Resolved
That: 1. The implementation of a Regional Control facility, as detailed in the report, based on four authorities progressing with the project, be endorsed. 2. The County Fire Officer and Chief Executive implement the appropriate governance and resourcing arrangements to deliver the project from within the approved budgets. 3. The Emergency Response Committee receive regular updates as the project proceeds. 4. The Clerk to the Authority be given delegated authority to expedite changes required for North West Fire Control Ltd, as detailed in the report, other than matters of principle.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.
Source: democracy.greatermanchester-ca.gov.uk