THE MAYOR'S CYCLING & WALKING CHALLENGE FUND (attached)
NotedCommittee1 paper
Greater Manchester Combined Authority noted this item on Friday 29 November 2019. Below is the council's own wording, with the papers it was decided on.
That the progress on the first five tranches previously granted Programme Entry for inclusion in the MCF be noted. 2. That the sixth tranche of cycling and walking schemes be approved for Programme Entry for inclusion in the MCF. 3. That the progress made in developing a prioritised list of schemes for development and delivery through the Mayor’s Challenge Fund, as the first phase of the Bee Network, be noted. 4. That it be noted that a pipeline of schemes was being develop, to strengthen further funding requests of Government.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
To provide an update on progress and to approve the sixth tranche of schemes for Programme Entry for the Mayor’s Cycling and Walking Challenge Fund (MCF).
Recommendations
Members are recommended to: (i) note the progress on the first five tranches previously granted Programme Entry for inclusion in the MCF; (ii) approve the sixth tranche of cycling and walking schemes to be granted Programme Entry for inclusion in the MCF; and (iii) note the progress made in developing a prioritised list of schemes for development and delivery through the Mayor’s Challenge Fund as the first phase of the Bee Network.
CONTACT OFFICERS:
Steve Warrener Director of Finance and 0161 244 1025 Corporate Services
Stephen Rhodes Customer Director 0161 244 1092
Simon Warburton Strategy Director 0161 244 1427 Risk Management – see paragraphs 3.2 and 3.9 Legal Considerations – N/A Financial Consequences – Revenue – N/A Financial Consequences – Capital – see paragraphs 3.7 - 3.9
Background papers
29 March 2018 – Transforming Cities Fund report to GMCA 25 May 2018 – Cycling & Walking Update 29 June 2018 – Transforming Cities Fund report to GMCA 27 July 2018 – Transforming Cities Fund report to GMCA 28 September 2018 – Mayor’s Cycling & Walking Challenge Fund 29 March 2019 – Mayor’s Cycling & Walking Challenge Fund 28 June 2019 – Mayor’s Cycling & Walking Challenge Fund
TRACKING/PROCESS Does this report relate to a major strategic decision, as set out in the No GMCA Constitution
EXEMPTION FROM CALL IN Are there any aspects in this report which No means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency? GM Transport Committee Overview & Scrutiny Committee N/A N/A
GMCA 20191129 The Mayor’s Cycling and Walking 2 25/11/2019 16:07 Challenge Fund Update Report v0.13 MAYOR’S CYCLING AND WALKING CHALLENGE FUND
1 INTRODUCTION
1.1On 29 March 2018, GMCA agreed to allocate £160 million of Greater Manchester’s £243 million Transforming Cities Fund to develop a Mayor’s Cycling and Walking Challenge Fund (MCF).
1.2The fund is being used to deliver the first phase of the Bee Network, which is the walking and cycling element of the Our Network plan to transform Greater Manchester’s transport system. The Bee Network, which, once complete, will cover circa 1,800 miles and be the longest, integrated, planned network in the country connecting every neighbourhood of Greater Manchester. The initial network plan was contained in Greater Manchester’s cycling and walking infrastructure proposal (adopted by GMCA in June 2018), as part of a GM Streets for All highways improvement programme.
1.3This paper recommends the approval of 25 additional schemes for programme entry taking the total number of schemes to 82 with a total value of £493 million which represents circa one third of the total estimated value of the Bee Network plan. The work completed to date shows the scale of ambition across all Greater Manchester Authorities; and highlights the need to secure additional funding from central government to deliver the full network.
2 TRANCHES 1-5 PROGRESS
2.1On 27 July, 28 September, 14 December 2018 and 29 March, 28 June 2019 GMCA approved Tranches 1 to 5 of the MCF fund for Programme Entry, comprising a total of 57 cycling and walking schemes with a current forecast total funding requirement from the MCF of £217.7 million. This figure excludes programme management costs and the GM Bike Hire, which is considered to be commercially sensitive.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Greater Manchester Combined Authority at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.