigation on this topic. This meeting will focus on the decision-making process applied to determine whether estates should be demolished and rebuilt or refurbished.
2. Recommendations 2.1 That the Committee agrees the terms of reference and scope of the investigation, as set out in Appendix 1 to this report.
2.2That the Committee notes the report as background to discussing with invited guests the key issues relating to decisions on demolition vs refurbishment.
3. Background 3.1 In February 2014 the Committee agreed to investigate the demolition and refurbishment of London’s social housing estates as its first topic for 2014/15. This is the first of two planned meetings on this topic. The Committee also intends to undertake a site visit which is expected to take place on 3 July 2014. The location for this visit remains to be confirmed but is likely to be either Clapham Park in Lambeth or the Market Estate in Islington.
3.2Just over half of all London’s council homes were built in the thirty years following World War Two,1 many of these on estates whose condition has deteriorated significantly over time. Recent years have seen a number of these estates being demolished to be replaced, commonly, by mixed-tenure developments. Exact data is hard to come by, but the London Development Database indicates that some 40,000 net units have been added through around 270 planning permissions on London’s demolished social housing estates in the last ten years.
3.3Such demolition programmes have divided opinion. The reasons advanced in favour either of demolishing and rebuilding or refurbishing depend on a wide range of factors, and the extent to which the range of factors are relevant will vary from estate to estate. There are arguments, for example, about the fabric of the buildings and the viability of refurbishment and about the cost 1 English Housing Survey data cited in Housing in London 2014, GLA City Hall, The Queen’s Walk, London SE1 2AA Enquiries: 020 7983 4100 minicom: 020 7983 4458 www.london.gov.uk benefit analysis in terms of the opportunity of building anew. For existing tenants, there are arguments about the disruption involved in moving at least once, compared with the inconvenience of refurbishment work, their own ongoing energy bills under either option, and, for many the most significant disadvantage, the fragmentation of existing communities including the permanent dispersal of some residents. For leaseholders, refurbishment might entail a one-off cost which they may or may not be happy and able to pay. Demolition would mean identifying another affordable comparable property within the area to which they can move. There are also environmental considerations; on the one hand, newer properties tend to be much more energy and carbon efficient than older properties, but evidence also exists involving more nuanced arguments around embodied carbon and emissions arising from demolition which indicate that basic forward energy and emissions calculations may be too simplistic.
3.4A scoping paper is attached as Appendix 1 to this report which outlines the intended shape of the investigation.
3.5The proposed Terms of Reference for the investigation are: To establish the criteria used to determine decisions, and clarify the decision-making process adopted, when social housing is considered for demolition or refurbishment To assess the comprehensiveness and robustness of the decision-making process To identify good practice in shaping decisions To scrutinise the role of the Mayor in supporting social housing refurbishment or regeneration and consider whether there is more he should do.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Action Taken Under Delegated AuthorityThat the action taken by the Chairman under delegated authority, in consultation with party Group Lead Members, be no...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies