Greater Manchester Transport Committee noted this item on Friday 21 February 2020. Below is the council's own wording, with the papers it was decided on.
That the Transport Network Performance Report be noted. 2. That TfGM would review the Manchester Community Transport offer where appropriate as part of the re-tendering process. 3. That relevant Members be kept informed of transition arrangements related to Manchester Community Transport within their wards; and 4. That officers be asked to respond directly to Councillor Steve Adshead regarding reliability issues with new trains replacing discontinued Pacer train services.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
This report provides an overview of Transport Network Performance in Greater Manchester for December 2019.
Recommendations
Members are asked to note the contents of the report.
CONTACT OFFICERS:
Alex Cropper Interim Head of Operations 0161 244 1122 [email removed]
Julie Flanagan COO Sponsor and 0161 244 1164 Support Officer [email removed] Risk Management – not applicable Legal Considerations – not applicable Financial Consequences – Revenue – not applicable Financial Consequences – Capital – not applicable
Number of attachments included in the report: 2
o Appendix A: Glossary o Appendix B: Metrolink Performance
BACKGROUND PAPERS: Nil
TRACKING/PROCESS Does this report relate to a major strategic decision, as set out in the No GMCA Constitution
EXEMPTION FROM CALL IN Are there any aspects in this report which None means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency? GMTC Overview & Scrutiny Committee Not applicable Not applicable
1.1The Greater Manchester Transport Committee has a key role to oversee the provision of transport services including the performance of Metrolink, Bus and Rail Operators and the Strategic Highways Network on behalf of residents, businesses and visitors. The Committee also oversees the move towards the Our Network vision for an integrated transport network for Greater Manchester, as set out in the 2040 Transport Strategy.
1.2This network performance report covers performance across all transport modes in Greater Manchester during December 2019.
2 OVERALL NETWORK PERFORMANCE SUMMARY
2.1There were increased delays on the highway network throughout early December due to seasonal effects of the weather, reduced daylight hours and changes in travel behaviour associated with the approaching festive season. During December term time traffic volumes in and around the regional centre were on average 4% above typical levels.
2.2The impact that seasonal changes in travel behaviour have on the highway network are evident in the traffic count data. While volumes during the AM peak on Fridays were up to 11% below the term time average, it is noted that they were up to 11% above typical on weekdays during the inter-peak and 18% above typical during the PM peak. In addition, weekend traffic volumes were consistently above average peaking at 16% above typical term time levels. Between Christmas and New Year traffic volumes during the AM peak were half the typical.
2.3The disruption to the operational capacity of the network during a period of increased demand for travel has had a detrimental effect on journey times and journey time reliability. Bus performance has shown a downward trend, reflecting the effects on the highway network. This again improved at the end of December when volumes reduced.
2.4Metrolink performance improved in terms of both punctuality and operated mileage in the period. A detailed quarterly report on Metrolink is submitted separately. GMTC 20200221 Transport Network Performance v0.4 3 13/02/2020 15:30 2.5 Both PPM and On-time performance for Northern and TPE have declined significantly period-on-period and compared to the corresponding period in 2018/19. The week of the December timetable change was the worst performance since the May 2018 timetable change. This mirrors national train operator performance, although nationally, declines have been less pronounced.
3 NETWORK OVERVIEW
Events
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Greater Manchester Transport Committee at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the Sub Committee MeetingsThat the minutes of the Metrolink & Rail Sub Committee held on 3 March 2023 be noted. 2. That the minutes of the Bus ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.