THE MAYOR'S CYCLING & WALKING CHALLENGE FUND (attached)

Noted Committee 1 paper

Greater Manchester Combined Authority noted this item on Friday 29 November 2019. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

That the progress on the first five tranches previously granted Programme Entry for inclusion in the MCF be noted. 2. That the sixth tranche of cycling and walking schemes be approved for Programme Entry for inclusion in the MCF. 3. That the progress made in developing a prioritised list of schemes for development and delivery through the Mayor’s Challenge Fund, as the first phase of the Bee Network, be noted. 4. That it be noted that a pipeline of schemes was being develop, to strengthen further funding requests of Government.
Word for word from the decision Greater Manchester Combined Authority published for this meeting. Source: democracy.greatermanchester-ca.gov.uk

Follow this further

Built from Greater Manchester Combined Authority's papers

What the report saysPro

Report to Greater Manchester Combined Authority

Purpose of report

To provide an update on progress and to approve the sixth tranche of schemes for Programme Entry for the Mayor’s Cycling and Walking Challenge Fund (MCF).

Recommendations

Members are recommended to: (i) note the progress on the first five tranches previously granted Programme Entry for inclusion in the MCF; (ii) approve the sixth tranche of cycling and walking schemes to be granted Programme Entry for inclusion in the MCF; and (iii) note the progress made in developing a prioritised list of schemes for development and delivery through the Mayor’s Challenge Fund as the first phase of the Bee Network.

CONTACT OFFICERS:

Steve Warrener Director of Finance and 0161 244 1025 Corporate Services

Stephen Rhodes Customer Director 0161 244 1092

Simon Warburton Strategy Director 0161 244 1427 Risk Management – see paragraphs 3.2 and 3.9 Legal Considerations – N/A Financial Consequences – Revenue – N/A Financial Consequences – Capital – see paragraphs 3.7 - 3.9

Background papers

 29 March 2018 – Transforming Cities Fund report to GMCA  25 May 2018 – Cycling & Walking Update  29 June 2018 – Transforming Cities Fund report to GMCA  27 July 2018 – Transforming Cities Fund report to GMCA  28 September 2018 – Mayor’s Cycling & Walking Challenge Fund  29 March 2019 – Mayor’s Cycling & Walking Challenge Fund  28 June 2019 – Mayor’s Cycling & Walking Challenge Fund

TRACKING/PROCESS Does this report relate to a major strategic decision, as set out in the No GMCA Constitution

EXEMPTION FROM CALL IN Are there any aspects in this report which No means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency? GM Transport Committee Overview & Scrutiny Committee N/A N/A

GMCA 20191129 The Mayor’s Cycling and Walking 2 25/11/2019 16:07 Challenge Fund Update Report v0.13 MAYOR’S CYCLING AND WALKING CHALLENGE FUND

1 INTRODUCTION

1.1On 29 March 2018, GMCA agreed to allocate £160 million of Greater Manchester’s £243 million Transforming Cities Fund to develop a Mayor’s Cycling and Walking Challenge Fund (MCF).

1.2The fund is being used to deliver the first phase of the Bee Network, which is the walking and cycling element of the Our Network plan to transform Greater Manchester’s transport system. The Bee Network, which, once complete, will cover circa 1,800 miles and be the longest, integrated, planned network in the country connecting every neighbourhood of Greater Manchester. The initial network plan was contained in Greater Manchester’s cycling and walking infrastructure proposal (adopted by GMCA in June 2018), as part of a GM Streets for All highways improvement programme.

1.3This paper recommends the approval of 25 additional schemes for programme entry taking the total number of schemes to 82 with a total value of £493 million which represents circa one third of the total estimated value of the Bee Network plan. The work completed to date shows the scale of ambition across all Greater Manchester Authorities; and highlights the need to secure additional funding from central government to deliver the full network.

2 TRANCHES 1-5 PROGRESS

2.1On 27 July, 28 September, 14 December 2018 and 29 March, 28 June 2019 GMCA approved Tranches 1 to 5 of the MCF fund for Programme Entry, comprising a total of 57 cycling and walking schemes with a current forecast total funding requirement from the MCF of £217.7 million. This figure excludes programme management costs and the GM Bike Hire, which is considered to be commercially sensitive.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
THE MAYOR'S CYCLING & WALKING CHALLENGE FUND (attached)Report 668 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 15 attended
GM
GM Mayor Andy BurnhamChair, present
DG
Councillor David GreenhalghCommittee Member, present
SW
Sylvia WelshOfficer (Full Permission), present
DJ
Councillor David JonesCommittee Member, apologies
BW
Councillor Brenda WarringtonVice-Chair, present
RL
Councillor Richard LeeseVice-Chair, present
DM
Deputy Mayor Beverley HughesCommittee Member, present
SF
Councillor Sean FieldingCommittee Member, present
AB
Councillor Allen BrettCommittee Member, present
CM
City Mayor Paul DennettCommittee Member, present
AW
Councillor Andrew WesternCommittee Member, present
DM
Councillor David MolyneuxCommittee Member, present

All 15 on the meeting page

On this subject at Greater Manchester Combined Authority

Search all
  1. THE MAYOR'S CYCLING & WALKING CHALLENGE FUND (attached)This decision
  2. Mayors Cycling and Walking Challenge FundApproved
  3. Mayor's Cycling and Walking Challenge FundApproved
  4. Mayor's Cycling and Walking Challenge FundApproved
  5. The Mayor's Cycling and Walking Challenge Fund and Side Road Zebra StudyApproved
  6. The Mayor's Cycling and Walking Challenge Fund and Active Travel FundApproved

More from Greater Manchester Combined Authority Greater Manchester Combined Authority

All decisions
MeetingDecisionOutcome
25 Sep 2026 ApologiesThat apologies be received from Councillor Eleanor Wills (Tameside), with Councillor Andrew Mclaren attending as subs... Decided Open
25 Sep 2026 Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities... Decided Open
25 Sep 2026 Declarations of InterestThat it be noted that no declarations of interest were received. Noted Open
25 Sep 2026 GMCA Minutes - 10 July 2026That the minutes of the GMCA meeting held on 10 July 2026 be approved. Approved Open
25 Sep 2026 Bee Network Committee - 25 June 2026That the proceedings of the Bee Network Committee held on 25 June 2026 be noted. Noted Open