That authority be delegated to the GMCA Treasurer and Greater Manchester Digital Portfolio Lead Chief Executive to enter into contract between GMCA and Cisco International for Greater Manchester One Network Integrator Services on behalf of the GMCA including GM Fire & Rescue and TFGM, and Bury, Stockport, Oldham and Rochdale Councils, as described in the report. 2. That authority be delegated to the GMCA Treasurer and Greater Manchester Digital Portfolio Lead Chief Executive to procure and enter into contracts to deliver BT Openreach Exchange Services and for ServiceNow capabilities as described in this report. 3. That authority be delegated to the GMCA Monitoring Officer for GMCA to enter into the Greater Manchester One Network Collaboration Agreement with TFGM and Bury, Stockport, Oldham and Rochdale Councils and to review and complete all necessary legal documentation and commend to those organisations that they sign their respective Collaboration Agreements. 4. That £5.67M of expenditure over 10 years against existing and planned GMCA Wide Area Networking budgets for GMCA(FRS) connectivity via Greater Manchester One Network be approved. 5. That an investment of £9.546M for Wide Area Networking services, implementation and operation for GMCA / TFGM Urban Traffic Controls Signals and TFGM sites via Greater Manchester One Network to be funded from existing TfGM revenue budget of £4.890m and additional capital and revenue investment of £4.656m in line with the decision made by GMCA in January 2020, be approved. 6. That it be noted that this collaborative procurement had secured substantial value for money and social value commitments and creates a platform for future connectivity requirements. 7. That the progress towards completion of the Greater Manchester Local Full Network Programme and the efforts of officers and commercial partners in its delivery be noted.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
This report sets out the process for a joint procurement of ICT Wide Area Network services across several councils, GMCA including GMFRS and Transport for Greater Manchester under the title of GM One Network.
Recommendations
GMCA is requested to:
Approve delegated authority to the GMCA Treasurer and GM Digital Portfolio Lead Chief Executive to enter into contract between GMCA and Cisco International for GM One Network Integrator Services on behalf of the GMCA including GM Fire & Rescue and TFGM, and Bury, Stockport, Oldham and Rochdale Councils as described in this report.
Approve delegated authority for the GMCA Treasurer and GM Digital Portfolio Lead Chief Executive to procure and enter into contracts to deliver BT Openreach Exchange Services and for ServiceNow capabilities as described in this report.
Approve delegated authority to the GMCA Monitoring officer for GMCA to enter into the GM One Network Collaboration Agreement with TFGM and Bury, Stockport, Oldham and Rochdale Councils and to review and complete all necessary legal documentation and commend to those organisations that they sign their respective Collaboration Agreements.
Approve £5.67M of expenditure over 10 years against existing and planned GMCA Wide Area Networking budgets for GMCA(FRS) connectivity via GM One Network.
Approve investment of £9.546M for Wide Area Networking services, implementation and operation for GMCA / TFGM Urban Traffic Controls Signals and TFGM sites via GM One Network to be funded from existing TfGM revenue budget of £4.890m and additional capital and revenue investment of £4.656m in line with the decision made by GMCA in January 2020.
Note that this collaborative procurement has secured substantial value for money and social value commitments and creates a platform for future connectivity requirements.
Note the progress towards completion of the GM Local Full Network Programme and the efforts of officers and commercial partners in its delivery.
2 Equalities Impact, Carbon and Sustainability Assessment:
Impacts Questionnaire Impact Indicator Result Justification/Mitigation Equality and Inclusion The Service will improve digital connectivity and resilience for relevant services and Health G organisations. The Service will improve digital connectivity and resilience for relevant services and Resilience and organisations. G Adaptation The Service will improve digital connectivity and resilience for relevant services and organisations. Housing The Service will create a globally significant set of digital capabilities. Economy G The Service will create a globally significant set of digital capabilities. The Service will "light" much of the GM Local Full Fibre Network in a scalable manner. The Service will upgrade equipment and connectivity in GM Urban Traffic Control Signals Mobility and The Service will improve digital connectivity and resilience for relevant services and G Connectivity organisations. This Service provides scalable and resilience Wide Area Network capabilities The Service will upgrade equipment and connectivity in GM Urban Traffic Control Signals Carbon, Nature and This Service will provide equipment and capabilities that are more energy efficient than at G Environment present. Consumption and Production
Contribution to achieving the GM Carbon Neutral 2038 target
Further Assessment(s): Carbon Assessment Positive impacts overall, Mix of positive and Mostly negative, with at whether long or short negative impacts. Trade- least one positive aspect. Negative impacts overall. term. offs to consider. Trade-offs to consider.
Risk management
See section 10
Legal Considerations:
See sections 3, 7, 8 and 9
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Greater Manchester Combined Authority at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.