GM Brownfield Housing Fund ("BHF") Tranche 1 Spend Allocation
ApprovedCommittee1 paper
Greater Manchester Combined Authority approved this item on Friday 30 October 2020. Below is the council's own wording, with the papers it was decided on.
That the allocation of grant funding, to those sites set out within Appendix A of the report, be approved. 2. That the progress of the work on the development of criteria for the prioritisation f or the second tranche (“Tranche 2”) of funding based on a Place Based Assessment where all eligible schemes will again be considered for 2021 spend and beyond be noted. 3. That it be noted that the work was aligned to wider GM policy objectives and the ‘Build Back Better’ areas of focus. 4. That the proposal for the GMCA entering into individual Grant Agreements for the Brownfield Housing Fund associated with the recommended sites be approved. 5. That authority be delegated to the GMCA Treasurer, acting in conjunction with the GMCA Monitoring Officer, to agree the final terms of all the necessary agreements.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
This report seeks the Greater Manchester Combined Authority’s approval to allocate grant funding to those sites recommended within this report and subsequently enter into individual Grant Agreements with the respective parties.
Recommendations
The GMCA is requested to:
1. Approve GMCA to allocate grant funding to those sites set out within Appendix A;
2. Approve GMCA entering into individual Grant Agreements for the BHF associated with the recommended sites; and
3. Delegate authority to the GMCA Treasurer acting in conjunction with the GMCA Monitoring Officer to agree the final terms of all the necessary agreements.
CONTACT OFFICERS:
Andrew McIntosh: [email protected] Neil Waddington: [email protected] Equalities Implications: The Brownfield Housing Fund is aimed at unlocking stalled, brownfield sites across GM. Sites which have been recommended to receive grant funding within this paper represent sites across each of the GM Districts. Housing which will be delivered as a result of the grant funding will align with those specific housing needs and priorities for that District and as a result will not have any adverse implications from an equality perspective.
Climate Change Impact Assessment and Mitigation Measures:
As part of the emerging prioritisation approach for “Tranche 2” of the BHF, the aspirations of the carbon neutral agenda will be addressed.
Risk Management: The grants will be conditional upon a satisfactory outcome of due diligence and ongoing monitoring confirmation that the schemes are being delivered satisfactorily. In view of the nature of the MHCLG grant funding agreements for BHF and the likely approach that any conditions will be mirrored in agreements between the GMCA and scheme promoters, there will be limited risk retained by the GMCA.
Legal Considerations: A detailed grant agreement and other associated legal documentation will be completed for each scheme ahead of the first grant payment. State Aid will be considered further for each individual scheme allocation with any allocation being state aid compliant.
Financial Consequences – Revenue: Any revenue costs are anticipated to be absorbed into the existing Delivery Team budget or subsequent revenue allocation (circa £1.94m) to be confirmed from MHCLG.
Financial Consequences – Capital: Capital expenditure is provided by the £81.1m Brownfield Housing Fund. Once received from MHCLG the funds will be distributed to sites based on a prioritisation process and there are therefore no capital consequences for the GMCA. The first annual block grant payment is anticipated to be made at the end October/early November 2020. Monitoring and reporting assurance will form part of the existing Single Pot Assurance Framework. The GMCA Accounting Officer will be required to confirm that investment is being used for the purposes agreed under the respective fund to deliver to fund’s objectives.
Number of attachments to the report: 0 Comments/recommendations from Overview & Scrutiny Committee None. BACKGROUND PAPERS:
None.
TRACKING/PROCESS Does this report relate to a major strategic decision, as set out in the Yes GMCA Constitution
EXEMPTION FROM CALL IN Are there any aspects in this report which No means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency? GM Transport Committee Overview & Scrutiny Committee N/A 8th October 2020 1. INTRODUCTION/BACKGROUND
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Greater Manchester Combined Authority at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.