That the changes to the commercial network set out in Annex A be noted; That it be agreed that no action be taken in respect of changes or de-registered commercial services set out in Annex A; That the action taken in respect of the service change set out in Annex B be noted. That the proposed changes to general subsidised services set out in Annex C be agreed. That further statistical information be provided to Councillor Kevin Peel (Bury Council), in respect of the proposal to terminate service route 66 at Prestwich, Longfield Centre.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
i. To inform Members of the changes that have taken place to the bus network since the last Bus Services Sub Committee meeting and report on action taken or proposed by Transport for Greater Manchester; and ii. To seek guidance from Members on the actions proposed by Transport for Greater Manchester.
Recommendations
Members are asked to:
1. note and comment as appropriate on changes to the commercial network set out in Annex A; 2. agree that no action is taken in respect of changes or de-registered commercial services set out in Annex A; 3. note the action taken in respect of the service change set out in Annex B; and 4. agree the proposed changes to general subsidised services set out in Annex C.
CONTACT OFFICERS:
Stephen Rhodes Customer Director & Interim Head of Bus Services, TfGM [email removed]
Nick Roberts Head of Services & Commercial Development, TfGM [email removed] Equalities Implications – n/a
Climate Change Impact Assessment and Mitigation Measures – n/a
Risk Management – n/a
Legal Considerations – n/a
Financial Consequences – Revenue – see paragraph 2 and Part B report
Financial Consequences – Capital – n/a
Number of attachments included in the report: main report only
Comments/recommendations from Overview & Scrutiny Committee – n/a
Background papers
Forthcoming Changes to the Bus Network report to the Greater Manchester Transport Committee, Bus Services Sub -Committee – 12th March 2021.
TRACKING/PROCESS Does this report relate to a major strategic decision, as set out in No the GMCA Constitution?
EXEMPTION FROM CALL IN Are there any aspects in this report which n/a means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency? GM Transport Committee Overview & Scrutiny Committee n/a n/a 1. INTRODUCTION/BACKGROUND 1.1. The Bus Services Sub Committee of the Greater Manchester Transport Committee considers all matters relating to the operation and service performance of the bus network in Greater Manchester, including commercially registered and subsidised services; Demand Responsive Services, bus stations and bus stops; passenger information services; contract monitoring; vehicle standards; and passenger safety for the subsidised bus network. 1.2. Acting under delegated authority, the Sub Committee is tasked to review closely and approve all proposed changes to the subsidised bus network and ensure that the cost of the subsidised general services is kept within the appropriate budget or any cash limits. This is achieved through:- rationalisation of existing services whilst maintaining key links on the network; engaging with operators with the objective of them taking on “marginal commercial” services; and
continuing to redesign and restructure grouped services to ensure that maximum value is obtained from subsidy.
1.3In general, withdrawals, reductions or amendments to services are currently only planned at the date of next renewal of the contract concerned and proposed changes will be reported to this Sub Committee. 1.4. The governance process that leads up to the reporting to the Bus Services Sub Committee involves the scrutiny of all tendered services at TfGM’s Tender Panel that consists of representatives from Legal, Procurement and Finance as well as TfGM’s Bus Services team. 2. 2021/22 BUDGET SUMMARY 2.1 The summary below provides the current position on the 2021/22 Subsidised Bus Services budget for the three months to 30th June 2021. 2.2 Net expenditure on Subsidised Services is £0.3m lower than budget in the year to date. It should be noted that considerable risk remains around future income (including continued government support) and cost.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Greater Manchester Transport Committee at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the Sub Committee MeetingsThat the minutes of the Metrolink & Rail Sub Committee held on 3 March 2023 be noted. 2. That the minutes of the Bus ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.