That the progress made in developing a set of Mayor’s Cycling and Walking Fund delivery priorities across GM and the agreement of a prioritise d first phase for the programme be noted. 2. That £ 0.6 million Mayor’s Cycling and Walking funding for the Wigan Smithy Brook Road scheme, in order to secure full approval and enable the signing of a delivery agreement, be approved. 3. That the addition to the 2020/21 Capital Programme of £1.9 million of costs, to be funded from the capital grant of £1.9 million that forms part of the £3.2 million of Emergency Active Travel (Tranche 1) funding, as set out in section 3 of the report, be approved.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
To note and approve the funding requirements set out in the following report, in order to ensure the continued delivery of the Mayor’s Cycling and Walking Challenge Fund programme.
Recommendations
The GMCA is requested to:
1. To note the progress made in developing a set of MCF delivery priorities across GM and the agreement of a prioritised first phase for the programme; and
2. Approve £0.6 million MCF funding for the Wigan Smithy Brook Road scheme in order to secure full approval and enable the signing of a delivery agreement; and
3. Approve the addition to the 2020/21 Capital Programme of £1.9 million of costs to be funded from the capital grant of £1.9 million that forms part of the £3.2 million of Emergency Active Travel (Tranche 1) funding, as set out in section 3 of this report. CONTACT OFFICERS:
Steve Warrener Director of Finance and 0161 244 1025 Corporate Services
Richard Nickson Cycling and Walking 0161 244 0987 Programme Director
Simon Warburton Strategy Director 0161 244 1427
Equalities Implications: The Bee Network and the infrastructure which will enable it, will be fully inclusive in its design and development, with the proactive involvement of organisations such as the Disability Design Reference Group (DDRG).
Climate Change Impact Assessment and Mitigation Measures: The Mayor’s Cycling and Walking Challenge Fund programme has been designed to support and expedite delivery of a network which is designed to facilitate a switch from a mechanised mode to walking or cycling, which will see a reduction in both local pollutants and greenhouse gases. By 2040 130,000 daily trips are expected to switch to cycling and walking from private car and taxi use. This equates to around 735,000 less vehicle kilometres being driven per day, with the resultant environmental benefits.
Risk Management: The recommendations of this report will directly support MCF scheme delivery and enable prioritised infrastructure spend. This will directly assist in mitigating the programme risk of not fully expending the available budget. A programme risk register is maintained and updated by the TfGM MCF programme team.
Legal Considerations: Legal Delivery Agreements and legal side-letters will be produced and implemented for full scheme and development cost approvals as appropriate.
Financial Consequences – Revenue: Not applicable
Financial Consequences – Capital: Financial consequences are set out in paragraphs 2.2 -2.5 Number of attachments to the report: No attachments.
Background papers
29 March 2018 – Transforming Cities Fund report to GMCA 25 May 2018 – Cycling & Walking Update 29 June 2018 – Transforming Cities Fund report to GMCA 27 July 2018 – Transforming Cities Fund report to GMCA 28 September 2018 – Mayor’s Cycling & Walking Challenge Fund 29 March 2019 – Mayor’s Cycling & Walking Challenge Fund 28 June 2019 – Mayor’s Cycling & Walking Challenge Fund 29 November 2019 - Mayor’s Cycling & Walking Challenge Fund 5 May 2020 - Mayor’s Cycling & Walking Challenge Fund
TRACKING/PROCESS Does this report relate to a major strategic decision, as set out in the No GMCA Constitution
EXEMPTION FROM CALL IN Are there any aspects in this report which No exemption means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency? GM Transport Committee Overview & Scrutiny Committee [Date considered at GM [Date considered by the Transport Cttee if appropriate] relevant Overview & Scrutiny Committee] 1. INTRODUCTION
1.1On 29 March 2018, GMCA agreed to allocate £160 million of Greater Manchester’s £243 million Transforming Cities Fund to develop a Mayor’s Cycling and Walking Challenge Fund (MCF).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Greater Manchester Combined Authority at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.