Local Growth Deal (1, 2 and 3) - Six Monthly Progress Update and Expenditure Approvals
NotedCommittee1 paper
Greater Manchester Combined Authority noted this item on Friday 25 September 2020. Below is the council's own wording, with the papers it was decided on.
That the good progress made in relation to the Growth Deal Transport Major Schemes programme be noted. That the good progress made in relation to the Growth Deal Transport Minor Works and Additional Priorities programmes be noted. That the good progress made in relation to the Non Transport Skills Capital and Economic Development & Regeneration (ED &R) programmes be noted. That the payment of grants of £1.819 million to Bolton in relation to the delivery of the SBNI Bolton Delivery Package 5 Phase 3 scheme be approved. That the expenditure approvals for phased delivery of the remaining SBNI 2020/21 works not exceeding £6.036 million be approved, subject to agreed Growth Deal governance. That the expenditure approval for delivery of the first phase of the Oldham Town Centre Regeneration 2020/21 works, not exceeding £1.355 million be approved, subject to agreed Growth Deal governance.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
The purpose of this report is to provide the Combined Authority with an overview of progress on the delivery of the Local Growth Deal (LGF) Programme (Tranches 1, 2 and 3) and to seek expenditure approvals for phased elements of the SBNI and Oldham Town Centre Regeneration delivery programmes, to ensure full Growth Deal grant spend by March 2021.
Recommendations
The GMCA is requested to:
1. Note the good progress made in relation to the Growth Deal Transport Major Schemes programme as set out in Sections 3 and 4 of this report.
2. Note the good progress made in relation to the Growth Deal Transport Minor Works and Additional Priorities programmes as set out in Section 6 of this report.
3. Note the good progress made in relation to the Non Transport Skills Capital and Economic Development & Regeneration (ED &R) programmes as set out in Section 8 of this report.
4. Note and agree payment of grants of £1.819 million to Bolton in relation to the delivery of the SBNI Bolton Delivery Package 5 Phase 3 scheme as set out in Section 7 of this report.
5. Agree the expenditure approvals for phased delivery of the remaining SBNI 2020/21 works not exceeding £6.036 million, as set out in Section 7 of this report, subject to agreed Growth Deal governance. 6. Agree the expenditure approval for delivery of the first phase of the Oldham Town Centre Regeneration 2020/21 works, not exceeding £1.355 million, as set out in Section 7 of this report, subject to agreed Growth Deal governance.
Phil Havenhand [phone removed] [email removed] BACKGROUND PAPERS:
None.
TRACKING/PROCESS Does this report relate to a major strategic decision, as set out in the Yes GMCA Constitution
EXEMPTION FROM CALL IN Are there any aspects in this report which N/A means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency? GM Transport Committee Overview & Scrutiny Committee N/A N/A Equalities Implications: The Growth Deal Transport programme is managed in line with current legislation and assessments are carried out by the promoters of each scheme.
Climate Change Impact Assessment and Mitigation Measures:
The Growth Deal Transport programme objectives are to introduce measures to enable economic growth within Greater Manchester. The programme contains measures to enable growth to be accommodated through improvements to the public transport network and to encourage increases in active travel.
Risk Management: Risk management considerations are referred in paragraphs 5.2 and 5.3 of the report.
Legal Considerations: Legal Considerations are referenced in paragraphs 5.2 and 5.3 of the report.
Financial Consequences – Revenue: Financial Consequences – Revenue, are referenced in paragraphs 5.1, 5.2, 5.3 and 5.4 of the report.
Financial Consequences – Capital: Financial Consequences – Capital, are referenced in paragraphs 5.1, 5.2, 5.3 and 5.4 of the report. Number of attachments to the report: None
Comments/recommendations from Overview & Scrutiny Committee N/A 1 EXECUTIVE SUMMARY
1.1This report sets out progress made on the Growth Deal programme over the last six months, seeks expenditure approvals for the SBNI and Oldham Town Centre Regeneration schemes, and notes that Government has now released in full the remaining third of GM’s 2020/21 Growth Deal allocation (£25.9 million) following on from the contractual commitments made on a number of major schemes as a result of approvals granted at the 31 July 2020 GMCA meeting.
2. INTRODUCTION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Greater Manchester Combined Authority at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.