Stockport Mayoral Development Corporation (MDC) Delivery Plan 2020-2025
ApprovedCommittee2 papers
Greater Manchester Combined Authority approved this item on Friday 26 June 2020. Below is the council's own wording, with the papers it was decided on.
That the Stockport Town Centre West Mayoral Development Corporation’s Strategic Business Plan May 2020 – March 2025 be approved. 2. That the Stockport Town Centre West Mayoral Development Corporation’s Action Plan May 2020 – March 2021 be approved. 3. That it be noted that The Stockport Mayoral Development Corporation model has the potential to be replicated in other GM areas, and all Local Authorities were invited to share in further the details of the scheme if they so wish.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
To seek approval from the GMCA of the Stockport Town Centre West Mayoral Development Corporation’s Strategic Business Plan 2020-2025 and the Annual Action Plan which sets out more detail on the commercially sensitive activities the MDC will undertake over the course of 2020 / 2021 to deliver the objectives in the full plan. The Annual Action Plan is included in confidential Appendix B of this report.
Recommendations
The GMCA is requested to:
1. To approve the Stockport Town Centre West Mayoral Development Corporation’s Strategic Business Plan May 2020 – March 2025 (Appendix A).
2. To approve the Stockport Town Centre West Mayoral Development Corporation’s Action Plan May 2020 – March 2021 (Appendix B)
CONTACT OFFICERS:
Simon Nokes, Executive Director of Policy & Strategy - Simon.nokes@greatermanchester- ca.gov.uk Anne Morgan, Head of Planning Strategy [email protected]
Equalities Implications – [see paragraphs 3.1 to 3.4] Climate Change Impact Assessment and Mitigation Measures – [see paragraphs 3.1 to 3.4 Risk Management – [see paragraphs 1.2 to 1.5] Legal Considerations – [see paragraph 1.3] Financial Consequences – [Revenue – see paragraphs 1.2 to 1.7] Financial Consequences – [Capital – see paragraph 1.2 to 1.7] Number of attachments included in the report – 2
Comments/recommendations from Overview & Scrutiny Committee
The Business Plan and the Annual Action plan was considered by the GMCA Economy Business Growth and Skills Overview and Scrutiny Committee on the 12 June 2020. Generally members were very supportive and welcomed it as a very positive plan and it was recommended that the Business Plan should be kept under review as we understand more about the implications of Covid. Any amended business plan would be submitted to the CA for approval in line with the oversight and accountability arrangements for the Mayoral Development Corporation.
Background papers
The Stockport Town Centre West Mayoral Development Corporation’s Strategic Business Plan May 2020 – March 2025 (Appendix A)
The Stockport Town Centre West Mayoral Development Corporation’s Action Plan May 2020 – March 2021 (Appendix B)
Town Centre Challenge Report to GMCA on 26 January 2018
Town Centre Challenge Report to GMCA on 28 September 2018
Stockport Council Cabinet Report on the Creation of a Mayoral Development Corporation in Stockport’s Town Centre West – December 18 2018
Stockport Mayoral Development Corporation Report to the Joint AGMA/GMCA Board on 11 January 2019 Town Centre Challenge: Stockport Mayoral Development Corporation to the GMCA on 29 March 2019
Stockport Council Report to the Corporate, Resource Management & Governance Scrutiny Committee on the 6 August 2019
The Stockport Town Centre West Mayoral Development Corporation (Establishment) Order 2019 (S.I. 2019/1040)
Stockport Mayoral Development Corporation Delivery Plan 2019 - 2020
Greater Manchester Economy, Business Growth and Skills Overview and Scrutiny Committee 12 June 2020
TRACKING/PROCESS Does this report relate to a major strategic decision, as set out in the Yes GMCA Constitution EXEMPTION FROM CALL IN Are there any aspects in this report which N/A means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency? TfGM Overview & Scrutiny Committee N/A 12/06/20 1. BACKGROUND
1.1On 28 September 2018 the GMCA agreed to support, in principle, the creation of a Mayoral Development Corporation (Corporation) in Stockport to help secure the regeneration of the Town Centre West area of Stockport. This agreement in principle was subject to further work being undertaken by Stockport Council in relation to the proposals.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Greater Manchester Combined Authority at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.